United States v. City of Painesville

431 F. Supp. 496, 10 ERC 1106, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20221, 10 ERC (BNA) 1106, 1977 U.S. Dist. LEXIS 17830
District Court, N.D. Ohio·Decided January 19, 1977·No. C76-324·Published·Cited by 7 cases

Opinion

MEMORANDUM AND ORDER

MANOS, District Judge.

On April 2, 1976 the plaintiff, the United States of America, filed a complaint requesting that the defendant, the City of Painesville, a municipal corporation, be enjoined from operating a steam generating coal fired power unit in violation of the Clean Air Act, 42 U.S.C. § 1857c-6(e) and the Standards of Performance For New Stationary Sources, promulgated thereunder. See, 40 C.F.R. Part 60. The defendant filed a motion for summary judgment on April 23, 1976, and the plaintiff filed a motion for summary judgment, as to the defendant’s liability, on July 30, 1976.

This Court has jurisdiction over this action pursuant to 28 U.S.C. § 1345 and 42 U.S.C. § 1857c-8(b)(3).

FINDINGS OF FACT

The facts of this case are undisputed. In 1966 the City of Painesville hired the engineering consultant firm of Glaus, Pyle & Schomer (Glaus) for advice on the possibility of expanding the electrical generating capacity of the Painesville Municipal Electric Utility (Municipal Electric). See, Painesville Ordinance No. 27-66, plaintiff’s Appendix A. In 1967 Painesville city council decided that expansion of Municipal Electric was both feasible and necessary and started a construction program to build an additional coal fed electrical generating unit. The completion of Municipal Electric’s expansion project was tentatively expected to be in early or mid 1972. See, Document 11, Appendix B.

On December 21, 1967 Painesville made its first purchase of equipment for the new generating unit; a used 25,000 kw turbo-generator at a cost of $118,000. See, Ordinance No. 46-67, Appendix A; Document No. 6, Appendix B. In November of 1969 Glaus submitted “specifications and proposals for pulverized coal fired steam generat *498 ing unit no. 5.” See, Document 12, Appendix B. On December 1, 1969 Painesville city council authorized the city manager to advertise for bids for the new generating unit (Unit No. 5) based on Glaus’ specifications. See, Resolution No. 60-69, Appendix A. On April 20, 1970, after receiving bids on Unit 5, a letter of intent to enter into a contract for the construction of a boiler was sent to Combustion Engineering Inc. See, Document 18, Appendix B. At this point the start of construction appeared imminent. However financing difficulties caused delays and with each delay the cost of Unit 5 increased. See, Document 22, Appendix B. In August of 1971 Painesville discussed with Glaus ways to decrease the cost of Unit 5. See, Document 27, Appendix B.

On August 17, 1971 the Administrator of the United States Environmental Protection Agency (EPA) published in the Federal Register proposed standards for performance for new stationary sources. See, 36 Fed.Reg. 15704.

On September 20, 1971 Painesville informed Glaus that their services would no longer be needed. See, Document 11, Appendix C. On November 29, 1971 the engineering firm of Campbell, Deboe, Giese & Weber (Campbell) was hired. See, Resolution No. 52-71, Appendix A.

On December 23, 1971, the Standards of Performance for new source fossil-fuel fired steam generators became final. See, 36 F.R. 24877. Approximately one month later Campbell submitted a report on the proposed construction of Unit 5. In this report Campbell stated:

“Existing new federal air pollution regulations and proposed State of Ohio air pollution regulations which are scheduled to go into effect in February of this year are such that it is questionable if the boiler equipment is appropriate in all respects if furnished as originally contemplated. The new regulations cover emissions of particular matter, sulphur dioxide and nitrous oxides.” See, Document 13, p. 6, Appendix C.

The report recommended a change in size of the boiler from 240,000 lbs. steam/hour (continuous rating) to 215,000 lbs. steam/hour (continuous rating). Painesville accepted the change in the boiler specifications, and on February 22, 1972 advertised for bids. See, Resolution 7-72, Appendix A. Bids were received and evaluated. One of the factors in the evaluation was whether the bids met the United States Environmental Protection Agency (EPA) and Ohio EPA regulations. Campbell noted that the bidders could only meet sulfur dioxide requirements by “fuel selection.” See, Document 4, Exhibit C.

On July 28, 1972 Painesville executed a contract with Babcock & Wilcox Company for the construction of the steam generating unit of Unit 5. See, Appendix D, Document 5.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. City of Painesville, 431 F. Supp. 496, 10 ERC 1106, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20221, 10 ERC (BNA) 1106, 1977 U.S. Dist. LEXIS 17830 (N.D. Ohio 1977).

431 F. Supp. 496 (United States v. City of Painesville) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related