Anderson v. United States

51 Ct. Cl. 228, 1916 U.S. Ct. Cl. LEXIS 67, 1916 WL 1092
CourtUnited States Court of Claims
DecidedApril 24, 1916
DocketNo. 30021
StatusPublished

This text of 51 Ct. Cl. 228 (Anderson v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. United States, 51 Ct. Cl. 228, 1916 U.S. Ct. Cl. LEXIS 67, 1916 WL 1092 (cc 1916).

Opinion

Campbell, Chief Justice,

reviewing the facts found to be established, delivered the opinion of the court:

The plaintiff made a contract with the United States, dated May 24, 1905, to deliver 20,000 barrels of cement, half of it to be delivered and used at Grande Island and the other half at Corregidor Island. The prices for the cement delivered in accordance with the specifications are stated in the contract. Section 50 of the specifications provides that the cement will be accepted in lots of from 1,000 barrels to 5,000 barrels at each place.” The first delivery at Corregidor was to be made in October, 1905, and at Grande Island in November, 1905, and it was provided that if delivered in lots of 5,000 barrels the second delivery would be made for each place four months after the first. If deliveries were in lots of less than 5,000 barrels, the second delivery would be made as many months after the first as there were thousands [232]*232of barrels in the first lot and thereafter at the rate of 1,500 barrels for each place. In making his bid the plaintiff indicated a desire to deliver the cement in lots of 2,000 barrels at a time. The first delivery requested by defendants was made in October, 1905, of 1,000 barrels. It was accepted and paid for by defendants. No other cement was ordered until March 6, 1906, when plaintiff was directed to deliver 2,000 barrels at Corregidor. It appears that the Government’s delay in ordering cement was occasioned by the facts that they did not receive the lumber to make the necessary forms, the vessel carrying the same having been lost at sea, and on account of climatic conditions the cement could not be safely stored at said islands. The plaintiff was at all times ready to make deliveries according to his contract and offered to do so. He transported and tendered the 2,000 barrels ordered in March, but the defendants could receive only 1,740 barrels of it for lack of barge space, and 260 barrels were accordingly left on plaintiff’s hands and were by him returned to Hongkong at the expense of freight and handling. The 1,740 barrels of cement, less 153 barrels which had been used, were subsequently rejected and replaced as hereinafter stated. No other shipments were ordered. The period during which the plaintiff was to make deliveries at the two places expired in April and May, 1906. He was not at fault, and the defendants were at fault in their failure to order and accept the cement. They breached the contract.

1. The item of $2,364.62 is claimed as damages representing a loss to plaintiff because of the breach of the contract, he claiming that if he had been permitted to perform he would have made a profit in the transaction to the amount of said sum.

In a case like this the plaintiff is entitled to recover the difference between what it would have cost him to perform and the contract price, if the latter exceeds the former. The general rule as to the measure of damages where a vendor sues on account of the purchaser’s failure to accept the goods is that he may recover the difference between the contract price and the market price at the time and place of delivery. But this rule is not a rigid one to the exclusion of any other [233]*233method of ascertaining the amount of the damages, and must be accommodated to exigencies of the particular case. Salem Iron Co. v. Lake Superior Mines, 112 Fed., 239; Southern Cotton Oil Co. v. Heflin, 99 Fed., 339, 347. It may frequently happen that there is no open market at the place of delivery, and while in such case it may be competent to show the market value at some near-by place or by other circumstances to determine the amount of damages, the fact that such proof is allowable but illustrates the view that the rules of law as to the measure of damages are not intended to deprive a plaintiff of a remedy when he may be unable to show the market value of the goods at a particular time or place. Eesort may be had to other forms of proof. The purpose of the law is to recognize his right to recover for a breach of the contract an amount that will reasonably and properly compensate him for his loss occasioned as a direct and proximate consequence of the breach. What the plaintiff lost was the equivalent of what his gain would have been if permitted to perform the contract. In other words, he lost the profits which a full performance would have brought to him. It is inferable from the facts that defendants had notice'that plaintiff expected to purchase cement with which to comply with his proposal and contract. He resided at Manila and was proposing to furnish a brand of cement manufactured near Hongkong. Whether such notice may be inferred or not, the fact is that plaintiff, after his bid was accepted, made a contract with the manufacturer of the “ Emerald ” brand to furnish him the cement necessary to meet the requirements of his contract with defendants. His evidence shows that said manufacturer was a responsible party who would have furnished the cement to plaintiff at a price which would have enabled him to fulfill his contract with defendants and have earned a profit of 13.7 cents per barrel. The deliveries were to be made in installments and at two different places—some at Grande Island and some at Corregidor Island or on barges at Manila. It would be difficult if not impossible to show what the market value of the cement was at the several times and places at which deliveries were to be made. It is not shown and it would be un[234]*234reasonable to infer that the plaintiff had on hand during the contract period the full amount of 17,240 barrels of cement awaiting orders of the engineer officer to make deliveries. The contract did not contemplate that he would have or hold the cement at hand, but rather that as and when notified that shipments were wanted he would comply, and this seems to have been the course of dealing in the matter by the parties. He was at all times ready and willing to make deliveries accordingly.

The familiar rule above stated as to the measure of damages is not in such case as satisfactory as the one which would enable proof to be made of the actual loss suffered by plaintiff. To prove what he would have earned, it is competent for him to show that he had in good faith made a contract with a responsible manufacturer to furnish him the cement at a definite price which would have enabled him to make deliveries at a profit over and above what the cement and its delivery would have cost him, and having made that proof the difference between what he would have paid for the cement, including the cost to him of its delivery, and what he would have received for it “is manifestly the amount of the loss actually suffered, and therefore must be the correct measure of damages recoverable.” Horst v. Roehm,, 84 Fed., 565, 571; Roehm v. Horst, 178 U. S., 1, 21; Danforth v. Walker, 87 Vt., 239.

The contention of the defendants that plaintiff could have taken the cement under his contract with the manufacturer and sold it for more than he would have received from defendants because it had advanced in price is without merit in this case. There was no duty upon him under the circumstances to do that in order to relieve the defendants of the consequences of their own default.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roehm v. Horst
178 U.S. 1 (Supreme Court, 1900)
Camp v. Barber
88 A. 812 (Supreme Court of Vermont, 1913)
Southern Cotton-Oil Co. v. Heflin
99 F. 339 (Fifth Circuit, 1900)
Horst v. Roehm
84 F. 565 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
51 Ct. Cl. 228, 1916 U.S. Ct. Cl. LEXIS 67, 1916 WL 1092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-united-states-cc-1916.