United States v. Peerless Casualty Company

255 F.2d 137
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 21, 1958
Docket15852
StatusPublished
Cited by18 cases

This text of 255 F.2d 137 (United States v. Peerless Casualty Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Peerless Casualty Company, 255 F.2d 137 (8th Cir. 1958).

Opinion

255 F.2d 137

UNITED STATES of America, for the Use and Benefit of HOPPER
BROS. QUARRIES, a partnership, Appellant,
v.
PEERLESS CASUALTY COMPANY, a Corporation, and Bill Curphy
Company, a Corporation, Appellees.

No. 15852.

United States Court of Appeals Eighth Circuit.

April 28, 1958, Rehearing Denied May 21, 1958.

Herman Ginsburg, Lincoln, Neb. (Hymen Rosenberg, Joseph Ginsburg, Lincoln, Neb., and Elmer F. Witte, Pawnee City, Neb., on the brief), for appellant.

John H. Neiman of Neiman, Neiman & Stone, Des Moines, Iowa (Robert A. Barlow of Healey, Davis, Wilson & Barlow, Lincoln, Neb., on the brief), for appellees.

Before SANBORN, WOODROUGH, and VOGEL, Circuit Judges.

WOODROUGH, Circuit Judge.

This action was brought under the Miller Act, 40 U.S.C.A. 270a(a)(1, 2) and 270b(a), against the prime contractor for surfacing levees in the Omaha Levee System, and its payment bondsman to recover $10,000.02 due and owing the use plaintiff (referred to as plaintiff) on account of 6,014.2 tons of crushed rock supplied by it to the subcontractor, Leonard M. McDonald, d/b/a Omaha Rock and Excavating Company, and used on the work. The plaintiff was entitled to recover in the action if it had met the requirements of section 270b in respect to giving notice ot the prime contractor within ninety days from June 16, 1953, when the last of the material was supplied. The District Court decided on the trial without a jury that the notice relied on by plaintiff was insufficient and dismissed the action on that ground. The plaintiff appeals.

Statement

It appears that the contract between the prime contractor and the sub-contractor called for the latter to furnish some 10,300 tons of the rock and that he purchased 6,014.2 tons of it from plaintiff. It was used on the work between May 19, 1953 and June 16, 1953, the agreed price and value being $10000.02. On June 16, 1953, thirty days after the last material was received on the work, the contractor settled with the subcontractor and paid him in full for all sums due him under his contract without inquiring of him whether he had paid for the material he used on the work. The plaintiff attempted without success to obtain payment from the subcontractor who was subsequently adjudged bankrupt with nothing for general creditors. On August 6, 1953, 51 days after plaintiff's last delivery of the material, plaintiff wrote, signed and mailed the following letter to the prime contractor:

'Hopper Bros. Quarries

Lime and Rock Products

Phone 2581

Pawnee City, Nebraska

August 6, 1953

'Bill Curphy Contracting Co.;

Des Moines, Iowa.

'Attention Mr. Curphy

'We Hopper Brothers furnished Omaha Rock Ex. Co. 60142 Tons of rock in the months of May and June, for The Corps of Engineers, Omaha Levee Surfacing No. 1 Levee Project, with you Mr. Curphy the Prime Contractor.

'We are unable to collect for this rock, will you give us information as to why this bill is not paid?

'Truly yours, Raymond Hopper, Hoppers Brothers.'

The actual amount of the rock furnished was 6,014.2 tons and the omission of the decimal point in the letter was as a result of a misprint or error.

In reply to the above letter, the contractor wrote plaintiff:

'Bill Curphy Co.

Contractors . . . 447 Insurance Exchange Building Des Moines 9, Iowa Telephone 8-0194 'August 7, 1953

'Attention: Raymond Hopper

'Gentlemen:

'After receiving your letter this morning we called Mr. McDonald of Omaha Rock & Excavating Co. regarding your unpaid bill for rock placed on the Omaha Levee for which we had the prime contract.

'He stated that there is some disagreement over the rejection of some 500 tons of rock but that if you would come in and talk to him he would be glad to settle with you. He said that he had talked to you by telephone several times but that you were reluctant to discuss the adjustment for the rejected rock. We are not familiar with the dispute but would suggest that you drop in to see him and try to work out a settlement to your mutual satisfaction.

'He has been notified that unless he settles with you immediately the matter will be turned over to his bonding company.

'Very truly yours, Bill Curphy Co. Glen Lange (s) Glen Lange Assistant Secretary

'cc: Anton, Hammond

Dunn, Inc.'

Anton, Hammond, Dunn, Inc., of Des Moines, Iowa, referred to in the lower left hand corner of the above letter, as having a copy of the letter sent to it, is the agent which wrote the payment bond sued on for the defendant Peerless Casualty Company and countersigned the same. It also wrote the contractor's performance bond furnished by the same casualty company and both a payment and a performance bond of the Merchants Mutual Bonding Company given by the subcontractor, McDonald, to the prime contractor.

Raymond Hopper, one of the partners of plaintiff, testified that on August 8, 1953, while the witness was at the rock quarries he received a telephone call from a party who stated that he was a representative of the bonding company. The following Tuesday the witness received another long distance telephone call from the same party. On Monday, August 10th, following the first telephone call, the witness went to Omaha and contacted Mr. McDonald, the sub-contractor; and in the second call which the witness received on Tuesday, the party calling made reference to the conversation which the witness had had with Mr. McDonald on the Monday precedng. The party calling on Tuesday wanted to know how the witness had come out when he talked to McDonald, and the witness told this party that he had agreed to deduct $600.00 from the amount due, and to settle for $10,000.00 which was to have been paid that day. McDonald did not pay then, but agreed to pay within a week or ten days; and the witness so reported to the person calling him over the telephone. This party then told the witness that if the witness did not receive the money shortly, the witness should let him know. This conversation occurred on August 11, after the witness had talked to Mr. McDonald on August 10th. The party with whom the witness talked on August 11 had the same voice as the party who had called the witness the preceding Saturday, August 8th. The call came from Des Moines.

When the call was made to the witness on August 8th, the party calling wanted to know if the witness had received any payment on the rock which he had delivered, and the witness told him that he had not, and the party then wanted to know why. The witness told the party inquiring that he did not know why, but that he would go to Omaha on Monday and look up McDonald and find out what had happened.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dysart Corporation v. Seaboard Surety, No. 525433 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1727 (Connecticut Superior Court, 1995)
Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)
School District No. 91, Bonneville County v. Taysom
495 P.2d 5 (Idaho Supreme Court, 1972)
Liles Construction Co. v. United States
415 F.2d 889 (Fifth Circuit, 1969)
Liles Construction Company, Inc. v. United States
415 F.2d 889 (Fifth Circuit, 1969)
Seldon v. S & S AGGREGATES COMPANY
441 S.W.2d 950 (Court of Appeals of Texas, 1969)
United States ex rel. Brown Bros. Grading Co. v. F. D. Rich Co.
285 F. Supp. 572 (D. South Carolina, 1968)
Russell v. Travelers Indemnity Co.
244 F. Supp. 419 (W.D. Missouri, 1965)
Woods Construction Co. v. Pool Construction Co.
348 F.2d 687 (Tenth Circuit, 1965)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
McWaters & Bartlett v. United States
272 F.2d 291 (Tenth Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
255 F.2d 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-peerless-casualty-company-ca8-1958.