This text of 173 Cal. App. 3d 86 (Severtson v. Williams Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Severtson v. Williams Construction Co., 173 Cal. App. 3d 86, 220 Cal. Rptr. 400, 1985 Cal. App. LEXIS 2609 (Cal. Ct. App. 1985).

Opinion

Opinion

CANTER, J. *

we are called upon to interpret Code of Civil Procedure section 1286.6, subdivision (a); more specifically, to determine the meaning of the words “evident miscalculation of figures” as they apply to the arbitrator’s authority to correct an award previously made.

A dispute which had arisen between property owners and the contractor they hired to construct their residence was submitted to arbitration. After two days of hearings, the arbitrator made his award and the owners applied for a correction, claiming an error had been made. The arbitrator agreed and amended the award by increasing the amount of damages and also granted the owners’ motion for additional attorneys fees and costs. The owners petitioned the superior court to have the amended award approved, and the contractor petitioned to have the original award approved. The superior court approved the original award and vacated the amended award, finding that the arbitrator had no authority to amend the original award. The owners appeal, contending the amended award should have been confirmed. Meanwhile, owners accepted payment of the original award and contractor asserts the appeal should be dismissed as moot. We affirm the confirmation of the original award and the vacation of the amended award.

*90 Facts

Richard and Diane Severtson entered into a contract with Bill Williams, doing business as Williams Construction Company, to construct a single-family dwelling. The Severtsons alleged defective workmanship and sued Williams in superior court. Williams cross-complained for monies due. By stipulation of the parties, it was agreed that the matter be arbitrated and that the arbitrator’s decision would be binding. Oral and documentary evidence was presented to the arbitrator on two hearing dates. The matter was submitted; written arguments were prepared and filed. The arbitrator made his written award in favor of the Severtsons with a minor offset in favor of Williams and provided each party with a letter stating the reasons for the award. The major item of damages was found to be $15,000 to correct the exterior siding which included removal of the existing knotty pine siding found to be inappropriate for exterior use, repapering, fixing of flashing and installing tongue and groove cedar on all exterior walls. In addition, the arbitrator awarded the Severtsons attorneys fees and costs.

The Severtsons then filed an application to arbitrator to correct award and motion to recover attorneys fees and costs after decision. Both were granted. In an amended award, the arbitrator increased the damages by $6,408 and granted additional attorney fees and costs to include the period during the hearing and for preparation of the briefs and written arguments. In addition, the Severtsons were awarded expert witness fees. A letter of explanation of the amended award was provided. From the letters accompanying the awards and a declaration of the arbitrator accompanying the motion for confirmation of the amended award, the rationale for the amendment was presented.

Issues

The questions on appeal are (1) whether the arbitrator’s action in amending the award was within his authority as a correction of an evident miscalculation of figures; (2) whether an arbitrator has authority to amend an award to increase attorneys fees and costs and provide for expert witness fees; and (3) whether the appeal is rendered moot by appellants’ accepting the amount of the original award.

Discussion

California has a comprehensive statutory arbitration scheme. (Code Civ. Proc., § 1280 et seq.) 1 The parties to this litigation voluntarily agreed *91 to submit their controversy to this process and thereby remove it from the procedures applicable to trial. They thereupon became bound by the rules of law pertaining to arbitration. (Lindholm v. Galvin (1979) 95 Cal.App.3d 443 [157 Cal.Rptr. 167].) The policy of the law is to encourage and foster arbitration, and the arbitrator’s award is generally conclusive on matters of fact and law. (Lehto v. Underground Constr. Co. (1977) 69 Cal.App.3d 933 [138 Cal.Rptr. 419].)

The statutory scheme provides a process for correction of an arbitrator’s award by the arbitrator under certain limited conditions. 2 The arbitrator purported herein to act pursuant to sections 1284 and 1286.6, subdivision (a), which provides for correction in the event of an “evident miscalculation of figures.”

Evident Miscalculation of Figures

A review of the documentation surrounding the award provides the factual background for the trial court’s action. The correction concerned what the arbitrator later characterized as a miscalculation of the costs of removing the knotty pine siding to replace it with cedar.

In the letter accompanying the original award, 3 the arbitrator indicated that he considered the bid of a Mr. Bartels which specified the amount of $11,634 “to remove and install one-half inch plywood” over the frame *92 walls and $9,774 to then install tongue and groove cedar siding. The arbitrator decided, however, that the building plans had not called for the plywood, and it was not a bargained-for item; the award should only include the cost of removing the existing pine siding and replacing it with cedar and not the cost of the plywood. The arbitrator therefore awarded $15,000 for removal of and replacing the siding, a figure which excluded the plywood.

In his declaration accompanying the motion for confirmation of the amended award, the arbitrator asserted his reliance upon the Bartels proposal, but stated he believed the $11,634 figure to “[r]emove and install l/>” plywood over frame walls” meant to remove the existing pine exterior siding. The arbitrator stated that he did not believe that all of the exterior siding needed to be removed and chose instead to award the lesser sum of $5,226 for that task. The latter figure was then added to item 2 of the proposal which indicated a cost of $9,774 to install tongue and groove cedar on all exterior walls. When presented with the application to correct, the arbitrator states that in reviewing the testimony given at the hearing, it became clear to him that Bartels used the word “remove” in item 4 to refer to removing the windows which had to be done in any case. Thus, the total cost to repair the exterior walls was the sum of item 4 ($11,634) plus item 2 ($9,774), or a total of $21,408. The arbitrator thereupon corrected the award by adding the difference of $6,408.

The Severtsons characterize the original award as a miscalculation of figures; Williams urges that the correction was not a miscalculation, but a misinterpretation of the evidence. Both the original award and the amended award simply set forth the dollar amount entitlements, there being no statement of rationale contained therein.

The arbitrator’s award must be in writing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fishman v. Advisors CA2/7
California Court of Appeal, 2026
Ortiz v. Elmcrest Care Center, LLC
California Court of Appeal, 2024
Gavriiloglou v. Prime Healthcare Management
California Court of Appeal, 2022
Sutey Oil v. Monroe's High Country
2022 MT 50 (Montana Supreme Court, 2022)
Liberty Mutual Fire Ins. v. Vafi CA2/4
California Court of Appeal, 2022
Crooymans v. Givner CA2/3
California Court of Appeal, 2021
Hillair Capital Investments v. West CA2/2
California Court of Appeal, 2021
Lonky v. Patel
California Court of Appeal, 2020
Heimlich v. Shivji
441 P.3d 857 (California Supreme Court, 2019)
D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company
242 So. 3d 92 (Mississippi Supreme Court, 2018)
Heimlich v. Shivji
California Court of Appeal, 2017
Heimlich v. Shivji
218 Cal. Rptr. 3d 576 (California Court of Appeals, 5th District, 2017)
Syson v. Montecito Bank & Trust CA2/6
California Court of Appeal, 2016
Baxter v. Bock
California Court of Appeal, 2016
Bucur v. Ahmad
244 Cal. App. 4th 175 (California Court of Appeal, 2016)
Cooper v. Lavely & Singer Professional Corp.
230 Cal. App. 4th 1 (California Court of Appeal, 2014)
Clark v. Zellet CA2/6
California Court of Appeal, 2014
Woolsey v. Woolsey
220 Cal. App. 4th 881 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
173 Cal. App. 3d 86, 220 Cal. Rptr. 400, 1985 Cal. App. LEXIS 2609, Counsel Stack Legal Research, https://law.counselstack.com/opinion/severtson-v-williams-construction-co-calctapp-1985.