Southeastern Connecticut Regional Resources Recovery Authority v. Department of Public Utility Control

709 A.2d 549, 244 Conn. 280, 1998 Conn. LEXIS 94
CourtSupreme Court of Connecticut
DecidedMarch 31, 1998
DocketSC 15666
StatusPublished
Cited by21 cases

This text of 709 A.2d 549 (Southeastern Connecticut Regional Resources Recovery Authority v. Department of Public Utility Control) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeastern Connecticut Regional Resources Recovery Authority v. Department of Public Utility Control, 709 A.2d 549, 244 Conn. 280, 1998 Conn. LEXIS 94 (Colo. 1998).

Opinion

Opinion

CALLAHAN, C. J.

This is an appeal from a judgment of the trial court sustaining the plaintiffs’1 appeal from a ruling by the named defendant, the department of public utility control (department), issued in response to a request for resolution of a payment dispute by the defendant Connecticut Light and Power Company, and from the department’s ruling on the petition for a declaratory ruling by the plaintiffs.2 The sole issue on appeal is whether the defendant is obligated to pay the contractually established “Average Municipal Retail Rate” for [282]*282electrical output produced by the plaintiffs that is in excess of 13.85 megawatts (MW). We conclude that the defendant is so obligated.

The relevant facts are undisputed. The defendant is an electric company as defined by General Statutes § 16-1 (a) (8)3 that is required to purchase electricity from the plaintiffs. The plaintiffs are the owners and operators of a resource recovery facility (facility), as defined by General Statutes § 22a-260 (ll),4 located in Preston, which produces electric energy from solid waste.

Prior to the construction of the facility, the plaintiffs and the defendant entered into an electrical energy purchase agreement (agreement) whereby the defendant agreed to purchase the entire output of electrical energy from the plaintiffs’ facility. The parties entered into the agreement pursuant to General Statutes (Rev. to 1989) § 16-243e.5 6Section 16-243e requires an electric [283]*283company that purchases electricity generated by a resource recovery facility owned or operated by or for the benefit of a municipality to enter into a contract, with a minimum duration of twenty years, in which the electric company agrees to purchase the electricity generated by the facility “at the same rate that the electric company charges the municipality or municipalities for electricity,” referred to generically as the “municipal rate.”

This case is the second appeal to this court in the continuing saga between these parties concerning this agreement and the meaning of § 16-243e. By way of background, in 1987, the parties entered into the statutorily mandated agreement and obtained approval of the agreement from the department. Southeastern Connecticut Regional Resources Recovery Authority, Department of Public Utility Control, Docket No. 87-06-12 (October 6, 1987). In its ruling approving the agreement, the department mandated that the defendant pay the municipal rate for the facility’s entire output of electricity. Id. The defendant appealed to the [284]*284Superior Court, challenging the constitutionality of § 16-243e and the department’s interpretation of that statute.6 Upon consideration of a reserved question from the trial court, we concluded that the defendant was obligated by § 16-243e to pay the municipal rate for only that portion of the electrical output attributable to waste that is obtained by the facility from municipalities within the defendant’s franchise area (franchise waste), i.e., those towns in which it serves customers.7 Connecticut Light & Power Co. v. Dept. of Public Utility Control, 210 Conn. 349, 357-58, 554 A.2d 1089 (1989). We reached that conclusion because we determined that § 16-243e requires an electric company that pinchases electricity from a resource recovery facility that is owned or operated by or for the benefit of a municipality or municipalities to pay the same rate that the electric company charges the municipalities for electricity. Id. If a municipality is not within the electric company’s franchise area, then, a fortiori, the electric company [285]*285does not charge that municipality for electricity. Consequently, we concluded that § 16-243e is not applicable to electrical output that is attributable to nonfranchise waste. Id.

We further concluded, however, that an electric company is required to purchase the entire electrical output of a resource recovery facility. Id., 358. Accordingly, it was necessary at that time to ascertain the applicable rate payable for electrical output attributable to non-franchise waste. The facility, in addition to being a resource recovery facility, is also a private power producer within the meaning of General Statutes § 16-243b (a) (3).8 General Statutes § 16-243a (b)9 requires an electric company to purchase the entire output of a private power producer.10 Section 16-243a (c) 11 provides that an electric company need pay only its “avoided costs” rate for energy purchased from a private power producer. We interpreted the foregoing statutes to require that the defendant: (1) purchase the entire electrical output of the facility; (2) pay the municipal rate as established in § 16-243e for the electrical output attributable to franchise waste; and (3) pay the avoided cost rate of § 16-243a (c) (2) for electrical output attributable [286]*286to nonfranchise waste.12 Connecticut Light & Power Co. v. Dept. of Public Utility Control, supra, 210 Conn. 358.

