Woodford v. Glenville State College Housing Corp.

225 S.E.2d 671, 159 W. Va. 442, 1976 W. Va. LEXIS 180
CourtWest Virginia Supreme Court
DecidedMarch 23, 1976
DocketNo. 13600
StatusPublished
Cited by35 cases

This text of 225 S.E.2d 671 (Woodford v. Glenville State College Housing Corp.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodford v. Glenville State College Housing Corp., 225 S.E.2d 671, 159 W. Va. 442, 1976 W. Va. LEXIS 180 (W. Va. 1976).

Opinions

Neely, Justice:

This case involves an attempt by the plaintiff, Paul H. Woodford, to recover payment for materials provided to a sub-contractor in the construction of a faculty and student housing facility on the Glenville State College campus. In April 1969 Centurion Corporation contracted with Glenville State College Housing Corporation for the construction of a living facility, which was to be known as “Project B,” upon property owned by the State Board of Education but leased to the defendant non-profit corporation. The defendant, Glenville State College Housing Corporation, (hereafter, Housing Corporation), was a non-profit corporation chartered in 1967 for the purpose of constructing housing on the Glenville State College campus. The corporation was authorized to borrow necessary funds, to issue securities of the corporation, and ultimately to convey any structures constructed in Glen-ville to the college.

Centurion Corporation then sub-contracted with a certain Mullins Building and Supply Company to do work on the project, and Mullins in turn purchased materials from the plaintiff which were used in Project B. Between April and November 1970 Centurion defaulted on the contract, having completed 85% of the project, and assigned its rights under the contract to the co-defendant, Amer-Con, Inc. for completion of the remaining 15%.

The plaintiff sought payment from defendants, Amer-Con and Housing Corporation, for over $16,000 of material he had supplied to the project, and when payment was refused, he instituted this action on April 14, 1971 in the Circuit Court of Gilmer County. Plaintiff had delivered his materials under his contract with Mullins in April 1970, but while Centurion had paid Mullins in full on all accounts, Mullins had not paid plaintiff and plaintiff took no steps to perfect a lien against Project B.

[444]*444When Centurion went bankrupt two other sub-contractors on the project filed liens against Project B, which were perfected and outstanding at the time that Amer-Con undertook to complete the project in the place of Centurion. In order for Amer-Con to receive payments which were due to Centurion for completed work which Housing Corporation was reluctant to pay because of the outstanding liens, Amer-Con and Housing Corporation entered into a contract by which Amer-Con agreed to pay outstanding claims against Project B. The contract between the two is as follows:

“AGREEMENT made this 30th day of November, 1970, in Glenville, West Virginia, between AMER-CON, INC. (hereinafter ‘Contractor’) and the GLENVILLE STATE COLLEGE HOUSING CORPORATION (hereinafter ‘Corporation’).
WHEREAS, Contractor, as successor to all the rights of Centurion Corporation, wishes to settle the claims arising out of a contract for ten (10) Faculty Housing Units known hereinafter as Project B between Centurion and Corporation, it is therefore agreed that:
(1) Corporation shall pay Contractor the amount of two hundred-fifty thousand dollars ($250,000) plus any amounts expended over thirty thousand dollars ($30,000) to complete said Project ‘B’.
(2) Contractor hereby agrees to be solely, liable and to fully satisfy any and all claims which Cotz & Cirigliano, Inc., dba Western Concrete Company; Paul H. Woodford; and Home and Community Improvement Corporation, all of West Virginia, may have against said Project ‘B’.
(3) Corporation shall pay Contractor with tax-exempt bonds which shall be issued as soon as possible. Corporation shall have the right to seek its own means of financing such bonds. In addition, Corporation shall have the right to call upon Contractor to use Contractor’s best efforts to find a means to finance said bonds. In all [445]*445events, Corporation shall have the duty to be liable for said financing costs, if any.

The plaintiff brought this action against Amer-Con and the Housing Corporation as a third party beneficiary of Paragraph 2 of the contract quoted above. Upon an agreed set of facts the Circuit Court of Gilmer County awarded judgment to the plaintiff. We are compelled to reverse.

