The Tolliver Group, Inc. v. United States

Procedural entryThis page is a short order in The Tolliver Group, Inc. v. United States. Read the opinion of the Court — 20 F.4th 771
Court of Appeals for the Federal Circuit·Decided December 13, 2021·No. 20-2341·Published

Opinion

United States Court of Appeals for the Federal Circuit

TOLLIVER GROUP, INC., Plaintiff-Appellee

v.

UNITED STATES, Defendant-Appellant

2020-2341

Appeal from the United States Court of Federal Claims in No. 1:17-cv-01763-CFL, Senior Judge Charles F. Lettow.

Decided: December 13, 2021

WALTER BRAD ENGLISH, Maynard, Cooper & Gale, PC, Huntsville, AL, argued for plaintiff-appellee. Also represented by EMILY J. CHANCEY; MICHAEL W. RICH, Burr & Forman LLP, Mobile, AL.

ASHLEY AKERS, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for defendant-appellant. Also represented by BRIAN M. BOYNTON, MARTIN F. HOCKEY, JR., TARA K. HOGAN.

Before DYK, TARANTO, and CHEN, Circuit Judges.

2 THE TOLLIVER GROUP, INC. v. US

TARANTO, Circuit Judge.

The Tolliver Group, Inc. had a contract with the United States under which Tolliver was obliged to write technical manuals for government-used equipment and the government was obliged to supply Tolliver certain information relevant to that task. When the government failed to obtain the information, and therefore failed to supply it to Tolliver, the parties modified the contract. Tolliver ultimately produced the manuals.

After the modification, however, a third party sued Tolliver in the name of the United States under the False Claims Act, alleging, among other things, that Tolliver had made a false certification of compliance with the original contract because Tolliver had not received the information that the government was contractually obliged to provide. The government, rather than intervening in the case (and then dismissing it), allowed the False Claims Act (qui tam) litigation to proceed. With evidentiary help from the government , Tolliver ultimately prevailed in the qui tam case, but only after incurring substantial legal fees.

Tolliver submitted a claim to the government’s contracting officer under the Contract Disputes Act (CDA), 41 U.S.C. § 7101 et seq., for an “equitable adjustment” for reimbursement of “allowable legal fees.” J.A. 109. The contracting officer denied the claim. Tolliver then brought the present action in the Court of Federal Claims (Claims Court), seeking payment of that claim under 41 U.S.C. § 7104(b)(1). The Claims Court entered judgment for Tolliver on the ground that the United States had breached an implied warranty of performance. Tolliver Grp., Inc. v. United States, 146 Fed. Cl. 475, 479 (2020) (CFC Opinion); Tolliver Grp., Inc. v. United States, 148 Fed. Cl. 351, 352 (2020) (Reconsideration Opinion). We now hold that because Tolliver never submitted a claim of breach of that warranty to the contracting officer, the Claims Court lacked jurisdiction to adjudicate such a claim.

THE TOLLIVER GROUP, INC. v. US 3

I

In September 2012, Tolliver assumed, by novation, responsibility for performance of a 2011 contract with the United States Army Contracting Command (Army) to write technical manuals addressing how to operate and maintain the Hydrema 910 mine-clearing vehicle. 1 Under that fixed-price level-of-effort contract, the Army promised to provide to Tolliver a “technical data package” (TDP) containing the manufacturer’s specifications for the vehicle. But the Army never in fact provided the TDP to Tolliver because it was unable to obtain the information from the manufacturer. According to Tolliver, the Army nevertheless directed Tolliver to continue its performance. J.A. 90, 93, 98, 101. In April 2013, the Army and Tolliver modified the contract, converting it to a fixed-price contract, substantially lengthening the time for performance, increasing its monetary value, and removing the Army’s obligation to provide Tolliver the TDP. The parties agree that Tolliver successfully fulfilled its obligations under the modified contract . J.A. 83, 87.

