Southeastern Steel Co. v. W. A. Hunt Construction Co.

390 S.E.2d 475, 301 S.C. 140, 12 U.C.C. Rep. Serv. 2d (West) 103, 1990 S.C. App. LEXIS 29
CourtCourt of Appeals of South Carolina
DecidedFebruary 26, 1990
Docket1466
StatusPublished
Cited by7 cases

This text of 390 S.E.2d 475 (Southeastern Steel Co. v. W. A. Hunt Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeastern Steel Co. v. W. A. Hunt Construction Co., 390 S.E.2d 475, 301 S.C. 140, 12 U.C.C. Rep. Serv. 2d (West) 103, 1990 S.C. App. LEXIS 29 (S.C. Ct. App. 1990).

Opinion

Sanders, Chief Judge:

This case arises under Section 2-607(3)(a) of the Uniform *141 Commercial Code. Respondent Southeastern Steel Company and appellant W.A. Hunt Construction Company, Inc. entered into a contract, by the terms of which Southeastern Steel agreed to supply certain goods, consisting of steel and steel products, to be used by Hunt in connection with two construction projects. Southeastern Steel supplied the goods and thereafter sued Hunt, alleging an amount due under the contract. Hunt stipulated the amount allegedly due but pleaded it was entitled to a set-off because of “the unworkmanlike performance of Southeastern Steel.” Summary judgment was granted for Southeastern Steel in the amount stipulated. The case then proceeded to trial on the issue of whether Hunt was entitled to a set-off. At the close of the evidence, the trial judge directed a verdict for Southeastern Steel on the ground that Hunt had not given it the notice required by Section 2-607(3)(a). We affirm.

I

In reviewing a decision to grant a motion for a directed verdict, we determine whether a verdict for the party opposing the motion would be reasonably possible under the facts. We view the evidence in the light most favorable to the opposing party, and we give that party the benefit of all reasonable inferences. We cannot, however, ignore facts unfavorable to the party opposing the motion. Haulbrooks v. Overton, 295 S.C. 380, 368 S.E. (2d) 676 (Ct. App. 1988). Viewed in the light most favorable to Hunt, the evidence can be fairly summarized as follows.

W. A. Hunt, the president of Hunt, testified his company had numerous problems with the steel and steel products. He testified that they contained defects and that this resulted in delays. He testified he told Southeastern Steel about the problems. He acknowledged that Southeastern Steel made efforts to correct the defects, and that the corrected goods were ultimately used in the construction projects, but he testified that Hunt was nevertheless damaged. He testified that he and other Hunt employees corrected some of the defects at their expense and that Hunt was penalized for being late in completing one of the projects. He testified as to the amount of the alleged damages.

*142 Mr. Hunt acknowledged that he met with the president of Southeastern Steel to discuss the balance due on the account. He admitted that, after adjusting for an error, “the balance of the account, approximately $10,000, was legitimate.” He also admitted he did not “attempt at that time, to resolve any of these claims for set-offs back against the faulty work.” (Hunt does not dispute the conclusion of the trial judge that “Mr. Hunt presented no evidence that [Hunt] notified [Southeastern] of any back charges for [its] shortcomings in the performance relative to the delivery of steel and steel products [to either of the construction projects].”)

The president of Southeastern Steel testified that, during the meeting with Mr. Hunt, he specifically asked “if there were any other problems or anything else [which] needed to be taken care of [and that] Mr. Hunt never responded to any back charges or any charges whatsoever he made against the company.” He further testified that he did not learn of the alleged damages or the claim for a set-off until his attorney took the deposition of Mr. Hunt. His testimony on both points was uncontradicted by Mr. Hunt or any other witness.

II

The dispositive issue in this case is whether Hunt gave Southeastern Steel the notice required by Section 2-607(3)(a).

Section 2-607(3)(a) provides, in part, as follows:

(3) Where a tender has been accepted
(a) the buyer must within a reasonable time after he discovers or should have discovered any breach notify the seller of breach or be barred from any remedy____

Section 36-2-607(3)(a), Code of Laws of South Carolina, 1976.

The trial judge ruled: “[Since Hunt] did not within a reasonable time after [it] discovered the breaches in perfor *143 manee notify [Southeastern Steel] of such breaches, [Hunt] is barred from any remedy.” 1

Section 2-607(3)(a) does not prescribe any form for the required notice. The absence of specific guidelines has forced courts to develop standards for determining what constitutes adequate notice. Some courts have held that almost any complaint will satisfy the requirement. E.g., Oregon Lumber Co. v. Dwyer Overseas Timber Products Co., 280 Or. 437, 571 P. (2d) 884 (1977). 2 The standard adopted by these courts is known as “the lenient standard of notification.” Other courts require the buyer to notify the seller that the buyer considers the seller to be legally in breach. E.g., Eastern Airlines v. McDonnell Douglas Corp., 532 F. (2d) 957 (5th Cir. 1976). 3 The standard adopted by these courts is known as “the strict standard of notification.”

Oregon Lumber illustrates the application of the lenient standard. There, the buyer bought timber of a particular grade from the seller. On several occasions, the buyer informed the seller that the lumber was below grade. However, the buyer continued to accept deliveries of the timber and made several payments before refusing to pay the balance due under the contract. The Court ruled the early *144 complaints of the buyer met the notice requirement of Section 2-607(3)(a). The Court held: “The notice may be given in any manner or form sufficient to appraise the seller that there are problems with the transaction.” Oregon Lumber, 280 Or. at 442, 571 P. (2d) at 887. The Court further held that, when the buyer notifies the seller of a problem with the transaction, the buyer need not assert the “intention to make a claim for damages or pursue any other remedy.” Id.

Eastern Airlines is the leading case adopting the strict standard. There, the buyer purchased aircraft from the seller for delivery in set intervals. The seller fell behind in the deliveries. The buyer at first indicated that it considered the seller to be in breach, but it thereafter indicated by its behavior that it was willing to accept late deliveries. The Court held: “The purpose of the notice is to advise the seller that he must meet a claim for damages.” Eastern Airlines, 532 F. (2d) at 972. The Court reasoned that, by indicating its willingness to accept late deliveries, the buyer may have lead the seller to believe it did not intend to take legal action. The Court held that Section 2-607(3)(a) requires the buyer to inform the seller that “the transaction is claimed to involve a breach.” Id. at 978.

The strict standard appears to be the majority view. See T.J. Stevenson & Co. Inc. v. 81,193 Bags of Flour, 629 F. (2d) 338, 360 (5th Cir. 1980) (“The Eastern Air Lines

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doll v. Ford Motor Co.
814 F. Supp. 2d 526 (D. Maryland, 2011)
Hitachi Electronic v. Platinum Technologies
Court of Appeals of South Carolina, 2003
Plantation Shutter Co., Inc. v. Ezell
492 S.E.2d 404 (Court of Appeals of South Carolina, 1997)
United States v. Southern Contracting of Charleston, Inc.
862 F. Supp. 107 (D. South Carolina, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
390 S.E.2d 475, 301 S.C. 140, 12 U.C.C. Rep. Serv. 2d (West) 103, 1990 S.C. App. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeastern-steel-co-v-w-a-hunt-construction-co-scctapp-1990.