Sierra Club v. Franklin County Powe

CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 27, 2008
Docket06-4045
StatusPublished

This text of Sierra Club v. Franklin County Powe (Sierra Club v. Franklin County Powe) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Franklin County Powe, (7th Cir. 2008).

Opinion

In the

United States Court of Appeals For the Seventh Circuit

No. 06-4045

S IERRA C LUB, Plaintiff-Appellee, v.

F RANKLIN C OUNTY P OWER OF ILLINOIS, LLC, formerly known as E NVIROP OWER OF ILLINOIS, LLC, E NVIROP OWER, LLC, and K HANJEE H OLDING (US), INC.,

Defendants-Appellants.

Appeal from the United States District Court for the Southern District of Illinois. No. 05 C 4095—J. Phil Gilbert, Judge.

A RGUED O CTOBER 29, 2007—D ECIDED O CTOBER 27, 2008

Before B AUER, R IPPLE, and W ILLIAMS, Circuit Judges. W ILLIAMS, Circuit Judge. Franklin County Power of Illinois, LLC, wants to build a coal power plant in southern Illinois. Because the plant will emit a significant amount of air pollution, the Company must first obtain a “Prevention of Significant Deterioration” (PSD) permit from the Illinois Environmental Protection Agency (IEPA), 2 No. 06-4045

the agency that the federal EPA has designated as the issuer of PSD permits in Illinois. Although the IEPA granted the Company a PSD permit in 2001, the IEPA has since made a “preliminary determination” that the permit has expired. Sierra Club is a non-profit environmental organization that sought to enjoin the Company from building the power plant by bringing this suit against the Company, its parent company EnviroPower, LLC, and Khanjee Holding (US), Inc., under a citizen suit provision of the Clean Air Act. Sierra Club alleged that the Company’s 2001 PSD permit had expired because the Company had neglected to “commence construction” of the plant within an 18-month window required under the permit. Sierra Club also claimed the permit was invalid under EPA regulations because the Company had discontinued construction of the plant for over 18 months. The district court agreed with Sierra Club on both points and granted summary judgment in its favor. The court also perma- nently enjoined the Company from building the plant until it obtained a new PSD permit, and the defendants appealed to this court. We agree with the district court that Sierra Club has standing to pursue this lawsuit and that its claim is ripe and permissible under the Clean Air Act. We also agree that the 2001 PSD permit has expired and that the district court properly granted permanent injunctive relief in favor of Sierra Club. Therefore, we affirm the district court’s grant of summary judgment in favor of Sierra Club. No. 06-4045 3

I. BACKGROUND A. Statutory and regulatory framework Sierra Club brought this suit under 42 U.S.C. § 7604(a)(3), a citizen suit provision of the Clean Air Act, which pro- vides in relevant part: [A]ny person may commence a civil action on his own behalf . . . (3) against any person who proposes to construct or constructs any new or modified major emitting facility with- out a permit required under [42 USCS §§ 7470 et seq.] (relating to significant deterioration of air quality) . . . or who is alleged to have violated (if there is evidence that the alleged violation has been repeated) or to be in violation of any condition of such permit. The parties agree that the coal power plant that the Com- pany seeks to build is a “major emitting facility” that requires a PSD permit. Such a permit contains an emission limitation that is set by the IEPA and represents the “best available control technology” for pollution. See 42 U.S.C. § 7475(a). Once issued, a PSD permit can expire and become invalid in three different ways: [a] [I]f construction is not commenced within 18 months after receipt of such approval, [b] if construction is discontinued for a period of 18 months or more, or 4 No. 06-4045

[c] if construction is not completed within a rea- sonable time. 40 C.F.R. § 52.21(r)(2). The IEPA Administrator “may extend the 18-month period upon a satisfactory showing that an extension is justified,” id.; otherwise, the PSD permit terminates by “automatic expiration.” 40 C.F.R. § 124.5(g)(2) (“PSD permits may be terminated only by recission under § 52.21(w) or by automatic ex- piration under § 52.21(r)(2).”).

