United States of America, for the Use and Benefit of Interstate Mechanical Contractors, Inc. v. International Fidelity Insurance Company

200 F.3d 456, 2000 U.S. App. LEXIS 526, 2000 WL 21033
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 14, 2000
Docket96-6013
StatusPublished
Cited by9 cases

This text of 200 F.3d 456 (United States of America, for the Use and Benefit of Interstate Mechanical Contractors, Inc. v. International Fidelity Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Interstate Mechanical Contractors, Inc. v. International Fidelity Insurance Company, 200 F.3d 456, 2000 U.S. App. LEXIS 526, 2000 WL 21033 (6th Cir. 2000).

Opinions

OPINION

DAVID W. McKEAGUE, District Judge.

Plaintiff Interstate Mechanical Contractors, Inc. (“Interstate”), a subcontractor, commenced this action under the Miller [458]*458Act, 40 U.S.C. § 270a et seq. Interstate seeks to recover against a payment bond issued by the defendant International Fidelity Insurance Co. (“Fidelity”), as surety for the prime contractor, Parmeco, Inc. (“Parmeco”). On cross-motions for summary judgment, the magistrate judge held that Interstate’s complaint was not filed within the Miller Act’s one-year statute of limitations period and granted summary judgment in favor of Fidelity. This appeal followed, and, for the reasons set forth below, we AFFIRM the judgment of the magistrate judge.

I

In November 1993 Interstate contracted with Parmeco to provide and install heating, ventilating, and air-conditioning systems at a U.S. Department of Commerce facility located in Morristown, Tennessee. Pursuant to § 270a of the Miller Act, Parmeco, as principal, posted a bond to guarantee payment under the contract with Fidelity as surety.

Under part 3.2 of the contract, Interstate agreed to install electric duct heaters, to coordinate the heaters’ installation with other work, and to “[test] operate installed duct heaters to demonstrate compliance with requirements.” Interstate further agreed to have substantially completed its work on the construction project by January 21, 1994, and to have finally completed all work by February 8, 1994. In fact, Interstate completed its construction in early June 1994, having installed two electric duct heaters as part of the heating, ventilating, and air-conditioning system. On June 17, 1994, after having been notified that construction was complete, the government took beneficial occupancy of the facility.

In late September or early October 1994, Sam Neeley, the subcontractor hired by Interstate to conduct testing of the system, noticed a discrepancy as he prepared his final reports. The numbers reported to him by his employees when they performed initial tests of the system did not satisfy the contract’s requirements. Assuming that his employees had inaccurately performed the tests, Neeley went to the facility to inspect the system. He discovered that the two electric heaters installed into the ducts did not meet the contract’s specifications. Although the heaters were the right size, fit properly into the ducts, and bore labels from the manufacturer indicating the correct wattage, in fact the heaters’ electrical output did not conform to the contract’s specifications. Interstate then replaced the heaters in early October, necessitating a third round of testing. Consequently, on October 18, 1994, Neeley returned to the facility and tested the heaters to confirm that they had been properly installed and that they were functioning as specified.

Exactly one year after this last test of the heaters, on October 18, 1995, Interstate filed suit in the Eastern District of Tennessee to recover the alleged $30, 967.00 that it claimed it was owed under the contract. Jurisdiction over the subject matter of the action was provided by 40 U.S.C. § 270b(b) and 28 U.S.C. § 1352.

The Miller Act requires that suits to recover against a payment bond be filed no more than “one year after the day on which the last of the labor was performed....” 40 U.S.C. § 270b(b). A magistrate judge heard the case by consent of the parties, and found that Neeley’s inspection and testing of the heaters on October 18, 1994 was properly characterized as a correction or repair to work previously performed by Interstate. Ruling that testing did not constitute “labor” under the Miller Act, the magistrate judge found that the statute of limitations barred Interstate’s claim and awarded summary judgment to Fidelity. Interstate filed a timely notice of appeal, and this Court has jurisdiction to hear the appeal pursuant to 28 U.S.C. § 636(c)(3).

II

This court reviews a district court’s grant of summary judgment de novo. See [459]*459Terry Barr Sales Agency, Inc. v. All-Lock Co., Inc., 96 F.3d 174, 178 (6th Cir.1996). A motion for summary judgment should be granted “if the pleadings, deposition, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). We view the facts and all inferences drawn therefrom in the light most favorable to the nonmoving party. See Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986).

The Miller Act, 40 U.S.C. § 270a et seq., requires a prime contractor on a federal construction project to post both a performance bond and a payment bond. The payment bond provides security to persons who supply labor or materials for the project. Such suppliers are precluded from filing liens on government facilities, and instead are granted a federal cause of action to satisfy any deficiency in payment by the prime contractor. Because of the remedial nature of the Act, its provisions are to be liberally construed. However, recovery under the Act requires a plaintiff to bring a claim within the Act’s one-year statute of limitations period. See United States ex rel. Consol. Pipe & Supply Co. v. Morrison-Knudsen Co., 687 F.2d 129, 131 (6th Cir.1982); United States ex rel. Martin Steel Constructors Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 761 (9th Cir. 1984); Canion v. Randall & Blake, 817 F.2d 1188, 1191 (5th Cir.1987).

The Act provides a supplier of labor or material who has not been paid in full a right of action to sue on the payment bond. See 40 U.S.C. § 270b(a). In order to provide repose, however, the Act specifies that “no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied ...” § 270b(b). The meaning of the words “labor” and “material” is not self-evident from an examination of the text alone. Unfortunately, turning to the Miller Act’s legislative history provides no more insight in interpreting § 270b(b). Prior to a 1959 amendment, the limitations period under the Act commenced on the “date of final settlement” of the contract. See S. Rep. No 86-551 (1959), reprinted in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
200 F.3d 456, 2000 U.S. App. LEXIS 526, 2000 WL 21033, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-interstate-mechanical-ca6-2000.