The plaintiffs’ facility became operational in January, 1992, and began producing and providing electricity pursuant to the agreement between the parties at that time. The agreement incorporated by reference a description of the facility that included specifications, which stated that the facility’s electrical output would be approximately 13.85 MW based on approximately 600 tons of waste processed per day.13 When the plaintiffs notified the defendant that the facility was com-[287]*287píete and ready to begin supplying electricity, they also gave notice that its output would be 13.91 MW and that the energy output and waste throughput were expected to increase owing to operational improvements. Upon receiving that notice, the defendant acknowledged that “all Prerequisites for Purchase under the Contract were satisfied on [January 5, 1992].”

Soon after the facility became operational, it began to generate more than an average of 13.85 MW on an hourly basis.14 It did not, however, exceed 13.85 MW on a monthly average until significantly later. The defendant does not dispute that it has a statutory obligation, incorporated into the agreement, to purchase all of the facility’s energy output, even that above the 13.85 MW level. It does challenge, however, its obligation to pay the contract price, i.e., the municipal rate, for production in excess of 13.85 MW. In January, 1993, the defendant filed with the department a request for resolution of a payment dispute.15 In its request, the defendant argued that the output in excess of 13.85 MW, measured [288]*288on an hourly basis, was not covered by the agreement and, therefore, that it was obligated to pay only the significantly lower “current avoided costs” rate for any electrical output in excess of that figure.16

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Suffolk Constr. v. Reliance Ins. Apl of: Suffolk
Supreme Court of Pennsylvania, 2019
CCT Communications, Inc. v. Zone Telecom, Inc.
172 A.3d 1228 (Supreme Court of Connecticut, 2017)
Grovenburg v. Rustle Meadow Associates, LLC
165 A.3d 193 (Connecticut Appellate Court, 2017)
Genua v. Logan
982 A.2d 1125 (Connecticut Appellate Court, 2009)
Goldberg v. Hartford Fire Insurance
849 A.2d 368 (Supreme Court of Connecticut, 2004)
Poole v. City of Waterbury
831 A.2d 211 (Supreme Court of Connecticut, 2003)
First Providence Financial Group v. Burke, No. Cv-01-506208s (Nov. 15, 2001)
2001 Conn. Super. Ct. 15423 (Connecticut Superior Court, 2001)
Anchor Elect. Contractors v. Waterbury, No. Cv 98-582103-S (Oct. 25, 2001)
2001 Conn. Super. Ct. 14211 (Connecticut Superior Court, 2001)
Office of Consumer Col. v. the Ct. Dpuc, No. Cv 99 0497238s (Sep. 21, 2001)
2001 Conn. Super. Ct. 13309 (Connecticut Superior Court, 2001)
Christian v. Gouldin, No. Cv99-0155219s (Jan. 30, 2001)
2001 Conn. Super. Ct. 1768 (Connecticut Superior Court, 2001)
Southbury Land Trust, Inc. v. Andricovich
757 A.2d 1263 (Connecticut Appellate Court, 2000)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)
Wichers v. Hatch
745 A.2d 789 (Supreme Court of Connecticut, 2000)
Bolivar v. Blue Ridge Insurance Co., No. Cv98 035 35 22 (Oct. 19, 1999)
1999 Conn. Super. Ct. 13790 (Connecticut Superior Court, 1999)
Devito v. Defrancesco, No. Cv 99 0171842s (Aug. 4, 1999)
1999 Conn. Super. Ct. 10705 (Connecticut Superior Court, 1999)
Gardiner v. Town of Fairfield
51 F. Supp. 2d 158 (D. Connecticut, 1999)
Pratt v. Aetna Life Ins. Co., No. Cv-96-0560740-S (Mar. 26, 1999)
1999 Conn. Super. Ct. 3575 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
709 A.2d 549, 244 Conn. 280, 1998 Conn. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeastern-connecticut-regional-resources-recovery-authority-v-conn-1998.