State Ex Rel. C & D Equipment Company v. Gainer

174 S.E.2d 729, 154 W. Va. 83, 1970 W. Va. LEXIS 179
CourtWest Virginia Supreme Court
DecidedApril 14, 1970
Docket12920
StatusPublished
Cited by13 cases

This text of 174 S.E.2d 729 (State Ex Rel. C & D Equipment Company v. Gainer) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. C & D Equipment Company v. Gainer, 174 S.E.2d 729, 154 W. Va. 83, 1970 W. Va. LEXIS 179 (W. Va. 1970).

Opinions

Berry, Judge:

This is an original proceeding in mandamus initially filed in this Court on December 9, 1969, in which the petitioner, C & D Equipment Company, a corporation, for the use and benefit of the First National Bank of South Charleston, West Virginia, to which money had been assigned, seeks a writ to compel the respondent, Denzil L. Gainer, Auditor of the State of West Virginia, to draw a warrant for the payment of an agreed amount between the petitioner and the State Building Commission of West Virginia on the funds of the said Commission in the hands of the State Treasurer of West Virginia, the said agreed amount to be paid to the petitioner as the result of a compromised claim for damages [85]*85in connection with a contract between the parties to demolish various houses and other structures in the vicinity of the State Capitol of West Virginia. The first application was refused, but a rule was issued January 19, 1970, on a second application by the petitioner, directing the respondent to show cause why a writ of mandamus should not be granted as prayed for to compel the payment of $29,907.68, the agreed amount of the settlement of the claim against the State Building Commission by the parties. The matter was submitted for decision on arguments and briefs of the respective parties at the January Regular Term, 1970, of this Court.

The controversy involved herein arose out of a contract executed December 29, 1967, between the C & D Equipment Company and the State Building Commission which provided for the demolition by the petitioner of approximately fifty structures in the vicinity of the State Capitol which occupied the site of two new office buildings which have since been erected with some adjacent parking areas. The contract was entitled “Demolition Contract, Project: Capitol Complex,” and was awarded to the petitioner as a result of the petitioner being the low bidder for the work to be done after notices had been given to prospective contractors for such work and sealed bids of the various bidders had been submitted to the Commission. The petitioner’s bid was in the amount of $41,717 for the work to be done and was accepted by the Commission. Attached to the contract was a list of structures to be demolished and the location thereof by street numbers around the area to be cleared.

According to the allegations of the petition, when the company started to work soon after the contract was executed, it developed that the Commission had not cleared all of the structures for demolition and some tenants were still occupying the structures. As the result of this situation, the company had to move its equipment around the structures which were occupied and not ready for demolition. This resulted in the unnecessary moving of the equipment and in numerous delays in waiting for various structures to be vacated in order that they could be demolished. The company had rented extra [86]*86equipment to be used on this project which was necessary to perform the work to be done, and rent therefor had to be paid by the company during this delay. It is claimed by the company, as indicated by an affidavit made on June 10, 1968, that it had been subjected to added costs in the amount of $29,907^68 in.addition to the contract price represented by its low bid contained in the contract of $41,717. It was further claimed by another affidavit made on June 12, 1968, that the completion of the work would take two more weeks after June 10,1968, in which the company would incur an additional loss of $6,702.88 for which it agreed not to press a claim if the Commission would reimburse it for the first amount claim of $29,907.68.

After the complaint with regard to the extra cost was presented to the Building Commission a subcommittee was appointed by the Commission to investigate the matter, and after an examination of the claim was made, it recommended the payment of $29,907.68. The Building Commission, by its secretary, then submitted a requisition for this amount to the State Auditor with the request that he issue a warrant to the State Treasurer to pay such amount.

The Auditor refused to issue a warrant authorizing the payment of the claim and gave as a reason by an endorsement on the requisition that the amount was in excess of the contract, was not supported by an authorized change order, and could possibly be presented as a claim for consideration. by the Court of Claims.

After the refusal of the Auditor to issue a warrant on the first requisition a purported change order was drawn up by the Commission and forwarded with another requisition to the Auditor for the payment of the claim of $29,907.68. The Auditor again refused to authorize the payment as requested and stated that the requisition was for an increase of approximately seventy per cent over the amount contained in the original contract and that he did not mean to convey the idea that a change order was all that was needed for the authorization for the payment in such case. He further stated that he [87]*87could not authorize the payment unless the matter was submitted to the Court of Claims to determine if there was a moral obligation and that he was accordingly submitting it to the Court of Claims.

The Court of Claims apparently considered the request for an advisory opinion without a hearing and indicated that it was not proper to bring the claim to its attention in this fashion but that there should be a hearing with evidence presented to it on the matter by the petitioner if petitioner desired to file a claim. The petitioner apparently did not ask the Court of Claims to consider its claim but instead instituted the instant proceeding in this Court.

It is contended by the petitioner that the Court of Claims did not have jurisdiction to hear this claim because the money for the operation of the Building Commission comes from the sale of bonds issued by the Commission which do not encumber the general funds of the State and that the Building Commission can be sued in the courts of this State and, therefore, under the statute creating the Court of Claims it has no jurisdiction in such cases.

The respondent filed a demurrer and an answer. In the demurrer he takes the position that the Commission is a State agency and therefore immune from a suit based on negligence or breach of contract, that this matter represents an effort to obtain additional compensation for a contractor, which is prohibited by the Constitution of this State, that it is his duty to refuse the authorization of such payment unless and until the claim has been declared to be a moral obligation by the Legislature and that mandamus, if granted, would compel him to do an illegal or unauthorized act.

The respondent’s answer denies there was any particular plan of operation in connection with the work required by the contract between the petitioner and the Commission and states that there was no duty on the part of the Commission to have each building lined up in order to conform to any plan the company might have had for the demolition work. The answer further states that the respondent did not ask [88]*88for an advisory opinion of the Court of Claims but merely suggested that it consider the matter as provided by law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaffer v. Stanley
593 S.E.2d 629 (West Virginia Supreme Court, 2003)
State ex rel. McLaughlin v. West Virginia Court of Claims
549 S.E.2d 286 (West Virginia Supreme Court, 2001)
Parkulo v. West Virginia Board of Probation & Parole
483 S.E.2d 507 (West Virginia Supreme Court, 1997)
DePond v. Gainer
351 S.E.2d 358 (West Virginia Supreme Court, 1986)
Pittsburgh Elevator Co. v. West Virginia Board of Regents
310 S.E.2d 675 (West Virginia Supreme Court, 1983)
Woodford v. Glenville State College Hous. Corp.
225 S.E.2d 671 (West Virginia Supreme Court, 1976)
Woodford v. Glenville State College Housing Corp.
225 S.E.2d 671 (West Virginia Supreme Court, 1976)
State Ex Rel. C. J. Langenfelder & Son, Inc. v. Ritchie
179 S.E.2d 591 (West Virginia Supreme Court, 1971)
State Ex Rel. C & D Equipment Company v. Gainer
174 S.E.2d 729 (West Virginia Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
174 S.E.2d 729, 154 W. Va. 83, 1970 W. Va. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-c-d-equipment-company-v-gainer-wva-1970.