B. Factual background On August 15, 2000, the Company applied to the IEPA for a PSD permit to build a 600 megawatt 1 coal-fired power plant in Benton, Illinois, on land for which it had a 99-year lease. The IEPA concluded the project would be a major air pollution source subject to PSD review. On July 3, 2001, the IEPA issued a PSD permit for the plant. The permit states it will become invalid if: construction of CFB [circulating fluidized bed] boilers is not commenced within 18 months after this permit becomes effective, if construction of these boilers is discontinued for a period of 18 months or more, or if construction of these boilers is not completed within a reasonable period of time.

1 Sierra Club claims the permit only authorized a 500 MW, not a 600 MW, facility. Because the defendants lost on summary judgment, we construe all facts in the light most favorable to them. See Rawoof v. Texor Petroleum Co., 521 F.3d 750, 755 (7th Cir. 2008). No. 06-4045 5

The permit defines “commence” and “construction” in terms of 40 C.F.R. § 52.21(b)(9) and § 52.21(b)(8), respec- tively, which are provisions we will discuss in more detail later. On December 2, 2002, the Company entered into an agreement with Black & Veatch (B&V), an engineering and construction company, that required the parties to “work together on an exclusive basis . . . in order to draft and negotiate the EPC [Engineering, Procurement and Construction] Contract.” On about December 18, 2002, the Company contracted with Alberici Constructors, Inc., for on-site excavation and foundation work. Alberici was to dig a hole at the site down to the bedrock and pour concrete to lay part of the foundation for the plant. On January 3, 2003, four Alberici employees began delivering equipment to the site, and five days later, they began excavating. On February 14, 2003, Alberici stopped the excavation after a dispute arose regarding payment. Alberici’s bills after that date include one day where workers showed up but did no work. All other days only include a super- visor’s hours spent maintaining a protective barricade around the site. In July 2004, the Company’s landlord had the hole refilled, apparently because the Company did not make a payment on its lease. In September 2004, the Company signed another contract for excavation and concrete work, which began anew on September 29, 2004. An IEPA inspector visited the plant site shortly there- after and determined that construction had commenced. 6 No. 06-4045

In the meantime, co-defendant Khanjee Holding (US), Inc. had obtained an option to buy the Company and all its assets. In June 2003, Khanjee affirmed its obligation to adhere to the Company’s contract with B&V. In January 2004, the Company secured a mandate letter from its lead financial arranger indicating that financing for the project was available. On November 19, 2004, the IEPA notified the Company that it had “made a preliminary finding” that its PSD permit had expired. The Company challenged this pre- liminary determination and as far as we know, that matter remains pending before the IEPA. On May 20, 2005, Sierra Club filed this suit, alleging that the 2001 PSD permit had expired and was invalid. The defendants moved to dismiss, claiming that the citizen suit provision of the Clean Air Act did not provide a basis for this suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Seckinger
397 U.S. 203 (Supreme Court, 1970)
Babbitt v. United Farm Workers National Union
442 U.S. 289 (Supreme Court, 1979)
Larson v. Valente
456 U.S. 228 (Supreme Court, 1982)
Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Thomas Jefferson University v. Shalala
512 U.S. 504 (Supreme Court, 1994)
United States v. Mead Corp.
533 U.S. 218 (Supreme Court, 2001)
Massachusetts v. Environmental Protection Agency
549 U.S. 497 (Supreme Court, 2007)
United States v. City of Painesville, Ohio
644 F.2d 1186 (Sixth Circuit, 1981)
United States v. Dennis Kaun
827 F.2d 1144 (Seventh Circuit, 1987)
United States v. Bethlehem Steel Corporation
38 F.3d 862 (Seventh Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Sierra Club v. Franklin County Powe, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-franklin-county-powe-ca7-2008.