Seldon v. S & S AGGREGATES COMPANY

441 S.W.2d 950, 1969 Tex. App. LEXIS 2236
Court of Appeals of Texas·Decided May 2, 1969·No. 4290·Published·Cited by 4 cases

Opinion

GRISSOM, Chief Justice.

In February 1965, W. J. Seldon was the general contractor for a state highway project in Dawson County. W. N. Fulfer was his subcontractor for construction of a highway between Lamesa and the Martin County line. S & S Aggregates Company leased a rock crusher to Fulfer for use on said project. The lease recited that the leased machinery was to be used on Texas State Highway Project F638(12) and F1018(6) in Dawson County. Fulfer used the rock crusher in the performance of his *952 contract. Fulfer did not pay the rent for the rock crusher and S & S Aggregates Company sued Seldon, the General Contractor, and Fidelity and Deposit Company of Maryland, the surety on his payment bond, for the unpaid rent. Plaintiff’s cause of action is based on the right granted one renting construction equipment “used in the direct prosecution of the work at the project site, or reasonably required and delivered for such use” by Article 5160, subd. C(b) (3).

In February 1968, the court rendered a partial summary judgment denying plaintiff recovery of rent for certain periods and also attorney’s fees. In June 1968, the court rendered judgment for the plaintiff, on a jury verdict, for rent from July 9th to September 29th, 1965, for $6,666.66 against Seldon and said surety. The judgment contained a recital that the court had theretofore rendered a partial summary judgment to the effect that plaintiff could not recover the rent for May 9th to June 9th and June 9th to July 9th and attorney’s fees. From the portion of the judgment against them Seldon and his surety have appealed.

Appellants’ principal contention is that the leased equipment was not “used on the project site”, that is, it was not placed on the road which they were building; that the crusher was used only at the Stewart rock quarry, about eight miles from the road, and therefore plaintiff was not entitled to recover rent from the general contractor and his surety. The Stewart pit, where the rock crusher was operated by Fulfer, was eight miles from the road which was being constructed. From this fact appellants conclude that rock crusher was not “used on the project site” and therefore appellee’s claim was not within the requirements of Article 5160 for creation of a cause of action for rent of construction equipment used in prosecution of public works. Appellants say the road that was being built was the project site and only when the rock crusher was used while on that road could the lessee have a cause of action for rent under Article 5160, subd. C(b) (3). Appellants also say, and as to this we think correctly, that before Article 5160 was amended in 1959 one renting equipment to a subcontractor for use on a project site could not recover his rent from the general contractor or the surety on his payment bond. From all of this appellants conclude that, since said amendment created such a cause of action, a lessor must show strict compliance with its terms, because it is in derogation of the common law. In support thereof they cite Mingus v. Wadley, 115 Tex. 551, 285 S.W. 1084; Trinity Road & Bridge Co., Inc., v. Watson, Tex.Civ.App., 341 S.W.2d 956, and the recent Supreme Court decision in New Amsterdam Casualty Company v. Texas Industries, Inc., 414 S.W.2d 914.

We disagree with appellants’ contention that the burden was upon the plaintiff to strictly comply with the statute. Article 5160 subd. C(b) (3) gives to one renting to a subcontractor construction equipment “used in the direct prosecution of the work at the project site, or reasonably required and delivered for such use” a cause of action against his general contractor and the surety on the general contractor’s payment bond for unpaid rent. Article 5160 is known as the McGregor Act. It was evidently patterned after the Miller Act, 40 U.S.C.A. Sections 270a and 270b. Said statutes were intended to give causes of action against such a contractor and surety under contracts for construction of public works, state and federal, where the one furnishing labor, or material, or renting equipment could not have a lien on the thing built because it was a public work project, such as the state highway in this case, and to provide a simple, direct way for collection of their debts. Contrary to appellants’ contention, Article 5160, as amended in 1959, is highly remedial in nature and clearly reflects the intention to change the public policy of Texas and provide a simple, direct method of giving notice and perfecting the claims of laborers, materialmen, and those renting equipment used in constructing public works. United Benefit *953 Fire Insurance Company v. Metropolitan Plumbing Company, Tex.Civ.App., 363 S. W.2d 843, 847; United States for Use and Benefit of Hopper Bros. Quarries v. Peerless Casualty Company, 8 Cir., 255 F.2d 137, 142; United States for Use and Benefit of J. P. Byrne & Co. v. Fire Association of Philadelphia, 2 Cir., 260 F.2d 541, 544; United States Fidelity and Guaranty Company v. Parker Brothers & Co., Inc., Tex.Civ.App., 437 S.W.2d 880, 881; Moran Towing Corporation v. M. A. Gammino Construction Company, 1 Cir., 363 F.2d 108, 115.

Free access — add to your briefcase to read the full text and ask questions with AI

Seldon v. S & S AGGREGATES COMPANY, 441 S.W.2d 950, 1969 Tex. App. LEXIS 2236 (Tex. Ct. App. 1969).

441 S.W.2d 950 (Seldon v. S & S AGGREGATES COMPANY) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Poth Corp. v. Marble Falls Independent School District
673 S.W.2d 648 (Court of Appeals of Texas, 1984)
Trucker's, Inc. v. South Texas Construction Co.
561 S.W.2d 855 (Court of Appeals of Texas, 1977)
Hastings v. American General Insurance Co.
547 S.W.2d 360 (Court of Appeals of Texas, 1977)