State Ex Rel. C. J. Langenfelder & Son, Inc. v. Ritchie

179 S.E.2d 591, 154 W. Va. 825, 1971 W. Va. LEXIS 241
CourtWest Virginia Supreme Court
DecidedMarch 9, 1971
Docket13033
StatusPublished
Cited by4 cases

This text of 179 S.E.2d 591 (State Ex Rel. C. J. Langenfelder & Son, Inc. v. Ritchie) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. C. J. Langenfelder & Son, Inc. v. Ritchie, 179 S.E.2d 591, 154 W. Va. 825, 1971 W. Va. LEXIS 241 (W. Va. 1971).

Opinion

Haymond, Judge:

In this original mandamus proceeding instituted in this Court in November, 1970, the petitioner, C. J. Langenfelder & Son, Inc., a corporation, seeks a writ to compel the defendant, Honorable William S. Ritchie, Jr., West Virginia Commissioner of Highways, to issue requisitions upon the auditor of this State to draw warrants for the payment by the treasurer of this State from the state road fund, of the amounts of money which the petitioner claims are owing to it by the defendant for work performed and materials furnished on two road construction proj'ects designated as Proj'ect 1-70-1 (12) 1 and Project 1-70-1 (13) 2, C-l, in Ohio County, West Virginia, under unit price contracts between the State of West Virginia acting by the State Road Commission of West Virginia, and the petitioner, dated July 24, 1963 and February 5, 1964. The projects were for the construction of what are designated as Wheeling Tunnel No. 2045 approximately 1425 feet in length and Interstate 70-Cemetery to Fulton Road approximately 3928 feet in length.

Upon the petition and its exhibits this Court issued a rule returnable January 19, 1971 at which time this proceeding was submitted for decision upon the petition and its exhibits, the answer of the defendant and its exhibits, the motion of the petitioner to strike certain portions of the answer of the *827 defendant, the demurrer and the general and special replication of the petitioner to the answer, the rejoinder of the defendant to the replication of the petitioner, and the briefs and the oral arguments in behalf of the respective parties.

There were three construction projects under three separate unit price contracts between the parties and after completion of the work the addition of numerous extras led to complications and differences and in October 1968 the petitioner filed in the Court of Claims of West Virginia claims on all three projects, which claims were designated as Numbers D-120, D-121 and D-122. After a hearing in the court of claims of claim Number D-120, the court of claims made an award in favor of the petitioner in the amount of $191,000.00. That award has been paid and it and the contract on which it was based are not involved in this proceeding.

Evidence was adduced by the petitioner and the defendant before the court of claims with respect to claim Number D-121, but before final action on that claim, and at the suggestion of the court of claims that counsel for the respective parties in claims Numbers D-121 and D-122 endeavor to settle those disputed claims, the defendant through his counsel and employees reviewed the entire matter and determined that the petitioner was entitled to the total of $325,000.00 for both claims, $130,134.90 for claim Number D-121 and $194,865.10 for claim Number D-122, and the defendant, through his counsel, agreed to the settlement of the claims for that amount and to pay that amount as soon as possible in accordance with the applicable statutes and laws of this State. By letter dated July 29, 1970, counsel for the petitioner accepted the settlement offered by the defendant in the amount of $325,000.00 as final payment for the disputed items of work and material involved in the claims. The letter contained a statement that payment should be made within thirty days but the record does not show that the defendant agreed to any time or method of payment. After the foregoing agreed settlement of the claims there have been no further proceedings concerning them in the court of claims.

*828 The petitioner insists that, inasmuch as the claims designated Number D-121 and Number D-122 have been reviewed by the defendant and the defendant has determined that the petitioner is entitled to the sum of $325,000.00 in payment of both claims, the petitioner is entitled to such payment without delay and without any further proceedings in the court of claims or otherwise. The defendant, however, contends that, inasmuch as the final estimate for the extras for Project 1-70-1 (12) 1 and the final estimate for the extras for Project 1-70-1 (13) 2, C-l, differ in amounts from the settlement amounts for claims Numbers D-121 and D-122, and differ in amount from the agreed settlement of $325,000.00 for both claims, the final estimates must be considered, processed and determined in the court of claims before payment may be made by the defendant. The refusal of the defendant to pay the agreed amount of the settlement of the claims without action by the court of claims has resulted in the institution of this proceeding. In short, the dispute involves, not the amount or the validity of the claims of the petitioner, but the manner of and the procedure to be followed in the payment.

The petitioner reserved the right to file claims before the court of claims for amounts in addition to the amounts shown by the final estimates but before the claims for such additional amounts were acted upon in the court of claims the agreed settlement of the claims was entered into fairly and in good faith between the parties in the total amount of $325,000.00 which is a substantially smaller amount than the total amount of the undetermined claims which include claim Number D-121 in the amount of $464,655.66. It is clear that the settlement reduces the claims of the petitioner at least by the difference between $484,655.66 and $325,000.00 of $159,655.66 in favor of the defendant.

With respect to the agreement to settle the claims designated Number D-121 and Number D-122 the answer of the defendant contains these allegations:

“The respondent, through his attorney and employees, reviewed the entire matter and determined that the petitioner would be entitled to the total sum of Three Hundred Twenty- *829 Five Thousand Dollars ($325,000.00) for both Claims Numbered D-121 and D-122, which amount was further broken down as follows: $130,134.90 in Claim Number D-121 $194,-865.10 in Claim Number D-122.

“The respondent, through his attorney, agreed to settle the disputed claims for the aforesaid amounts, which agreement was to the effect that the respondent was willing to pay the relator herein the total sum of Three Hundred Twenty-Five Thousand Dollars ($325,000.00) on the amounts claimed by relator in its claims filed in the Court of Claims of the State of West Virginia.”

The defendant has refused to pay the agreed amount of $325,000.00 in the foregoing settlement because he contends that payment of that amount can only be achieved by obtaining an award in the court of claims under the provisions of Chapter 14, Article 2, Sections 16 and 23, Code, 1931, as amended, and obtaining an appropriation of an amount in payment of the claim from the Legislature or, in the alternative, if the claim is made on an existing appropriation under the provisions of Chapter 14, Article 2, Section 19, Code, 1931, as amended, the payment can only be made if the court of claims certifies the approved claim and award to the West Virginia Commissioner of Highways, the State auditor and the Governor and the Governor instructs the auditor to issue his warrant in payment of the award.

There is no merit in that contention and inasmuch as a fair and valid settlement favorable to the defendant has been agreed to between the parties there is no necessity for action by the court of claims concerning the agreed settlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. State of West Virginia Human Rights Commission
324 S.E.2d 99 (West Virginia Supreme Court, 1984)
Reed v. Hansbarger
314 S.E.2d 616 (West Virginia Supreme Court, 1984)
Ables v. Mooney
264 S.E.2d 424 (West Virginia Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
179 S.E.2d 591, 154 W. Va. 825, 1971 W. Va. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-c-j-langenfelder-son-inc-v-ritchie-wva-1971.