MEMORANDUM AND ORDER
MANOS, District Judge.
On April 2, 1976 the plaintiff, the United States of America, filed a complaint requesting that the defendant, the City of Painesville, a municipal corporation, be enjoined from operating a steam generating coal fired power unit in violation of the Clean Air Act, 42 U.S.C. § 1857c-6(e) and the Standards of Performance For New Stationary Sources, promulgated thereunder.
See,
40 C.F.R. Part 60. The defendant filed a motion for summary judgment on April 23, 1976, and the plaintiff filed a motion for summary judgment, as to the defendant’s liability, on July 30, 1976.
This Court has jurisdiction over this action pursuant to 28 U.S.C. § 1345 and 42 U.S.C. § 1857c-8(b)(3).
FINDINGS OF FACT
The facts of this case are undisputed. In 1966 the City of Painesville hired the engineering consultant firm of Glaus, Pyle & Schomer (Glaus) for advice on the possibility of expanding the electrical generating capacity of the Painesville Municipal Electric Utility (Municipal Electric).
See,
Painesville Ordinance No. 27-66, plaintiff’s Appendix A. In 1967 Painesville city council decided that expansion of Municipal Electric was both feasible and necessary and started a construction program to build an additional coal fed electrical generating unit. The completion of Municipal Electric’s expansion project was tentatively expected to be in early or mid 1972.
See,
Document 11, Appendix B.
On December 21, 1967 Painesville made its first purchase of equipment for the new generating unit; a used 25,000 kw turbo-generator at a cost of $118,000.
See,
Ordinance No. 46-67, Appendix A; Document No. 6, Appendix B. In November of 1969 Glaus submitted “specifications and proposals for pulverized coal fired steam generat
ing unit no. 5.”
See,
Document 12, Appendix B. On December 1, 1969 Painesville city council authorized the city manager to advertise for bids for the new generating unit (Unit No. 5) based on Glaus’ specifications.
See,
Resolution No. 60-69, Appendix A. On April 20, 1970, after receiving bids on Unit 5, a letter of intent to enter into a contract for the construction of a boiler was sent to Combustion Engineering Inc.
See,
Document 18, Appendix B. At this point the start of construction appeared imminent. However financing difficulties caused delays and with each delay the cost of Unit 5 increased.
See,
Document 22, Appendix B. In August of 1971 Painesville discussed with Glaus ways to decrease the cost of Unit 5.
See,
Document 27, Appendix B.
On August 17, 1971 the Administrator of the United States Environmental Protection Agency (EPA) published in the
Federal Register
proposed standards for performance for new stationary sources.
See,
36 Fed.Reg. 15704.
On September 20, 1971 Painesville informed Glaus that their services would no longer be needed.
See,
Document 11, Appendix C. On November 29, 1971 the engineering firm of Campbell, Deboe, Giese & Weber (Campbell) was hired.
See,
Resolution No. 52-71, Appendix A.
On December 23, 1971, the Standards of Performance for new source fossil-fuel fired steam generators became final.
See,
36 F.R. 24877. Approximately one month later Campbell submitted a report on the proposed construction of Unit 5. In this report Campbell stated:
“Existing new federal air pollution regulations and proposed State of Ohio air pollution regulations which are scheduled to go into effect in February of this year are such that it is questionable if the boiler equipment is appropriate in all respects if furnished as originally contemplated. The new regulations cover emissions of particular matter, sulphur dioxide and nitrous oxides.”
See,
Document 13, p. 6, Appendix C.
The report recommended a change in size of the boiler from 240,000 lbs. steam/hour (continuous rating) to 215,000 lbs. steam/hour (continuous rating). Painesville accepted the change in the boiler specifications, and on February 22, 1972 advertised for bids.
See,
Resolution 7-72, Appendix A. Bids were received and evaluated. One of the factors in the evaluation was whether the bids met the United States Environmental Protection Agency (EPA) and Ohio EPA regulations. Campbell noted that the bidders could only meet sulfur dioxide requirements by “fuel selection.” See, Document 4, Exhibit C.
