State Corps v. United States

CourtUnited States Court of Federal Claims
DecidedJune 9, 2015
Docket14-1121
StatusUnpublished

This text of State Corps v. United States (State Corps v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Corps v. United States, (uscfc 2015).

Opinion

United States Court of Federal Claims No. 14-1121 C (Filed June 9, 2015)

STATE CORPS, ) Plaintiff, ) v. ) ) THE UNITED STATES, ) Defendant. )

OPINION

On November 18, 2014, plaintiff filed a complaint in this court seeking: (1) a declaration that the United States Army Corps of Engineers improperly terminated a contract for construction of logistics facilities in Qatar for default; (2) conversion of the default termination to a termination for convenience; and (3) compensation for the damages that plaintiff incurred as a result of the improper termination decision. See Doc. 1 at 1.

The government moved to stay the proceedings and for dismissal of plaintiff’s damages claim for lack of jurisdiction. See Doc. 8. On April 30, 2015, the court requested additional briefing in support of the government’s motion to stay, see Doc. 13, and in response, the government moved to withdraw the motion, see Doc. 14. Because the plaintiff did not file a response by the June 5, 2015 deadline, the court assumes it has no objection, and the motion to withdraw is hereby GRANTED.

The government’s partial motion to dismiss, then, is before the court. The government concedes that the court has jurisdiction over plaintiff’s claim that the termination for default should be converted to a termination for convenience. See Docs. 8 at 16; 12 at 2. It argues, however, that the court lacks jurisdiction over plaintiff’s claim for monetary relief on the basis that plaintiff failed to submit a valid claim to the contracting officer prior to filing the instant lawsuit. See Doc. 8 at 13.

ANALYSIS

Plaintiff bears the burden to demonstrate, by a preponderance of the evidence, that the court has jurisdiction to hear its case. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327 (Fed. Cir. 2010) (citing Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988)). “In determining jurisdiction, a court must accept as true all undisputed facts asserted in the plaintiff’s complaint and draw all reasonable inferences in favor of the plaintiff.” Trusted Integration, Inc. v. United States, 659 F.3d 1159, 1163 (Fed. Cir. 2011) (citing Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995)). But if the court lacks subject matter jurisdiction, it must dismiss the case. See Rebish v. United States, 120 Fed. Cl. 184, 187 (2015) (citing Arbaugh v. Y & H Corp., 546 U.S. 500, 514 (2006); Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94-95 (1998)).

Pursuant to 28 U.S.C. § 1491(a)(1), the Court of Federal Claims has jurisdiction “to render judgment upon any claim against the United States founded . . . upon any express or implied contract with the United States . . . .” The court specifically has jurisdiction “to render judgment upon any claim by or against, or dispute with, a contractor arising under section 7104(b)(1) of title 41 . . . .” 28 U.S.C. § 1491(a)(2).

Section 7104(b)(1) provides for de novo proceedings by this court following a contracting officer’s final decision to deny relief based on a written claim against the government made under section 7103. See 41 U.S.C. § 7104(b)(1). Section 7103, in turn, requires that claims by contractors against the government be made to the contracting officer, in writing, within six years of the claim’s accrual. See 41 U.S.C. § 7103(a). The Federal Circuit has held that jurisdiction “requires both a valid claim and a contracting officer’s final decision on that claim.” Maropakis, 609 F.3d at 1327 (citing James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541–42 (Fed.Cir.1996)).

Plaintiff argues that the allegations in this case fall within these jurisdictional limits because it submitted a claim under section 7103, in the form of its letter dated July 6, 2014, see Doc. 8-1, to which the government responded on October 31, 2014, see Doc. 1, Ex. C. The government counters that plaintiff has failed to satisfy the requirements of sections 7103 and 7104 because its July 6 letter did not technically constitute a claim. See Doc. 8 at 13-15.

The term “claim,” as used in sections 7103 and 7104, is not defined in title 41, but courts look to the Federal Acquisition Regulation (“FAR”) for its meaning. See Todd Constr., L.P. v. United States, 656 F.3d 1306, 1311 (Fed. Cir. 2011) (citing H.L. Smith, Inc. v. Dalton, 49 F.3d 1563, 1564-65 (Fed. Cir. 1995)). The FAR defines “claim” as:

2 a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.

FAR § 2.101. Here, the parties agree that a valid claim must:

(1) be a written demand or assertion; (2) be non-routine, or in dispute; (3) seek payment as a matter of right; (4) seek payment as a sum certain; (5) “indicate to the contracting officer that the contractor is requesting a final decision;” and (6) be certified if seeking more than $100,000.

Doc. 8 at 12-13 (government’s motion to dismiss, compiling requirements from statutory, regulatory and Federal Circuit authority, including, 41 U.S.C. § 7103(b)(1); FAR § 2.101; Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1576-83 (Fed. Cir. 1995); M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327 (Fed. Cir. 2010); James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 n.4 (Fed. Cir. 1996); and Fischback & Moore Int’l Corp. v. Christopher, 987 F.2d 759, 762 (Fed. Cir. 1993)). See also Doc. 11 at 7 (plaintiff’s response to the government’s motion to dismiss, agreeing with the government’s listed requirements for a valid claim).

Plaintiff argues that its July 6 letter complies with each of these requirements. See Doc. 11 at 7. The government argues that the letter is not a valid claim because it fails to seek a sum certain. See Doc. 8 at 13-15.

As the plaintiff points out, the July 6 letter does include specific dollar figures. On the first page, the letter states that plaintiff seeks “no less than $1,497,466.80.” See Doc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arbaugh v. Y & H Corp.
546 U.S. 500 (Supreme Court, 2006)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Scott Aviation v. The United States
953 F.2d 1377 (Federal Circuit, 1992)
Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
Donald A. Henke v. United States
60 F.3d 795 (Federal Circuit, 1995)
Steel Co. v. Citizens for a Better Environment
523 U.S. 83 (Supreme Court, 1998)
Rebish v. United States
120 Fed. Cl. 184 (Federal Claims, 2015)
Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)
Cerner Corp. v. Visicu, Inc.
469 F. App'x 903 (Federal Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
State Corps v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-corps-v-united-states-uscfc-2015.