Shafer Electric & Construction v. Mantia

96 A.3d 989, 626 Pa. 258, 2014 WL 3579687, 2014 Pa. LEXIS 1766
CourtSupreme Court of Pennsylvania
DecidedJuly 21, 2014
StatusPublished
Cited by61 cases

This text of 96 A.3d 989 (Shafer Electric & Construction v. Mantia) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shafer Electric & Construction v. Mantia, 96 A.3d 989, 626 Pa. 258, 2014 WL 3579687, 2014 Pa. LEXIS 1766 (Pa. 2014).

Opinion

OPINION

Justice BAER.

We granted allowance of appeal in this matter to determine whether the Home Improvement Consumer Protection Act, 73 P.S. §§ 517.1-517.18 (the Act), bars a contractor from recovery under a theory of quantum meruit in the absence of a valid and enforceable home improvement contract as defined by the Act. The Superior Court held that the Act does not bar a [991]*991cause of action sounding in quantum me-ruit and, for the reasons that follow, we affirm that decision albeit on slightly different grounds.

The facts of the instant appeal are not in dispute. In August, 2010, Appellants, Raymond and Donna Mantia, residents of Avella, Washington County, engaged Ap-pellee, Shafer Electric & Construction, a registered West Virginia contractor, to build a 34 foot by 24 foot, two-car garage addition onto their house. The initial proposal by Appellee, found at Reproduced Record (R.R.) 24a, was extremely detailed in the work to be completed, including the dimensions of the addition, type of roof to be installed, size of skylights to be placed in the roof, and brand and type of sof-fit/fascia to be used. An addendum to the initial proposal, found at R.R. 25a, further elaborated upon details, specifications, and upgrades to portions of the project. Between the two proposals, Appellee agreed to furnish materials and labor in consideration of $102,000.00.

The proposals,1 however, did not comply with several requirements of Section 517.7 of the Act. Specifically, pursuant to the Act, any home improvement contract, in order to be valid and enforceable against the owner of real property, must be legible, in writing, and contain thirteen other specific requirements. See 73 P.S. § 517.7(a).2 Despite the detail in the spec[992]*992ifications for the work to be completed, the contract only complied with subsections (5), (7), and (8) of Section 517.7(a). For example, the contract did not contain approximate start and completion dates as provided by subsection (a)(6), nor did it inform Appellants of the toll-free, consumer protection hotline number pursuant to subsection (a)(12).

Notwithstanding these deficiencies, work on the project began in October, 2010, when Appellants, who owned their own excavation business, began the foundation excavation. When Appellee commenced construction of the addition, however, it contended that problems surfaced because of Appellants’ failure to complete the excavation work properly. During the subsequent months, Appellants eventually reexcavated the foundation area for the addition and, in the process (according to Appellee), changed the design of the addition several times. Negotiations into these design changes and other necessary alterations as a result of the excavation problems occurred, but ultimately failed when Appellants apparently refused to enter into a new contract with Appellee. Upon the breakdown of the negotiations, the parties mutually agreed that Appellee would invoice Appellants for the work completed, and that Appellee would discontinue efforts on the project. On February 23, 2011, Appellee sent a final invoice to Appellants in the amount of $37,874.20, which included the cost of materials, architect fees, and labor. See Invoice, found at R.R. 26a.

Appellants, however, refused to pay the bill, and on April 29, 2011, Appellee filed a mechanic’s lien in the Washington County Court of Common Pleas. When, on November 16, 2011, Appellants still had failed to satisfy the outstanding balance, Appel-lee filed a civil action in the common pleas court, alleging both breach of contract and quantum meruit causes of action.3

Appellants filed preliminary objections in the nature of a demurrer to the complaint, contending that Section 517.7(g) of the Act barred Appellee from filing suit. Subsection (g), entitled “Contractor’s recovery right,” provides,

Nothing in this section shall preclude a contractor who has complied with subsection (a) from the recovery of payment for work performed based on the reasonable value of services which were requested by the owner if a court determines that it would be inequitable to deny such recovery.

73 P.S. § 517.7(g). Appellants averred that because Appellee did not comply with several of the requirements of subsection (a), it was precluded under subsection (g) from filing any cause of action — in contract, quantum meruit, or otherwise.