I

The plaintiff, Woodford, alleges that he did not perfect a lien against Project B according to the statutory lien procedure provided by W. Va. Code, 38-2-1 et seq., because the Housing Corporation was an instrumentality of the State and therefore enjoyed immunity from legal actions by virtue of W. Va. Const., Art. VI, § 35. We disagree with plaintiff’s assumption and allegation. This Court has dealt with the issue of the applicability of sovereign immunity to myriad forms of State instrumen-talities throughout the Twentieth Century. Due to the seemingly limitless variety of situations in which the issue has arisen and will continue to arise, this Court has never attempted to establish any definitive set of rules to apply to all situations. However, certain general criteria for the application of the doctrine of sovereign immunity in this type of situation may be gleaned from the comparatively recent cases of Hope Natural Gas Co. v. West Virginia Turnpike Commission, 143 W. Va. 913, 105 S.E.2d 630 (1958), and Morgantown v. Ducker, 153 W. Va. 121, 168 S.E.2d 298 (1969) as well as numerous others cited in the footnotes. The Housing Corporation meets none of these criteria.

For example, the Housing Corporation was not created or granted authority to perform any function on behalf of the State by specific enactment of the Legislature.1 [446]*446This is the preeminent criterion established by Morgantown v. Ducker, supra, where the following language appears at 153 W. Va. 127, 168 S.E.2d 302:

“This Court has held in numerous cases that proceedings against boards and commissions, created by the Legislature as agencies of the State, are suits against the State within the meaning of Article VI, Section 35 of the Constitution of West Virginia, even though the State is not named as a party in such proceeding.”

Funds for the operation of the Housing Corporation were not appropriated by the Legislature.2 There was no mandate that revenues received and income produced by the Housing Corporation must or would be paid into the State Treasury rather than expended on its own behalf,3 and monies available to the Housing Corporation to pay off its debts were not obtainable from a State source.4 On the contrary, the Housing Corporation was a private, non-profit, corporation with no call upon the State treasury and it was not subject to State control in any way. Its revenues were limited to contributions, income from rent payments from prospective faculty and students, and from borrowed funds. Most importantly, it was not in any regard liable to creditors for amounts in excess of its assets.

[447]*447In defense of plaintiff’s position that the Housing Corporation was a public corporation and arm of the State, plaintiff maintains that the State Board of Education was not entitled to lease land to which it held title to a private corporation, and cites for that proposition W. Va. Code 5A-5-1 [1965] which provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donna S. v. Travis S.
West Virginia Supreme Court, 2022
Stonerise Healthcare, LLC v. Susan K. Oates
West Virginia Supreme Court, 2020
Adam Lunsford v. Cravens Funeral Home
West Virginia Supreme Court, 2015
Ellis-Walker Builders, Inc. v. Don Reynolds Properties, LLC
695 S.E.2d 832 (Court of Appeals of North Carolina, 2010)
Badger Lumber Co. v. Redd
583 S.E.2d 76 (West Virginia Supreme Court, 2003)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
Casto v. Dupuy
515 S.E.2d 364 (West Virginia Supreme Court, 1999)
Elmore v. State Farm Mutual Automobile Insurance
504 S.E.2d 893 (West Virginia Supreme Court, 1998)
Robinson v. Cabell Huntington Hospital, Inc.
498 S.E.2d 27 (West Virginia Supreme Court, 1997)
Clint Hurt & Associates, Inc. v. Rare Earth Energy, Inc.
480 S.E.2d 529 (West Virginia Supreme Court, 1996)
Marks Construction Co. v. Board of Education
408 S.E.2d 79 (West Virginia Supreme Court, 1991)
Blower v. West Virginia Educational Broadcasting Authority
389 S.E.2d 739 (West Virginia Supreme Court, 1990)
Waco Equipment Co. v. B.C. Hale Construction Co.
387 S.E.2d 848 (West Virginia Supreme Court, 1989)
4-H Road Community Ass'n v. West Virginia University Foundation, Inc.
388 S.E.2d 308 (West Virginia Supreme Court, 1989)
Brooks v. United States
833 F.2d 1136 (Fourth Circuit, 1987)
Commercial Bank of Bluefield v. St. Paul Fire & Marine Insurance
336 S.E.2d 552 (West Virginia Supreme Court, 1985)
Dunlap v. Hinkle
317 S.E.2d 508 (West Virginia Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
225 S.E.2d 671, 159 W. Va. 442, 1976 W. Va. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodford-v-glenville-state-college-housing-corp-wva-1976.