On July 28, 1972 Painesville executed a contract with Babcock & Wilcox Company for the construction of the steam generating unit of Unit 5. See, Appendix D, Document 5.
On May 17,1973 the Ohio EPA found the City of Painesville was not required to meet Ohio’s air quality standards contained in R.C. §§ 3704
et seq.
because Unit 5 was not a new air contaminate source. The basis for this decision was that the contracts for purchase of the equipment for Unit 5 were made before the effective date of the Ohio Air Pollution Control Regulations, February 15, 1972.
See,
Defendant’s Exhibit D. A consent and abatement order was later entered into by Painesville and Ohio EPA in which Painesville agreed to comply with Ohio particulate regulations and to burn coal containing less than 3.2% sulfur.
See,
Defendant’s Exhibit B. On March 31,1975, the EPA informed Painesville that it would not pursue enforcement of federal particulate emission standards because of the consent and abatement order, but the letter did not preclude EPA from enforcing sulfur dioxide emission standards.
See,
Document 3, Appendix D. On November 24, 1975 EPA issued notice that Painesville was in violation of 40 C.F.R. §§ 60.40 and 60.43 because it intended to burn coal with a 3% sulfur content which would cause in excess of 4.8 lbs. sulfur dioxide/million btu heat input to be emitted from Unit 5, a fossil-fuel fired steam generating unit with more than 250 million btu/hour heat input.
See,
Document 8, Appendix D. Under § 60.43 a
new stationary source may emit no more than 1.2 lbs. sulfur dioxide/million btu heat input. Painesville does not contest that Unit 5’s emissions violate the standards set by 40 C.F.R. § 60.43 if they apply.
However, Painesville claims that 40 C.F.R. Part 60
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM AND ORDER
MANOS, District Judge.
On April 2, 1976 the plaintiff, the United States of America, filed a complaint requesting that the defendant, the City of Painesville, a municipal corporation, be enjoined from operating a steam generating coal fired power unit in violation of the Clean Air Act, 42 U.S.C. § 1857c-6(e) and the Standards of Performance For New Stationary Sources, promulgated thereunder.
See,
40 C.F.R. Part 60. The defendant filed a motion for summary judgment on April 23, 1976, and the plaintiff filed a motion for summary judgment, as to the defendant’s liability, on July 30, 1976.
This Court has jurisdiction over this action pursuant to 28 U.S.C. § 1345 and 42 U.S.C. § 1857c-8(b)(3).
FINDINGS OF FACT
The facts of this case are undisputed. In 1966 the City of Painesville hired the engineering consultant firm of Glaus, Pyle & Schomer (Glaus) for advice on the possibility of expanding the electrical generating capacity of the Painesville Municipal Electric Utility (Municipal Electric).
See,
Painesville Ordinance No. 27-66, plaintiff’s Appendix A. In 1967 Painesville city council decided that expansion of Municipal Electric was both feasible and necessary and started a construction program to build an additional coal fed electrical generating unit. The completion of Municipal Electric’s expansion project was tentatively expected to be in early or mid 1972.
See,
Document 11, Appendix B.
On December 21, 1967 Painesville made its first purchase of equipment for the new generating unit; a used 25,000 kw turbo-generator at a cost of $118,000.
See,
Ordinance No. 46-67, Appendix A; Document No. 6, Appendix B. In November of 1969 Glaus submitted “specifications and proposals for pulverized coal fired steam generat
ing unit no. 5.”
See,
Document 12, Appendix B. On December 1, 1969 Painesville city council authorized the city manager to advertise for bids for the new generating unit (Unit No. 5) based on Glaus’ specifications.
See,
Resolution No. 60-69, Appendix A. On April 20, 1970, after receiving bids on Unit 5, a letter of intent to enter into a contract for the construction of a boiler was sent to Combustion Engineering Inc.
See,
Document 18, Appendix B. At this point the start of construction appeared imminent. However financing difficulties caused delays and with each delay the cost of Unit 5 increased.
See,
Document 22, Appendix B. In August of 1971 Painesville discussed with Glaus ways to decrease the cost of Unit 5.
See,
Document 27, Appendix B.
