Sierra Pacific Power Company and Idaho Power Company v. United States Environmental Protection Agency

647 F.2d 60, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20671, 16 ERC (BNA) 1313, 1981 U.S. App. LEXIS 12596
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 5, 1981
Docket79-7542, 80-7301
StatusPublished
Cited by15 cases

This text of 647 F.2d 60 (Sierra Pacific Power Company and Idaho Power Company v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Pacific Power Company and Idaho Power Company v. United States Environmental Protection Agency, 647 F.2d 60, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20671, 16 ERC (BNA) 1313, 1981 U.S. App. LEXIS 12596 (9th Cir. 1981).

Opinion

BOOCHEVER, Circuit Judge:

This case involves the applicability of the anti-pollution requirements of the Clean Air Act, section 111 (42 U.S.C. § 7411), and the regulations promulgated under that section. Sierra Pacific Power Company and Idaho Power Company appeal Environmental Protection Agency (EPA) decisions holding that Unit 2 of their coal-fired power plant must conform to the stringent anti-pollution regulations promulgated by the EPA in 1978. The power companies argue that they had “commenced construction” of Unit 2 prior to September 19, 1978, and are therefore exempt from proposed standards promulgated on that date. The EPA interpreted its regulations to require actual physical construction of or a binding construction contract for Unit 2, independent of Unit 1, prior to the relevant regulatory date, and refused to consider planning and design activity. Because the EPA did not abuse its discretion in so interpreting its regulations, we affirm.

FACTS

Sierra Pacific Power Company and Idaho Power Company (Sierra Pacific) are jointly constructing 1 a coal-fired electric power plant at North Valmy Station in Humboldt County, Nevada. The plant consists of two boilers (Unit 1 and Unit 2) which are located at the same site and share common equipment. In two separate decisions, the EPA determined that Sierra Pacific had not “commenced construction” on Unit 2 before September 19, 1978, the date the EPA proposed new, more restrictive regulations. The EPA therefore determined that Sierra Pacific would have to meet the more stringent air pollution equipment requirements contained in the proposed regulations. Unit 1 is exempt from the 1978 regulations because construction of that unit was commenced prior to September 19,1978. Sierra Pacific has appealed the Unit 2 EPA determinations directly to this court pursuant to 42 U.S.C. § 7607(b)(1). 2

A. Statutory and Regulation Background

In 1970, Congress extensively amended the Clean Air Act of 1955, for the first time enacting a comprehensive program to combat air pollution at both the state and federal level. Pub.L.No. 91-604, 84 Stat. 1676 (1970). Section 111 of the Act authorized the EPA to issue regulations for new stationary sources of air pollution, which would include such facilities as power plants. In 1971, the EPA issued “new source performance standards” for coal-fired power plants such as Sierra Pacific’s, requiring the use of either a high-grade *? (low sulfur) type of coal, or the installation of flue gas desulfurization equipment, commonly called “scrubbers.” 3 36 Fed.Reg. 24876 (Dec. 23, 1971). Both units of Sierra Pacific’s proposed plant were originally designed to meet these requirements by burning high-grade coal, and did not contemplate scrubbers.

In 1977, Congress amended section 111 of the Clean Air Act and directed the EPA to issue regulations requiring new pollution sources to use the best adequately demonstrated technology available. Pub.L.No. 95-95 § 109, 91 Stat. 685 (1977). See H.R. Rep.No. 1175, 94th Cong., 2d Sess. 156-59 (1976). Section 111 now provides in part that “[a]ny new or modified fossil fuel fired stationary source which commences construction prior to the date of publication of the proposed revised standards shall not be required to comply with such revised standards.” 42 U.S.C. § 7411(b)(6) (emphasis added). On September 19, 1978, the EPA published the proposed revised standards, 4 which, in effect, required scrubbers on all coal-fired power plants above a certain size. 43 Fed.Reg. 42154 et seq. (1978); 40 C.F.R. § 60.40a (1980). Because Sierra Pacific had entered into a binding construction contract for Unit 1 prior to September 19, 1978, this unit is exempt from the new regulations. The issue in this case is whether Sierra Pacific “commenced construction” on Unit 2 prior to September 19, 1978. If not, the company will be forced to install a scrubber on Unit 2.

B. History of Sierra Pacific’s Construction

Sierra Pacific initially began planning the North Valmy power plant in .1974. There is no dispute that the company planned to build both units from the very beginning. In 1975 its Board of Directors authorized construction of both units. On February 17, 1976, Sierra Pacific contracted with Babcock and Wilcox to purchase and construct the boiler for Unit 1. Sierra Pacific had an option for the purchase and construction of the Unit 2 boiler which it never exercised. Also in 1976, Sierra. Pacific prepared an environmental report which it filed with the State of Nevada. The company received certification from Nevada for the entire project in several stages in late 1976 and 1977. On December 19, 1977, it received a permit for physical, on-site construction of Unit 1 and some common facilities for both units from the Nevada Public Service Commission. Nevada Utility Environmental Protection Act, Nev.Rev.Stat. § 704.865. The state advised Sierra Pacific that it should apply for the Unit 2 permit after determination of the role Unit 2 was to play in the company’s overall load and supply program.

On April 4, 1978, the EPA issued a “prevention of significant deterioration” permit for the entire project as it was then planned, which did not include scrubbers. Issuance of such a permit merely indicates that the EPA believes the plant will not result in significant deterioration of the ambient air quality; the permit does not excuse compliance with the new source pollution standards of 40 C.F.R. Part 60. 5 On *64 September 12, 1978, Sierra Pacific appeared before the Nevada State Environmental Commission requesting a one-year extension on the expiration date for its Unit 2 construction certificate. A company representative, Mr. Saibini, told the Commission that “only preliminary design work has been done on the [Unit 2] boiler” because the company had been unable to enter into a binding contractual commitment. The request for an extension was granted, and the Unit 2 permit was finally issued on March 26,1979. Therefore, on September 18,1978, the last day to “commence construction,” the company had an on-site construction permit for Unit 1, but by its own statements was not ready to complete its application for a permit or begin actual construction on Unit 2. On April 11, 1979, Sierra Pacific contracted with the Foster Wheeler Company for the purchase of the Unit 2 boiler.

The company notified Region IX of the EPA that actual construction commenced on Unit 1 and some of the common facilities on September 11, 1978.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States House of Representatives v. Burwell
185 F. Supp. 3d 165 (District of Columbia, 2016)
Center for Biological Diversity v. Salazar
791 F. Supp. 2d 687 (D. Arizona, 2011)
Sierra Club v. Franklin County Power of Illinois, LLC
546 F.3d 918 (Seventh Circuit, 2008)
United States v. Kanchanalak
192 F.3d 1037 (D.C. Circuit, 1999)
Kester v. Campbell
652 F.2d 13 (Ninth Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
647 F.2d 60, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20671, 16 ERC (BNA) 1313, 1981 U.S. App. LEXIS 12596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-pacific-power-company-and-idaho-power-company-v-united-states-ca9-1981.