United States v. Southern Contracting of Charleston, Inc.

862 F. Supp. 107, 27 U.C.C. Rep. Serv. 2d (West) 114, 1994 U.S. Dist. LEXIS 12682, 1994 WL 483844
CourtDistrict Court, D. South Carolina
DecidedSeptember 1, 1994
DocketCiv. A. 2:93-2495-18
StatusPublished
Cited by7 cases

This text of 862 F. Supp. 107 (United States v. Southern Contracting of Charleston, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Southern Contracting of Charleston, Inc., 862 F. Supp. 107, 27 U.C.C. Rep. Serv. 2d (West) 114, 1994 U.S. Dist. LEXIS 12682, 1994 WL 483844 (D.S.C. 1994).

Opinion

ORDER

NORTON, District Judge.

This matter is before the court on Plaintiffs Motion for Summary Judgment.

I. BACKGROUND

On September 24, 1991, the Air Force awarded Defendant Southern Contracting of Charleston, Inc. (SoCon) a contract to replace an existing incinerator at the Charleston Air Force Base. SoCon contracted with Plaintiff Laura M. Conroy for the construction and installation of a new incinerator, which was known as “Burney” the Burner. Defendant Fireman’s Fund Insurance Company served as a surety for SoCon on the project.

Taking the facts in the light most favorable to SoCon (the nonmoving party), Conroy caused delays in the incinerator project from the outset. For example, the intended completion date for the project was March 16, 1992; however, Conroy did not begin manufacture of Burney until May 18, 1992, two months beyond the original completion date. The subcontract required Conroy to design and submit blueprints that would comply with Air Force plans and specifications, but the Air Force rejected Conroy’s submittals on three occasions.

As a consequence of these delays, SoCon was unable to complete its contract on time. The Air Force assessed liquidated damages against SoCon, and SoCon incurred substantial overhead expenses and consequential damages due to these delays.

Upon delivery of Burney on August 10, 1992, SoCon discovered several defects. The specifications called for the incinerator to be painted with heat resistant paint, but Burney was shipped to the site with only a coat of primer on it. Burney’s refractory was defective. Upon attempting to assemble Burney, SoCon discovered the pieces would not fit together properly due to irregularities in the refractory between Burney’s primary and secondary chambers. SoCon notified Plaintiffs representative at the site, Tyler Troupe, of this problem. With Conroy’s consent, So-Con retained a technician to grind down the refractory so Burney could be assembled.

The subcontract required Conroy to provided “field service technician” to be on site “in an advisory capacity to ensure proper operation of the system during testing____ Failure to have an incinerator manufacturer’s field service technician on site during performance testing will void the performance guarantee.” Specifications for Project BKFX91-1087. The parties’ interpretation of the duties of the field service technician under this provision varied. The field ser *109 vice technician himself testified that he was required to do nothing at the project site and was there mainly to pick up the check for the final payment owed to Conroy by SoCon.

SoCon encountered problems regarding Burney’s electronic control box. The computer logic for the electronic control system for the computer was flawed, preventing Burney from operating properly in automatic mode. SoCon’s president, an electrical engineer, substantially revised and edited the computer logic for Conroy’s program to make the automatic mode function properly.

Due to these problems, SoCon, in lieu of sending final payment to Conroy, sent an invoice which listed SoCon’s damages that flowed from Conroy’s alleged breach of contract. These damages included the costs for extended overhead; liquidated damages assessed by the Government; and the cost of labor and materials incurred in making Burney operate properly in conformity with government specifications. The net result was a balance due to SoCon in excess of $65,000.

On September 22, 1993, Conroy filed suit against SoCon seeking payment of the balance of the subcontract price' ($29,150.84). SoCon asserted as defenses that Conroy had materially breached the subcontract and failed to perform a condition precedent. So-Con also counterclaimed for breach of contract and breach of warranty.

Plaintiff now seeks summary judgment on its cause of action for payment of the contract price and on SoCon’s causes of action for breach of contract and breach of warranty-

II. ANALYSIS

To grant a motion for summary judgment, this court must find “that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(e). In evaluating a motion for summary judgment, this court must view the record in the light most favorable to the nonmoving party. Perini Corp. v. Perini Constr., Inc., 915 F.2d 121, 123-23 (4th Cir.1990). The judge is not to weigh the evidence himself but rather to determine if there is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 2510-11, 91 L.Ed.2d 202 (1986).

A Applicability of Article 2 of the Uniform Commercial Code

As a preliminary matter, this court must address the applicability of Article 2 of the UCC, as codified in Title 36 of the South Carolina Code, to this transaction. SoCon claims Article 2 is not applicable, because this transaction involves a mix of goods and services and the “services required of Plaintiff were far greater than incidental to Plaintiffs performance under the contract.” Def.’s Mem.Opp’n Summ.J. at 11. Conroy contends that the transaction is primarily for the sale of a good.

This court agrees that this transportation involves a hybrid contract, calling for the delivery of goods and the provision of services. However, it may nevertheless be a “contract for the sale of goods” within the scope of § 36-2-201(1). In considering whether a hybrid contract is one “for the sale of goods” under the UCC, courts generally employ the “predominant thrust” or “predominant factor” test. See Ranger Constr. Co. v. Dixie Floor Co., 433 F.Supp. 442 (D.S.C.1977). Under this test, courts evaluate transactions to determine if “their predominant factor, their thrust, their purpose, reasonably stated, is the rendition of service, with goods incidentally involved (e.g., contract with artist for painting) or is a transaction of sale, with labor incidentally involved (e.g., installation of a water heater in a bathroom).” Bonebrake v. Cox, 499 F.2d 951, 960 (8th Cir.1974).

While it is true that Conroy was required to design blueprints, submit plans to the Air Force for approval, obtain Department of Health and Environmental Control approval, and perform various other steps before manufacturing and delivering the incinerator, these services were not the primary thrust of the contract. The primary purpose is evidenced in an August 5,1991 proposal sent by Conroy to SoCon stating: “Please consider our quote to. supply ‘Burney’ the Burner Incinerator in compliance with data sheets titled ‘Construction Specifications’: $93,- *110 325.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lessin v. Ford Motor Company
S.D. California, 2021
Flores v. FCA US LLC
E.D. Michigan, 2021
Sloan v. Gen. Motors LLC
287 F. Supp. 3d 840 (N.D. California, 2018)
Peavey Electronics Corp. v. Baan U.S.A., Inc.
10 So. 3d 945 (Court of Appeals of Mississippi, 2009)
Trident Const. Co., Inc. v. Austin Co.
272 F. Supp. 2d 566 (D. South Carolina, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
862 F. Supp. 107, 27 U.C.C. Rep. Serv. 2d (West) 114, 1994 U.S. Dist. LEXIS 12682, 1994 WL 483844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-southern-contracting-of-charleston-inc-scd-1994.