On August 17, 1971 the Administrator of the United States Environmental Protection Agency (EPA) published in the
Federal Register
proposed standards for performance for new stationary sources.
See,
36 Fed.Reg. 15704.
On September 20, 1971 Painesville informed Glaus that their services would no longer be needed.
See,
Document 11, Appendix C. On November 29, 1971 the engineering firm of Campbell, Deboe, Giese & Weber (Campbell) was hired.
See,
Resolution No. 52-71, Appendix A.
On December 23, 1971, the Standards of Performance for new source fossil-fuel fired steam generators became final.
See,
36 F.R. 24877. Approximately one month later Campbell submitted a report on the proposed construction of Unit 5. In this report Campbell stated:
“Existing new federal air pollution regulations and proposed State of Ohio air pollution regulations which are scheduled to go into effect in February of this year are such that it is questionable if the boiler equipment is appropriate in all respects if furnished as originally contemplated. The new regulations cover emissions of particular matter, sulphur dioxide and nitrous oxides.”
See,
Document 13, p. 6, Appendix C.
The report recommended a change in size of the boiler from 240,000 lbs. steam/hour (continuous rating) to 215,000 lbs. steam/hour (continuous rating). Painesville accepted the change in the boiler specifications, and on February 22, 1972 advertised for bids.
See,
Resolution 7-72, Appendix A. Bids were received and evaluated. One of the factors in the evaluation was whether the bids met the United States Environmental Protection Agency (EPA) and Ohio EPA regulations. Campbell noted that the bidders could only meet sulfur dioxide requirements by “fuel selection.” See, Document 4, Exhibit C.
On July 28, 1972 Painesville executed a contract with Babcock & Wilcox Company for the construction of the steam generating unit of Unit 5. See, Appendix D, Document 5.
On May 17,1973 the Ohio EPA found the City of Painesville was not required to meet Ohio’s air quality standards contained in R.C. §§ 3704
et seq.
because Unit 5 was not a new air contaminate source. The basis for this decision was that the contracts for purchase of the equipment for Unit 5 were made before the effective date of the Ohio Air Pollution Control Regulations, February 15, 1972.
See,
Defendant’s Exhibit D. A consent and abatement order was later entered into by Painesville and Ohio EPA in which Painesville agreed to comply with Ohio particulate regulations and to burn coal containing less than 3.2% sulfur.
See,
Defendant’s Exhibit B. On March 31,1975, the EPA informed Painesville that it would not pursue enforcement of federal particulate emission standards because of the consent and abatement order, but the letter did not preclude EPA from enforcing sulfur dioxide emission standards.
See,
Document 3, Appendix D. On November 24, 1975 EPA issued notice that Painesville was in violation of 40 C.F.R. §§ 60.40 and 60.43 because it intended to burn coal with a 3% sulfur content which would cause in excess of 4.8 lbs. sulfur dioxide/million btu heat input to be emitted from Unit 5, a fossil-fuel fired steam generating unit with more than 250 million btu/hour heat input.
See,
Document 8, Appendix D. Under § 60.43 a
new stationary source may emit no more than 1.2 lbs. sulfur dioxide/million btu heat input. Painesville does not contest that Unit 5’s emissions violate the standards set by 40 C.F.R. § 60.43 if they apply.
However, Painesville claims that 40 C.F.R. Part 60, Standards Of Performance For New Stationary Sources, does not apply because Unit 5 is not a new source as that term is used in. 42 U.S.C. § 1857c-6(a)(2) and the regulations promulgated thereunder.
CONCLUSIONS OF LAW
The sole issue
for determination is whether Painesville’s Unit 5 is a new source that is required to meet the regulations contained in 40 C.F.R. Part 60.
42 U.S.C. § 1857c-6(a)(2) reads,
“The term ‘new source’ means any stationary source, the construction or modification of which is commenced after the publication of regulations (or, if earlier, proposed regulations) prescribing a standard of performance under this section which will be applicable to such source.”
