Southern Cotton-Oil Co. v. Heflin

99 F. 339, 39 C.C.A. 546, 1900 U.S. App. LEXIS 4146
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 23, 1900
DocketNo. 843
StatusPublished
Cited by14 cases

This text of 99 F. 339 (Southern Cotton-Oil Co. v. Heflin) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Cotton-Oil Co. v. Heflin, 99 F. 339, 39 C.C.A. 546, 1900 U.S. App. LEXIS 4146 (5th Cir. 1900).

Opinion

SHELBY, Circuit Judge,

after stating the case as above, delivered the opinion of the court.

This is a suit for damages for breach of a contract. The material question in the case relates to the measure of damages. By the contract dated April 12, 1894, the Southern Cotton-Oil Company, the plaintiff in error, sold to E. L. Heflin, the defendant in error, all the prime cotton-seed cake and meal made at the mill of the former at Houston, Tex., during the season beginning on September 1, 1894, and ending on March 31, 1895, at $18 a ton of 2,000 pounds, free on board cars at Houston. The plaintiff guarantied a minimum quantity of 6,000 tons, and Heflin was not required to receive more than 10,000 tons. The cake and meal were to be packed in good,' merchantable sacks, and marked or branded as ordered. The defendant agreed that the plaintiff should not be without shipping orders at any time longer than 10 days, and that for any excess (over 10 days) he should pay both interest and insurance to the date of the orders. 2,084 tons of meal were delivered by the plaintiff to the defendant under the contract, and were duly paid for. 1,904 tons weré afterwards delivered in like manner, but Heflin claimed that the meal was not prime, and paid only $15 a ton for it. 6,012 tons were afterwards made, and tendered by the plaintiff to the defendant under the contract, which the latter refused to take, and the meal was then sold by the former at public sale, after notice to the latter, and it brought the then market price of $11.50-a ton. The plaintiff was engaged in the business, and had been for several years, of producing oil, meal, hulls, and lint from cotton seed. The 6,012 tons of meal were made after notice by the defendant to the plaintiff that the meal would not be received.

The first count in the declaration is for the difference between $15' a ton and $18 a ton on the 1,904 tons delivered under the contract, but not fully paid for. The plaintiff, under the ruling of the circuit court, had verdict and judgment for the difference, $5,712, with interest, and the questions relating to that breach of the contract are eliminated. There is also a count for damages for the failure and refusal of the defendant to accept the 6,012 tons, the price of which, by the contract, being $18 a ton. The plaintiff sold it, after notice to the defendant, at auction, for $11.50 a ton, which is shown to have been the market price. The plaintiff claimed and sued for $39,047.94, the difference between the contract price and the market price. The plaintiff' recovered nothing on this count in [343]*343its declaration. The learned judge who presided in the circuit court was of opinion, and so instructed the jury, that the difference between the contract price and the market price of tlie 6,012 tons was not the proper measure of damages. The correct measure of damages, the learned judge held, was the profit which the plaintiff would have made if the defendant had received the meal at the contract price. The jury was, therefore, instructed to disregard the claim for $39,047.94. The court also held, in effect, that the defendant’s notice to the plaintiff that he would not accept the meal ended the contract. The idea is that the damages must be fixed by the condition of things at the date of the notice, because the notice itself was a breach of the contract. It is true that the plaintiff could have acted on the notice, and treated it as terminating the contract; hut it was not compelled to do so. It had the right to hold to the contract as still in force, and tender the meal according to the contract. If the plaintiff had been building a house for the defendant, or cleaning and repairing paintings for him, or, to use a comprehensive phrase, if his contract had been one to do work and labor, an unequivocal notice to quit work would have fixed the period of the breach and the time from which to assess damages. But the contract was an executory contract of sale, and the purchaser cannot, by his action alone, deprive the vendor of any of the benefits of such contract. In such case the refusal of the purchaser to take the goods must be unequivocal, and “must have been acted on by the plaintiff”; otherwise, the refusal in advance of the time for delivery does not fix the period for assessing the damages. In Smoot’s Case, 15 Wall. 36, 48, 21 L. Ed. 107, the court, quoting Benjamin on Sales, said:

“A mere assertion that the party will be unable or will refuse to perform hig contract is not sufficient. It must he a distinct and unequivocal absolute refusal to perform the promise, and must be treated and acted upon as such by the party to whom the promise was made; for, if he afterwards continue to urge or demand a compliance with the contract, it is plain that he docs not understand it to be at an end.”

