Anchor Elect. Contractors v. Waterbury, No. Cv 98-582103-S (Oct. 25, 2001)

2001 Conn. Super. Ct. 14211
CourtConnecticut Superior Court
DecidedOctober 25, 2001
DocketNo. CV 98-582103-S
StatusUnpublished

This text of 2001 Conn. Super. Ct. 14211 (Anchor Elect. Contractors v. Waterbury, No. Cv 98-582103-S (Oct. 25, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchor Elect. Contractors v. Waterbury, No. Cv 98-582103-S (Oct. 25, 2001), 2001 Conn. Super. Ct. 14211 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
Presently before the court are objections to the findings of fact issued by a fact finder pursuant to General Statutes § 52-549n.1 The plaintiff, Anchor Electrical Contractors, Inc., filed a one-count complaint arising out of contract for electrical work at the New South End Elementary School in the City of Waterbury. The dispute involves two particular items which the plaintiff has claimed as change orders and which defendant claims were required under the terms of the contract.

The matter was referred to a fact finder pursuant to § 52-549n.2 Following a two-day hearing, on August 28, 2000, the fact finder issued a report to the court finding in favor of the plaintiff and recommending a total award of $32,393.87. After the time was extended by the court (Langenbach, J.), the defendant filed objections to the findings of fact pursuant to General Statutes § 52-549s(a)3 which the plaintiff opposes. CT Page 14212

Following is a summary of the findings of fact: The plaintiff seeks recovery for what it characterizes as the defendant's request for two change orders: (1) a change order relating to the use of steel conduit under slab areas as opposed to plastic (PVC) conduit; and (2) a change order involving the tie back and securing of certain light fixtures.

With respect to the steel conduits, the plaintiff seeks $22,733.87 for labor, material, overhead and profit after being required by the project manager to use steel conduit instead of PVC conduit under concrete slab. The plaintiff claimed that the contract specifications only required the use of PVC under slab areas as opposed to the more expensive steel conduit.

In an effort to resolve the disputed claims of the parties, the fact finder reviewed the contract to determine whether the contract specifications called for the use of PVC or steel conduit under slab areas. The fact finder found a conflict in the specification provisions that could not be clarified or harmonized within the four corners of the contract between the material specified in the "Execution and Installation" section of the contract which called for the use of PVC (plastic) conduit and that specified in the "Product" section of the contract which called for the use of rigid steel conduit. The fact finder thereafter interpreted the contract and determined that the plaintiff's interpretation was permissible, reasonable and supported by credible corroborating testimony to the effect that it is common industry practice to use plastic conduit in sub-surface environments and also to look to the installation section of the specifications to determine the products called for in a given location. Accordingly, the fact finder awarded the plaintiff the requested damages.

With respect to the tie backs, the plaintiff sought $9,660 in compensation for labor, overhead and profit to attach tie wires to fixtures at the request of the project manager. The fact finder reviewed the contract specifications and determined, that based on the more credible evidence, that the tie backs were the responsibility of the ceiling contractor and were therefore not contemplated by the plaintiff's bid. The fact finder further found that the project manager requested the plaintiff to undertake the tie back work in consideration for extra compensation. Accordingly, the fact finder awarded the plaintiff its requested relief further finding that an award of statutory interest was not warranted by the circumstances.

Standard of Review
"A reviewing authority may not substitute its findings for those of the CT Page 14213 trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . . or the Superior Court reviewing the findings of . . . attorney trial referees. . . . This court has articulated that attorney trial referees and factfinders share the same function . . . whose determination of the facts is reviewable in accordance with well established procedures prior to the rendition of judgment by the court." (Citations omitted; internal quotation marks omitted.) Elgar v. Elgar, 238 Conn. 839, 848, 679 A.2d 937 (1996). "In a contract action, findings of fact should be overturned only when they are clearly erroneous." Wilcox Trucking, Inc. v. MansourBuilders, Inc., 20 Conn. App. 420, 425, 567 A.2d 1250 (1989), cert. denied, 214 Conn. 804, 573 A.2d 318 (1990).

I
The defendant's first challenge to the findings is advanced with respect to the fact finder's interpretation of the contract. "The fact finder erred in granting conditional admissibility of extrinsic evidence . . . and that [the] evidence allowed in `conditionally' . . . ultimately persuaded the [fact finder] that the contract was ambiguous." (Defendant's Objections, p. 14.) In other words, the defendant's challenge is to the fact finder's finding that the contract was ambiguous because, it is claimed, that in coming to that conclusion the fact finder impermissibly relied on conditionally admitted evidence. The plaintiff claims that the record independently of the extrinsic evidence supports the finding that the contract was ambiguous.

"Although ordinarily the question of contract interpretation, being a question of the parties' intent, is a question of fact . . . [w]here there is definitive contract language, the determination of what the parties intended by their contractual commitments is a question of law. . . ." (Citations omitted; internal quotation marks omitted.)Tallmadge Bros. v. Iroquois Gas Transmission System,252 Conn. 479, 495, 746 A.2d 1277 (2000). "Where the language of the contract is clear and unambiguous, the contract is to be given effect according to its terms." (Internal quotation marks omitted.) Southeastern Connecticut Regional ResourcesRecovery Authority v. Dept. of Public Utility Control,244 Conn. 280, 291, 709 A.2d 549 (1998). Where a contract term is ambiguous extrinsic evidence is admissible to assist the court in resolving the question of the parties' intent." Cody v. RemingtonElectric Shavers, 179 Conn. 494, 500, 427 A.2d 810 (1980).

"Contract language is unambiguous when it has a definite and precise meaning . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cody v. Remington Electric Shavers
427 A.2d 810 (Supreme Court of Connecticut, 1980)
City of Groton v. Yankee Gas Services Co.
620 A.2d 771 (Supreme Court of Connecticut, 1993)
Elgar v. Elgar
679 A.2d 937 (Supreme Court of Connecticut, 1996)
Parsons v. United Technologies Corp.
700 A.2d 655 (Supreme Court of Connecticut, 1997)
Levine v. Advest, Inc.
714 A.2d 649 (Supreme Court of Connecticut, 1998)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)
Wilcox Trucking, Inc. v. Mansour Builders, Inc.
567 A.2d 1250 (Connecticut Appellate Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 14211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchor-elect-contractors-v-waterbury-no-cv-98-582103-s-oct-25-2001-connsuperct-2001.