The trial court agreed with Appellants, sustained the preliminary objection, struck [993]*993the mechanic’s lien, and dismissed the complaint with prejudice. The court first determined that the breach of contract claim could not withstand the preliminary objections because Appellee’s failure to comply with Section 517.7(a) rendered the contract void and unenforceable. Regarding the quantum meruit claim, the court summarily concluded, “[ujnder a plain reading of [Section 517.7(g)], it is clear that quantum meruit recovery is only permitted if a contractor has complied with the requirements of 73 P.S. § 517.7(a).” Shafer Elec. & Const. v. Mantia, No. 2011-2775, slip op. at *3 (unpaginated) (CP Washington Aug. 17, 2012).

Appellee filed a timely appeal to the Superior Court, alleging, inter alia, that the trial court erred in finding that the Act barred its quantum meruit claim. After setting forth the relevant statutory provisions, the court opined that the legislature’s “obvious ‘purpose’ in drafting Section 517.7(g) was to provide for an equitable remedy in situations where there was no valid and enforceable written contract under section 517.7(a). To conclude otherwise renders the type of recovery contemplated by the [legislature in subsection (g) impossible.” Shafer Elec. & Const. v. Mantia, 67 A.3d 8, 12-13 (Pa.Super.2013). The court continued that quasi-contract theories of recovery, such as quantum me-ruit, are readily utilized when a cause of action expressly sounding in contract cannot be sustained. Id. at 13. In the court’s view, if a contractor such as Appel-lee would have complied with subsection (a), then quasi-contract theories would be unnecessary, because the contractor could sue in contract and receive the damages associated with a contract claim.

The Superior Court further recognized that a different panel of that court had decided the identical issue in Durst v. Mil-roy General Contracting, Inc., 52 A.3d 357 (Pa.Super.2012) just nine months earlier. In Durst, a contractor brought a quantum meruit claim against two homeowners who had failed to pay him pursuant to an oral contract for home improvements. The Durst Court considered whether Section 517.7(g) of the Act precluded lawsuits sounding in quantum meruit, because the failure to document the agreement in writing violated Section 517.7(a)(1).

The Durst Court began its analysis by noting that quantum meruit is essentially a claim for unjust enrichment, which “implies a contract [and] requires the defendant to pay to the plaintiff the value of the benefit conferred.” Id. at 360. The court continued that, in a quantum meruit

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham Nelson, C. v. Nelson, F.
Superior Court of Pennsylvania, 2025
Dupont Dev. v. Searfass, J.
Superior Court of Pennsylvania, 2024
Genser v. Butler Brd. of Elec. Appeal of: RNC
Supreme Court of Pennsylvania, 2024
SnowWolf v. Iacovazzi
M.D. Pennsylvania, 2024
Ursinus College v. PWAB Apl of: IBEW, Loc. 98
Supreme Court of Pennsylvania, 2024
Estate of A.J.M., Appeal of: Lynch Law Group
2024 Pa. Super. 4 (Superior Court of Pennsylvania, 2024)
Hayes, B. v. Hayes, B.
Superior Court of Pennsylvania, 2023
Waverly Custom Homes v. Smith, M.
Superior Court of Pennsylvania, 2023
SOLEM v. HORSESHOE TRAIL FARM, LLC
E.D. Pennsylvania, 2022
Artisan Builders, Inc. v. Jang, S.
2022 Pa. Super. 36 (Superior Court of Pennsylvania, 2022)
Z.P. v. K.P.
2022 Pa. Super. 6 (Superior Court of Pennsylvania, 2022)
The Carlyle Condominium v. Spruce Street
Superior Court of Pennsylvania, 2021
B. Prunty v. UCBR
Commonwealth Court of Pennsylvania, 2021
Estate of James Kirk, Appeal of: James Kirk
Superior Court of Pennsylvania, 2021

Cite This Page — Counsel Stack

Bluebook (online)
96 A.3d 989, 626 Pa. 258, 2014 WL 3579687, 2014 Pa. LEXIS 1766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shafer-electric-construction-v-mantia-pa-2014.