The supreme court, in the case cited, in commenting on the English decisions, clearly affirmed the rule that, in the case of an executory contract of sale, where the defendant had agreed to receive and pay for wrheat, and who gave notice that he would not receive it, the measure of damages would not be governed by the price of wheat at the time of the notice, hut by its value at the time of the tender. Tn the case of Dingley v. Oler, 117 U. S. 490, 503, 6 Sup. Ct. 854, 29 L. Ed. 988, the court says:

“The words or conduct relied on as a breach of the contract by anticipation must amount to a total refusal to perform It; and that does not, by itself, amount to a breach of the contract unless so acted upon and adopted by tlu; other party.”

When the defendant gave notice that he would not receive the meal, he could not have complained if the plaintiff had acted upon the notice, and sued "him at once. But he could not require t:he plaintiff to recede from its contract. The plaintiff had a vested right in the contract to deliver the meal sold at the time fixed by the agree[344]*344ment, and no notice of the defendant could deprive it of this right. •This seems well settled by authority. Kadish v. Young, 108 Ill. 175, 178; Railway Co. v. Kichards, 152 Ill. 69, 100, 38 N. E. 773, 30 L. R. A. 33; Marks v. Van Eeghen, 30 C. C. A. 208, 85 Fed. 855; Sedg. Dam: (6th Ed.) § 284; Zuck v. McClure, 98 Pa. St. 541; Cooper v. Young, 22 Ga. 269.

The contention of the plaintiff is that the proper measure of dam-. ages is the difference between the market value of the cotton-seed meal and the contract price. If this contention is right, the instructions given to the jury were erroneous. The learned counsel for the defendant correctly says:

. “It is not tbe concern of tbe defendant to define and maintain, as applicable to tbe case presented, tbe true measure of damages. It is enough for bina to .meet tbe claim of tbe plaintiff that tbe measure contended for by it is tbe true one.”

It is not denied, however, by counsel for defendant, that on proper suit the plaintiff was entitled to damages in some measure for the breach in question. The learned judge who tried the case in the circuit court so held. He directed a verdict against the plaintiff as to the breach in question, because it had mistaken the measure of damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bomberger v. McKelvey
220 P.2d 729 (California Supreme Court, 1950)
Rocky Brook Mills Co. v. United States
70 Ct. Cl. 646 (Court of Claims, 1930)
Solomon v. Waterbury Brass Goods Corp.
6 F.2d 990 (Second Circuit, 1925)
Alabama Grocery Co. v. Hammond
285 F. 723 (Fifth Circuit, 1922)
Anderson v. United States
51 Ct. Cl. 228 (Court of Claims, 1916)
Wheeler v. Krohn, Fechheimer & Co.
64 So. 179 (Alabama Court of Appeals, 1913)
Hopkinsville Milling Co. v. Gwin
60 So. 270 (Supreme Court of Alabama, 1912)
Jebeles & Colias Confectionery Co. v. Stephenson
60 So. 437 (Alabama Court of Appeals, 1912)
Willoughby v. Jernigan
60 So. 514 (Alabama Court of Appeals, 1912)
In re Bellevue Pipe & Foundry Co.
189 F. 169 (N.D. Ohio, 1910)
Malcomson v. Reeves Pulley Co.
167 F. 939 (Sixth Circuit, 1909)
Kinkead v. Lynch
132 F. 692 (U.S. Circuit Court for the District of Nevada, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
99 F. 339, 39 C.C.A. 546, 1900 U.S. App. LEXIS 4146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-cotton-oil-co-v-heflin-ca5-1900.