Niagara Mohawk Power Corporation v. Federal Energy Regulatory Commission, Independent Power Producers of New York, Inc., Intervenors

117 F.3d 1485, 326 U.S. App. D.C. 135, 1997 U.S. App. LEXIS 17369
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 11, 1997
Docket95-1222, 95-1223, 95-1298, 95-1299, 95-1302, 95-1303 and 95-1309
StatusPublished
Cited by11 cases

This text of 117 F.3d 1485 (Niagara Mohawk Power Corporation v. Federal Energy Regulatory Commission, Independent Power Producers of New York, Inc., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Niagara Mohawk Power Corporation v. Federal Energy Regulatory Commission, Independent Power Producers of New York, Inc., Intervenors, 117 F.3d 1485, 326 U.S. App. D.C. 135, 1997 U.S. App. LEXIS 17369 (D.C. Cir. 1997).

Opinion

Opinion for the Court filed by Circuit Judge GINSBURG.

GINSBURG, Circuit Judge:

Petitioners seek review of two declaratory orders of the Federal Energy Regulatory Commission interpreting the Public Utility Regulatory Policies Act (PURPA), 16 U.S.C. § 824a-3. Because the two orders do nothing more than set out the position that the Commission would take in an enforcement action before the district court, we are without jurisdiction to review them.

I. Background

In June 1987 the Southeastern Connecticut Regional Resources Recovery Authority, a political subdivision of the State of Connecticut chartered to dispose of municipal waste, petitioned the Connecticut Department of Utility Control (CDUC) for a declaration that § 16-243e of the Connecticut General Statutes required the Connecticut Light and Power Company (CL&P) to purchase electricity from a cogeneration facility operated by the Authority at the rate the utility charges a municipality for electricity. The CDUC ordered CL&P to pay the municipal rate, as the statute clearly commands.

CL&P appealed this decision to the Supreme Court of Connecticut, arguing that the PURPA preempts § 16-243e, at least insofar as the Connecticut statute would require a utility to pay more for electricity than its avoided cost. The Court held that the CDUC had misapplied § 16-243e and remanded the matter for the agency to recalculate the rate. Connecticut Light & Power Co. v. Department of Public Utility Control, 210 Conn. 349, 554 A.2d 1089 (1989). The Court did not address CL&P’s claim of preemption.

Believing that the rate calculated by the CDUC on remand still exceeded its avoided cost, CL&P sued the Authority in federal district court seeking a declaratory judgment that the PURPA preempts § 16-243e. Applying' the doctrine of primary jurisdiction, *1487 the district court stayed the proceeding for CL&P first to seek a declaratory ruling from the FERC. Connecticut Light & Power Co. v. South Eastern [sic] Connecticut Regional Resources Recovery Authority, 822 F.Supp. 888 (D.Conn.1993). CL&P duly petitioned the FERC for an answer to the question: “Does federal law preempt the application of § 16-243e of the Connecticut General Statutes to CL&P either in all circumstances or as § 16-243e has been applied in the context of the resources recovery facility of the Southeastern Regional Resources Recovery Authority located in Preston, Connecticut?” Connecticut Light & Power Co., 70 FERC ¶ 61,012 (January 11, 1995).

The Commission declared that the PURPA preempts§ 16-243& Id. Section 210(f) of the PURPA requires the Commission to ensure that the rate a utility pays to a eogener-ator is no higher than the utility’s avoided cost. See § 824a-3(b) (“No such rule prescribed under subsection (a) of this section shall provide for a rate which exceeds the incremental cost to the electric utility of alternative electric energy”), and 824a-3(d) (defining incremental cost); American Paper Institute Inc. v. American Electric Power, 461 U.S. 402, 406, 103 S.Ct. 1921, 1924, 76 L.Ed.2d 22 (1983) (PURPA and implementing regulations “requirfe] a utility to purchase electricity from a [qualified facility] at a rate equal to the utility’s full avoided cost.”) According to the Commission, the PURPA gives the States responsibility only for “implementing” the rules promulgated by the Commission, citing § 824a-3(f); it does not authorize the States to override or to subvert those rules, as § 16-243e would do.

The Commission also declared that it would not apply its newly-announced preemption analysis to invalidate contracts that had not previously been challenged on the ground of preemption. “The appropriate time to challenge a state-imposed rate,” the Commission reasoned, “is up to or at the time the contract is signed, not several years into a contract which heretofore has been satisfactory to both parties.”

The Authority requested rehearing of the preemption issue. Niagara Mohawk also petitioned for rehearing, arguing that the Commission should apply its decision to all contracts regardless whether they had previously been challenged on the ground of preemption. The Commission denied both petitions, Connecticut Light & Power Co., 71 FERC¶61,035 (April 12, 1995), and both petitioners now seek review before this court. *

Niagara Mohawk also seeks review of the FERC’s decision in Orange & Rockland Utilities, Inc., 70 FERC ¶ 61,014 (January 11, 1995), vacating 43 FERC ¶ 61,067 (April 14, 1988). Orange and Rockland originally petitioned the Commission for a declaration that the PURPA preempts § 66-c of the New York Public Service Law, which set a minimum rate of six cents per kilowatt-hour for electricity generated by a eogenerator. Niagara Mohawk intervened in support of Orange and Rockland. In 1988 the Commission issued an order declaring that a State may not impose a rate that exceeds a utility’s avoided cost, 43 FERC ¶ 61,067, but stayed the order pending judicial review and resolution of a related rulemaking. Orange & Rockland Utilities, 43 FERC¶ 61,546 (June 16, 1988). In 1992 New York repealed the six-cent provision prospectively. See N.Y. Pub. Serv. L. § 66-C.1-2 (McKinney Supp. 1993). Because the stayed order would have acted only prospectively, the Commission then vacated it as moot. 70 FERC ¶ 61,014.

II. Analysis

The Commission argues, among other things, that we are without jurisdiction to review the challenged orders because they do nothing more than announce the interpretation of the PURPA upon which the Commission would rely in an enforcement action. The orders do not determine any factual question, such as “whether the rates ... do or do not exceed avoided cost.” Nor are they binding upon the district court in which *1488 any enforcement action might be pursued. The Commission maintains that, in order to avoid usurping the role assigned to the district courts in the elaborate enforcement scheme established in § 210 of the PURPA, we must conclude, as we did in Industrial Cogenerators v. FERC, 47 F.3d 1231 (D.C.Cir.1995), that the Congress did not confer jurisdiction upon the courts of appeals to review a declaratory order in which the FERC interprets the PURPA.

The petitioners counter that Industrial Co-generators is inapplicable because each of the orders challenged here announces a rule of general application and not, as in the earlier case, a decision limited to a specific set of facts. “[Njothing in Industrial Cogenera-tors,”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
117 F.3d 1485, 326 U.S. App. D.C. 135, 1997 U.S. App. LEXIS 17369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/niagara-mohawk-power-corporation-v-federal-energy-regulatory-commission-cadc-1997.