Washington Utilities & Transportation Commission v. Federal Energy Regulatory Commission

26 F.3d 935
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 7, 1994
DocketNos. 91-70619, 91-70628
StatusPublished
Cited by6 cases

This text of 26 F.3d 935 (Washington Utilities & Transportation Commission v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Utilities & Transportation Commission v. Federal Energy Regulatory Commission, 26 F.3d 935 (9th Cir. 1994).

Opinion

Opinion by Judge CANBY.

CANBY, Circuit Judge:

BACKGROUND

THE RESIDENTIAL EXCHANGE PROGRAM

This case presents a challenge to certain cost calculations made by the Bonneville Power Administration (“BPA”) in its operation of the Residential Exchange Program of the Pacific Northwest Electric Power Planning Conservation Act (“Northwest Power Act”), 16 U.S.C. §§ 839-839h (1985). BPA is the marketing agent for electric power produced by federal generating plants in the Pacific Northwest. The Northwest Power Act established a power exchange program between BPA and qualified investor owned utilities (“IOUs”) of the Pacific Northwest. The exchange program is designed to eliminate the disparities between electric rates paid by residential customers of IOUs and [937]*937the lower rates paid by customers of publicly-owned utilities. An IOU participating in the program may sell electricity to BPA at a rate that reflects the utility’s “average system cost” (“ASC”) and in exchange purchase an equivalent amount of power at BPA’s lower preferred rate. In actuality, no power is exchanged. Instead, BPA pays the utility the difference between the cost of the utility’s power and the cost of BPA power. In effect, the Residential Exchange Program alleviates rate disparities by making BPA customers pay a subsidy to defray the cost of power that participating IOUs sell to residential customers. Petitioner Puget Sound Power & Light Company (“Puget”) takes part in this exchange program.

The Northwest Power Act delegates to BPA the task of calculating a participating utility’s ASC. 16 U.S.C. § 839c(c)(7). As might be expected, the calculus that BPA uses to determine a utility’s ASC is complex, encompassing a variety of factors. See generally Average System Cost Methodology, 18 C.F.R. § 301.1 (1991). At its simplest, the ASC equals the utility’s “contract system costs” divided by its “contract system load.” Id. § 301.1(b)(1). Contract system costs are the costs of production and transmission of electricity. The contract system load reflects the utility’s total retail sales for a fixed period.

BPA has adopted a “jurisdictional” approach to determining the ASCs of participating IOUs, relying on the state utility regulatory commissions determination of each utility’s costs. An IOU seeking an ASC determination must submit to BPA a “loss study” containing a breakdown of the utility’s costs, as determined by the state commission, for obtaining and transmitting power.

THE BEP AGREEMENT

During the 1970’s, BPA, Puget and other investors entered into an agreement to finance the construction of a nuclear power plant, WNP-3, a part of the Washington Public Power Supply System. The agreement provided that BPA would oversee the construction and would take a seventy percent interest in the plant. Puget would receive a five percent interest. When the plant was two-thirds complete, BPA deferred construction indefinitely. Puget and the other investors sued BPA and eventually reached a settlement. The settlement requires BPA to supply Puget, for thirty years, the amount of electric power (“Bonneville Exchange Power” or “BEP”) equivalent to that quantity Puget would have received had the WNP-3 plant been completed, reduced to account for the fact that Puget had been relieved of the obligation to pay the unpaid portion of its anticipated capital investment. The agreement also requires Puget to pay BPA’s surrogate operating and maintenance costs, that is, the amount Puget would have had to contribute for WNP-3’s upkeep had the plant been completed.

How Puget’s investment in WNP-3 figures into Puget’s average system costs, for the purposes of its participation in the Residential Exchange Program, was deliberately left undetermined in the settlement agreement and is the core issue in this appeal.

THE WUTC DECISION

The Washington Utilities ánd Transportation Commission (“WUTC”) is the regulatory body charged with setting retail electric rates in the State of Washington. As part of the rate-setting process, the WUTC examines a utility’s costs to decide which may be passed on to the consumer and on which of its investments the utility may earn a return. Costs that the WUTC determines were incurred imprudently are not figured into a utility’s retail rate.

Puget requested a rate increase to cover the funds Puget had invested in the WNP-3 project. The WUTC concluded that the entire expenditure, approximately $147 million, had been prudent and therefore permitted Puget to recover the investment in its retail rates. However, the WUTC decided that Puget should be allowed to earn a return only on the part of its investment that represented avoided costs, that is, the price Puget would have had to pay to acquire from some other source the quantity of power equivalent to the BEP it receives pursuant to the settlement agreement. The WUTC found that the avoided costs amounted to $95 million. Puget could recover the remaining $52 million through consumer rates, the WUTC ruled, [938]*938but was not entitled to earn a return on that portion of the WNP-3 investment. The WUTC noted, “This approach will be consistent with our prior decisions regarding extraordinary expenses and provides a fair sharing of responsibility between stockholders and rate payers.”

THE ASC DETERMINATIONS

Puget has submitted three ASC rate filings with the BPA since the WUTC’s rate decision. In each of the filings, Puget listed among its production costs $147 million for the BEP. In each case, BPA excluded the $52 million portion from the calculation of Puget’s ASC.

Puget filed for FERC review of each of the three determinations, contesting BPA’s decision to disallow the $52 million. The WUTC asked FERC to convene a joint state board to assist FERC in the review, as specified in the Northwest Power Act. 16 U.S.C. § 839f(g). After consolidating the three cases, FERC issued an order accepting BPA’s conclusions and rejecting the WUTC’s request for a joint state board.

ISSUES ON APPEAL

This case presents several novel issues related to the administration of the Residential Exchange Program. Foremost is the question whether BPA acted improperly in excluding from Puget’s ASC calculation that portion of Puget’s investment in the WNP-3 project that the WUTC determined did not represent avoided costs. In addition, the petitioners challenge FERC’s refusal to convene a joint state board to review BPA’s ASC determination. Before reaching that issue, however, we must determine whether we have jurisdiction to review FERC’s decision. Finally, the intervenors in this ease, direct customers of BPA, have sought to attack other aspects of the BPA order and we discuss our reasons for refusing to entertain their claims.

DISCUSSION

I. THE BPA’S DECISION TO EXCLUDE THE $52 MILLION FROM PUGET’S ASC CALCULATION

The scope of our review of BPA’s ASC determination is governed by the Administrative Procedure Act, 5 U.S.C. § 706 (1977). 16 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
26 F.3d 935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-utilities-transportation-commission-v-federal-energy-ca9-1994.