Proposed regulations foiLjiew source emissions were issued AugustT7t<L971,
see,
36 Fed.Reg. 15704, so that if, as of August 17, 1971, “construction” or “modification”
of Municipal Electric had been “commenced,” Unit 5 would not be a new source and therefore sulphur dioxide emission standards promulgated under 42 U.S.C. § 1857c-6 do not apply. The words “construction,” “modified,” and “commenced” are not defined in § 1857e-6 but have been defined in 40 C.F.R. § 60.2(g)(h) and (i) respectively. While an interpretation of an act by the enforcing agency is not conclusive, it is entitled to “great deference,”
Udall v. Tallman,
380 U.S. 1, 16, 85 S.Ct. 792, 13 L.Ed.2d 616 (1965);
see, e. g., Youakim
v.
Miller,
425 U.S. 231, 235-236, 96 S.Ct. 1399, 1402, 47 L.Ed.2d 701 (1976);
Satty
v.
Nashville Gas Company,
522 F.2d 850, 854 (6th Cir. 1975). Further the interpretation by an administrative agency of its own regulations is controlling unless plainly erroneous.
See, e. g., Udall v. Tallman,
380 U.S. 1, 17, 85 S.Ct. 792, 13 L.Ed.2d 616 (1965);
Compton
v.
Tennessee Dept, of Public Welfare,
532 F.2d 561, 565 (6th Cir. 1976).
In 40 C.F.R. § 60.2(g) “construction” is defined as the “. . . fabrication, erection or installation of an affected facility.” An “affected facility” is defined in § 60.2(e) as meaning “. . . with reference to a stationary source, any
apparatus
to which a standard is applicable.” (emphasis added). Standards are made applicable to fossil-fuel fired steam generators, like Unit 5, by § 60.40. A fossil-fuel fired steam generator is a boiler,
see,
40 C.F.R. § 60.41(a). It follows, in this case, that the “affected facility” of Unit 5 is the boiler, because it is the apparatus to which the emission standards are applicable. There
fore it is the date of the “commencement” of “construction” of the boiler which determines whether Unit 5 is or is not a new source.
In 40 C.F.R. § 60.2(i) “commenced” is defined as meaning,
“. . . with respect to the definition of ‘new source’ in Section 111(a)(2) of the Act, that an owner or operator has undertaken a continuous program of construction or modification or that an owner or operator has entered into a contractual obligation to undertake and complete, within a reasonable time, a continuous program of construction or modification.”
Using this definition EPA argues that the construction of the “affected facility,” the boiler, commenced at one of two times: First, when actual construction at the building site was started for a particular type of boiler, so that modification of existing physical construction would be required if the boiler specifications were changed to accommodate anti-pollution control devices; or, second, that construction commenced at the time a contract for the purchase of a new boiler was signed, with the proviso that delivery be required within a reasonable time. The Court finds that EPA’s interpretation of 40 C.F.R. § 60.2(i).
is fully supported by the language of that regulation.
Applying the above definition to the facts of this case the Court finds that of August 17, 1971 “construction” of Unit 5 had not “commenced.” No contract for the production of a boiler for Unit 5 had been entered into. Construction of Unit 5 had not progressed to the point that a change in its design would have required the facility already erected to be. modified in order to insure that it could comply with the sulfur dioxide emission standards of 40 C.F.R. § 60.43. In fact the Court finds in the record no evidence that any purchase of equipment made prior to August, 1971 would have been incompatible with a complying operation of Unit 5.
As is evidenced by the change in the specifications of the boiler in January of 1972, Painesville could have modified its plans for Unit 6 at a time well after the proposed regulations for new stationary sources became final, without loss of the money previously spent on capital purchases.
The Court finds that Municipal Electric’s Unit 5 is a new
stationary
source
subject to the emission standards established by 40 C.F.R. § 60.43. Further the Court finds that the burning of coal with the sulfur content of approximately 3.0% will cause the emissions of sulfur dioxide in excess of 1.2 lbs./million btu input heat. Summary judgment on liability is granted to the plaintiff, the United States of America. The parties are ordered to prepare plans with documentation, which would allow the operation of Unit 5 in compliance with 40 C.F.R. § 60.43 and at an economically acceptable level.
IT IS SO ORDERED.