Meanwhile, in April 2014, Robert Searle, acting in the name of the United States, brought an action under the False Claims Act, 31 U.S.C. § 3729 et seq., against Tolliver in the District Court for the Eastern District of Virginia. Searle, as third-party relator, alleged that Tolliver had falsely certified compliance with the original contract, despite never having received the promised TDP. The United States declined to intervene in the qui tam suit (a step that, had it been taken, would have allowed the government to request dismissal of the suit, subject to statutory procedures ). See 31 U.S.C. § 3730(b)(1), (c)(2)(A). With evidentiary assistance from the government, J.A. 84, Tolliver successfully defended the lawsuit, both in the district court

1 For present purposes, we may, and do, refer to Tolliver and its predecessors on the contract as “Tolliver.”

4 THE TOLLIVER GROUP, INC. v. US

and then on Searle’s appeal to the United States Court of Appeals for the Fourth Circuit. See United States ex rel. Searle v. DRS Technical Servs., Inc., No. 1:14-cv-00402, 2015 WL 6691973 (E.D. Va. Nov. 2, 2015); United States ex rel. Searle v. DRS C3 & Aviation Co., 680 F. App’x 163 (4th Cir. 2017).

In June 2017, after the qui tam suit ended, Tolliver sought reimbursement for the legal fees it had expended defending the lawsuit. In a letter to the contracting officer, Tolliver sought “an equitable adjustment and payment . . . in the amount of $195,889.78 for allowable legal fees.” J.A. 109. Citing Federal Acquisition Regulations (FAR) § 31.205-47, codified at 48 C.F.R. § 31.205-47, Tolliver argued that “[a] contractor who successfully defends a False Claim[s] Act action is entitled to recover its costs in defending the action, including legal fees, up to a maximum of 80% of those fees.” Id. The contracting officer denied the claim, reasoning that the claimed legal fees were neither allocable to the contract nor permitted by the terms of the fixed-price contract. See J.A. 104–07.

Tolliver then sued the United States in the Claims Court. In its initial complaint, Tolliver stated two causes of action. Tolliver alleged that the government had made a “Constructive Change” to the contract by requiring Tolliver to proceed without the TDP, and it was that directive which provoked the qui tam action and hence caused Tolliver to incur the legal fees for which it was seeking government payment. J.A. 101. Tolliver separately alleged a “Breach of Contract – Denial of Allowable Costs,” arguing that it was entitled to reimbursement for 80% of its legal fees under the FAR. J.A. 101–02.

After the United States filed a motion to dismiss, Tolliver amended its complaint. For the constructive-change claim, Tolliver added that the United States had instructed Tolliver to reverse engineer the Hydrema without the TDP and that the United States had failed to dismiss the

THE TOLLIVER GROUP, INC. v. US 5

meritless False Claims Act suit brought in its name. J.A. 93–94. For the second claim, Tolliver changed the name of the claim to just “Breach of Contract,” added the allegation that the government breached the contract by failing to provide the TDP as promised, and alleged that Searle’s lawsuit was a “direct, proximate and foreseeable result of the government’s failure to provide the TDP.” J.A. 94.

The United States filed another motion to dismiss, and at a hearing on the motion, the Claims Court expressed skepticism that the claim before it had been before the contracting officer, saying: “[T]he elements of the claim you made to the contracting officer are different from the elements of a constructive change or breach of contract claim that you [made here]. They’re just different.” J.A. 86–87. Tolliver again amended its complaint. J.A. 74–80. The second amended complaint contained a single claim, for “Recovery of Allowable Cost under FAR § 31.205-47.” J.A. 79. That complaint survived the United States’ next motion to dismiss. Tolliver Grp., Inc. v. United States, 140 Fed. Cl. 520, 522–23 (2018).

Free access — add to your briefcase to read the full text and ask questions with AI

The Tolliver Group, Inc. v. United States, (Fed. Cir. 2021).

The Tolliver Group, Inc. v. United States (The Tolliver Group, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Al Johnson Construction Company v. The United States
854 F.2d 467 (Federal Circuit, 1988)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Raytheon Company v. United States
747 F.3d 1341 (Federal Circuit, 2014)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
U.S. ex rel. Robert Searle v. DRS C3 & Aviation Company
680 F. App'x 163 (Fourth Circuit, 2017)
Croman Corp. v. United States
44 Fed. Cl. 796 (Federal Claims, 1999)
Fluor Hanford, Inc. v. United States
66 Fed. Cl. 230 (Federal Claims, 2005)