STEWARD MACH. CO., INC. v. White Oak Corp.

462 F. Supp. 2d 251, 2006 U.S. Dist. LEXIS 83842, 2006 WL 3349477
CourtDistrict Court, D. Connecticut
DecidedNovember 16, 2006
DocketCivil Action 3:00cv834(SRU)
StatusPublished

This text of 462 F. Supp. 2d 251 (STEWARD MACH. CO., INC. v. White Oak Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STEWARD MACH. CO., INC. v. White Oak Corp., 462 F. Supp. 2d 251, 2006 U.S. Dist. LEXIS 83842, 2006 WL 3349477 (D. Conn. 2006).

Opinion

MEMORANDUM OF DECISION

UNDERHILL, District Judge.

Steward Machine Co., Inc. (“Steward”) has sued White Oak Corp. (“White Oak”) and White Oak’s surety, National Union Fire Insurance Co. of Pittsburgh, PA (“National Union”). The action arises out of the construction of the Tomlinson Bridge in New Haven, Connecticut. In 1994, the Connecticut Department of Transportation (“ConnDOT” or “the State”) engaged White Oak to be the project’s general contractor. White Oak then procured a payment bond, with National Union as surety, and sub-contracted with Steward for the latter to furnish certain machinery for the project.

Steward filed suit against the defendants seeking damages for White Oak’s failure to pay Steward in full on a timely basis, White Oak’s failure to accept delivery of the machinery, and the lengthy, ensuing storage of the Tomlinson Bridge machinery at Steward’s plants.

The parties tried the case to the court over six days. My findings of fact and conclusions of law are set forth below. See Fed.R.Civ.P. 52.

I. Background

The parties presented conflicting testimony regarding the effect of their contracts. My findings of fact are largely based on the written purchase order contract, documents relating to the contracts at issue, the parties’ written correspondence, and the testimony of Steward’s President Whitney DeBardeleben, whom I find credible.

A. Parties’ Involvement ivith the Tom-linson Bridge Project

Steward is a family-owned, specialized job shop located in Birmingham, Alabama. Among other large-scale items, Steward manufactures mechanical equipment, including sheaves and counterweight ropes, for moveable bridges.

During the design phase of the Tomlin-son Bridge project, the engineering firm Hardesty & Hanover, the project’s design engineers, contacted Steward to inquire about the feasibility of the bridge design plans. As a result of that contact, Steward became interested in the project. Once the engineers submitted their design to the State, ConnDOT solicited bids from general contractors. Steward submitted its bids to the general contractors that were bidding on the project, including White Oak. ConnDOT eventually awarded White *254 Oak the contract for State Project 92-435, the construction of the Tomlinson Bridge in New Haven, Connecticut.

As required by Conn. Gen.Stat. § 49-41, White Oak secured a payment bond to guarantee the public work project. On June 6, 1994, National Union issued that payment bond, guaranteeing the project in the amount of $87,868,378.10. Pl.Ex. 1.

B. Purchase Order Contract

White Oak subcontracted with Steward for the latter to furnish large-scale equipment for the Tomlinson Bridge. On August 8, 1994, Steward and White Oak executed a written purchase order contract setting forth the details of the parties’ subcontract. Pl.Ex. 3.

1. ConnDOT Approval

The introductory paragraph of the purchase order specifies that the bid items “shall be in accordance with the plans and specifications prepared by” ConnDOT, the project owner. Pl.Ex. 3 at 1.

2. Bid Items and Prices

The purchase order contract included four items and a delivery allowance. Id. The four items were identified by Conn-DOT bid item numbers, corresponding to the items as listed on White Oak’s prime contract with the State. With their corresponding values, the items were:

Operating machinery $1,215,000
Main and auxiliary counterweight ropes and accessories 1,465,000
Counterweight sheaves, shafts and bearings 4,400,000
Lock machinery 253,000
Total for bid items $7,333,000

3.Delivery

In addition to the four bid items, the purchase order included a delivery allowance in the amount of $220,000. Thus, the value of the purchase order contract totaled $7,553,000.

