Fluor Hanford, Inc. v. United States

66 Fed. Cl. 230, 2005 U.S. Claims LEXIS 184, 2005 WL 1540946
CourtUnited States Court of Federal Claims
DecidedJuly 1, 2005
DocketNos. 02-759C, 03-1287C
StatusPublished
Cited by5 cases

This text of 66 Fed. Cl. 230 (Fluor Hanford, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fluor Hanford, Inc. v. United States, 66 Fed. Cl. 230, 2005 U.S. Claims LEXIS 184, 2005 WL 1540946 (uscfc 2005).

Opinion

OPINION AND ORDER

HODGES, Judge.

Fluor Hanford alleges that the Department of Energy breached its contract by refusing to reimburse legal costs and expenses that plaintiff incurred defending a qui tam action. The issue is whether plaintiff should be reimbursed for its legal expenses or limited to a lesser amount. The Government does not dispute that it owes Fluor a portion of the cost, perhaps eighty percent. The parties filed cross-motions for partial summary judgment on the amount to which Fluor is entitled.

This ease is controlled by an opinion of the Court of Appeals for the Federal Circuit on a related issue. See Boeing N. Am., Inc. v. Roche, 298 F.3d 1274 (Fed.Cir.2002). We must grant defendant’s motion to cap plaintiffs reimbursement at eighty percent.

BACKGROUND

The United States Department of Energy owns a facility for production of nuclear materials in southeast Washington State. The Hanford facility was operated by Westinghouse Hanford Corporation until the mid-[231]*2311990’s. DOE requested proposals for a new manager for the site in 1996 and awarded the contract to Fluor in August of that year. Fluor undertook management responsibilities for the Hanford site in October 1996.1

Plaintiffs agreement with the Department of Energy was primarily a cost-type contract under which DOE agreed to reimburse Fluor for all its allowable costs, including legal costs. See Clause H.38 — “Insurance-litigation and claims.”2 The contract also required the Government to reimburse Fluor for liabilities arising from all pre-existing conditions at the Hanford site.

An employee named David Carbaugh filed a qui tam action against Westinghouse Han-ford Corporation when it was still operating the Facility.3 The primary basis of Mr. Car-baugh’s suit was the company’s use of a financial data system at the Hanford facility that allegedly overcharged the Government for certain personnel costs. The Transfer Agreement between Fluor and Westinghouse required Fluor to retain a portion of the existing workforce, including Mr. Carbaugh. Fluor was responsible for a payroll that was due just days after Fluor began operations at the Hanford site. The accelerated transition schedule made it necessary for Fluor to continue using the same financial data system after it took over in October 1996.

Fluor eliminated 150 positions from its workforce at the Hanford site in January 1997. Mr. Carbaugh’s was one of the jobs eliminated. Mr. Carbaugh amended his qui tam complaint to add Fluor as a defendant following his dismissal in March 1997. The amended complaint included essentially the same allegations against Fluor as Mr. Car-baugh had asserted against Westinghouse. Later he added state employment law claims related to his termination.

The Justice Department reviewed Mr. Carbaugh’s qui tam action and declined to prosecute the claims against Fluor. A district court unsealed the qui tam complaint and ordered that it be served on Fluor in April 1998. The court granted Fluor’s motions for summary judgment on some of Car-baugh’s claims and dismissed other claims. The parties agreed to settle the state employment law claims for $450,000 in January 2002. Fluor submitted a claim to the Government for reimbursement of approximately $1.42 million in April 2001 for legal expenses it incurred defending the qui tam action. It submitted a second claim for approximately $1.99 million for legal costs accruing thereafter, until the lawsuit was dismissed with prejudice in 2002.

Broad indemnity clauses such as those included in the August 1996 contract as Clause H.3 are typical of management contracts of this type. See, e.g., Abraham v. Rockwell Int'l Corp., 326 F.3d 1242, 1245 (Fed.Cir. 2003) (“Because of the inherent danger in manufacturing nuclear weapons components, the [Management and Operation] contracts required the government to assume ‘virtually all operational and financial risks’ in performing the contracts.”) (citation omitted). Clause H.3 of plaintiffs August 1996 contract with the Government provides that:

The DOE agrees to reimburse [Fluor] ... for any liability ... and any civil fine or penalty, expense, or remediation cost, but limited to those of a civil nature, which may be incurred by, imposed on, or asserted against the Contractor arising out of any condition, act, or failure to act that occurred before the Contractor assumed responsibility on October 1,1996.

Contract Clause H.3 — Pre-Existing Conditions. Though the qui tam action against Fluor was such a liability, having arisen “before the Contractor assumed responsibility on October 1,1996,” the Government refused [232]*232to reimburse plaintiff its legal costs. The Contracting Officer agreed to reimburse only eighty percent of Fluor’s reasonable costs of defending the qui tam action. She partly denied Fluor’s $1.99 million second claim, allowing reimbursement of only $1.72 million.4 The Government has not paid Fluor for the claim that it submitted to DOE in April 2001.

DISCUSSION

Summary judgment is appropriate when the record contains no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(e); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The parties do not dispute genuine issues of material fact. Issues of statutory interpretation are matters of law that may be decided on motions for summary judgment. Santa Fe Pac. R.R. Co. v. United States, 294 F.3d 1336, 1340 (Fed.Cir.2002).

The contracting officer’s justification for withholding full reimbursement of plaintiffs costs of defense is a FAR provision that was issued pursuant to the Major Fraud Act of 1988, 10 U.S.C. § 2324, 41 U.S.C. § 256; 48 C.F.R. § 31.205-47(b). The Major Fraud Act disallows certain costs incurred by a contractor in connection with a proceeding commenced by the United States. Its purpose is to prevent the Government from financing both sides of a lawsuit. See 10 U.S.C. § 2324(k); 41 U.S.C. § 256(k). Fluor’s right to full reimbursement of its legal costs of defending the qui tam action in dispute depends on the interpretation of the Major Fraud Act, the applicability of a 1998 amendment to Federal Acquisition Regulations promulgated pursuant to that Act, and a ruling by the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
66 Fed. Cl. 230, 2005 U.S. Claims LEXIS 184, 2005 WL 1540946, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fluor-hanford-inc-v-united-states-uscfc-2005.