The purchase order contract included the following provision regarding delivery:

Delivery will commence within 12 months from approval of drawings and be complete within 18 months from approval of drawings. Seller shall make all deliveries in accordance with the Buyer’s schedule.

Pl.Ex. 3 at 6.

White Oak and National Union have argued, in essence, that the second sentence of the delivery provision (“Seller shall make all deliveries in accordance with the Buyer’s schedule.”) overrides the first sentence. Accordingly, the defendants argue that Steward (the Seller) agreed to abide by White Oak’s (the Buyer’s) delivery schedule even if that schedule included a delay of several years after the approval of drawings. In other words, they argue that Steward — not White Oak — bore any risk of delay.

Based on the language of the purchase order’s delivery provision and the testimony of DeBardeleben, however, I find that the parties did not agree to an indefinite delivery date or one that could extend several years beyond the twelve- to eighteen-month window set forth in the contract’s delivery provision. The parties’ contract provided that Steward would make deliveries in accordance with White Oak’s schedule, with respect to each bid item, but that schedule was limited to the six-month period commencing twelve months after the approval of Steward’s drawings.

The approval of drawings for each bid item spanned several years. The last approval of drawings for the lock machinery was May 15, 1998; the last approval of drawings for the sheaves was January 29, 1996; the last approval of drawings for the counterweight ropes and accessories was March 19, 1996; and the last approval of *255 drawings for the operating machinery was January 6, 2000. Def. Ex. 785.

White Oak had until eighteen months after each of those dates to request and accept delivery of the respective bid item. Thus, under the purchase order contract, delivery of the lock machinery was to occur by November 16, 1999; delivery of the sheaves was to occur by July 30, 1997; delivery of the counterweight ropes was to occur by September 20, 1997; and delivery of the operating machinery was to occur by July 7, 2001.

4. Ten-ms and Conditions

a. Terms of Payment and Effect of Payment from ConnDOT

The purchase order contract included the following terms of payment:

Buyer [White Oak] will cooperate with Seller [Steward] to submit requests for payment on a timely basis to Owner [ConnDOT] for all items of work incorporated herein or a portion thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brogan v. National Surety Co.
246 U.S. 257 (Supreme Court, 1918)
Standard Ins. Co. v. United States
302 U.S. 442 (Supreme Court, 1938)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
American Masons' Supply Co. v. F. W. Brown Co.
384 A.2d 378 (Supreme Court of Connecticut, 1978)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
Otto Contracting Co. v. S. Schinella & Son, Inc.
427 A.2d 856 (Supreme Court of Connecticut, 1980)
Loda v. H. K. Sargeant & Associates, Inc.
448 A.2d 812 (Supreme Court of Connecticut, 1982)
Ubysz v. DiPietro
440 A.2d 830 (Supreme Court of Connecticut, 1981)
West Haven Sound Development Corp. v. City of West Haven
514 A.2d 734 (Supreme Court of Connecticut, 1986)
Presidential Capital Corp. v. Reale
652 A.2d 489 (Supreme Court of Connecticut, 1994)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Poole v. City of Waterbury
831 A.2d 211 (Supreme Court of Connecticut, 2003)
Tureck v. George
687 A.2d 1309 (Connecticut Appellate Court, 1997)
Paulus v. LaSala
742 A.2d 379 (Connecticut Appellate Court, 1999)
Rosato v. Mascardo
844 A.2d 893 (Connecticut Appellate Court, 2004)
Anthem Health Plans, Inc. v. Action Motors Corp.
850 A.2d 1122 (Connecticut Appellate Court, 2004)
Positive Impact Corp. v. Indotronix International Corp.
900 A.2d 535 (Connecticut Appellate Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
462 F. Supp. 2d 251, 2006 U.S. Dist. LEXIS 83842, 2006 WL 3349477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steward-mach-co-inc-v-white-oak-corp-ctd-2006.