D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company

242 So. 3d 92
CourtMississippi Supreme Court
DecidedMay 10, 2018
DocketNO. 2017–CA–00116–SCT
StatusPublished
Cited by5 cases

This text of 242 So. 3d 92 (D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company, 242 So. 3d 92 (Mich. 2018).

Opinion

BEAM, JUSTICE, FOR THE COURT:

¶ 1. This Court adheres to the widely recognized standards providing for a trial court's amendment of an arbitration award under limited conditions. Importantly, those standards provide that a court may modify an arbitrator's award to correct an evident miscalculation of figures before entering its judgment. See Miss. Code Ann. § 11-15-135 (Rev. 2004). However, this Court has yet to determine what qualifies as an evident miscalculation and to what extent a judge may inquire to determine whether such a miscalculation exists.

¶ 2. Through the analysis below, we find first that the miscalculations alleged in this matter are not evident from the award itself, nor are they apparent from the agreed-upon record. Additionally, we find that the judge erred when he allowed the parties to present witness testimony regarding the extent of any alleged miscalculations, rather than relying on the award and the arbitration record as the relevant law suggests. Finding error, we reverse the circuit court's decision and remand this case to the circuit court with directions to confirm the December 8, 2015, arbitration award. Furthermore, because the subcontract between the parties provides that each contractor will be responsible for his own fees and costs, the Court declines to assess costs to one party over the other, and instead, enforces their bargained-for agreement.

FACTS AND PROCEDURAL HISTORY

¶ 3. Yates Construction, LLC, and D.W. Caldwell, Inc., entered into a construction subcontract for the roof installation on a residential dormitory at Auburn University in Auburn, Alabama. Caldwell-the roofing subcontractor-began work on the roof in October 2012. Early on, Caldwell employees identified structural issues with the building, preventing the company from moving forward with the roof installation. Caldwell notified Yates of the issues, and after some discussion about the repairs needed, Caldwell agreed to repair the building prior to installing the roof. Rather than amending the existing subcontract or creating a new contract for the repair expenses, Yates urged Caldwell to bill against "unperformed work" for those costs related to the extra work completed. Although the arrangement was unconventional, Caldwell orally agreed to the billing scheme, requiring that it be paid weekly, on a "cost plus overhead and profit basis."

¶ 4. When Caldwell completed both the repairs and the roof installation, it had yet to receive total payment for the structural repairs. The companies disputed the scope and expense of these repairs and quickly negotiated their way to an impasse. Thereafter, Caldwell filed a claim against Yates for causing delay and increased costs by failing to pay for work performed, which was in breach of the agreements between the parties.

¶ 5. The parties proceeded to arbitration. Although the arbitration record was neither recorded nor transcribed, the parties concede that the arbitrator considered arguments, reviewed evidence, and heard witness testimony over the course of three days. He then reopened the proceedings for additional documentation, before issuing his thirteen-page award on December 8, 2015. Shortly thereafter, Yates timely filed its motion for clarification and/or correction of the arbitration award, which was summarily dismissed by the arbitrator. Noting that the award included no clerical, typographical, technical, or computational errors, the arbitrator determined he lacked the authority to re-evaluate the merits of any claim already decided, under the circumstances.

¶ 6. Within two weeks of the arbitrator's decision to deny Yates's motion, Caldwell requested that the circuit court confirm the award under Mississippi Code Section 11-15-125. One month later, Yates moved the trial court to alter, amend, or vacate the award under Mississippi Code Section 11-15-25. 1 With the understanding that Yates would provide oral argument on its motion at the award confirmation hearing, Caldwell filed a request to limit the presentation of proof before the circuit court.

¶ 7. The hearing on all three motions was held on December 1, 2016. The circuit court judge began by requesting arguments on Caldwell's motion to limit proof. Throughout the presentations, the court asked questions of the parties' representatives and heard arguments on several issues under discussion. Believing that an evident miscalculation was present as it related to the retainage amounts 2 included in both the subcontract and the final award, the court overruled Caldwell's request to limit proof and permitted the parties to proceed on Yates's motion to alter, amend, or vacate the arbitration award. During this second phase of the hearing, the trial court allowed the parties to introduce evidence and witness testimony. Though Caldwell's attorneys objected on the basis of whether such evidence was on the record during the arbitration and whether such testimony was considered by the arbitrator in his ultimate decision, the court allowed counsel for Yates to continue with his witness examination and evidence presentation.

¶ 8. Ultimately, the trial court reviewed fourteen exhibits and the testimony of one witness in making its decision. Based on this evidence, the court issued its order modifying the arbitrator's award on January 10, 2017. Under Mississippi Code Section 11-15-135 and the Federal Arbitration Act, the court determined that the award contained a "facially evident miscalculation which permitted ... Caldwell to receive double payment." Finding that the arbitrator had duplicated the labor costs for shingle installation in its award-once under the original subcontract and once under the oral agreement to repair the structural damage (referred to as the Repair Agreement)-it amended the award, reducing the total by $104,507.

¶ 9. On appeal, Caldwell argues that the trial court erred when it denied the motion to limit proof and allowed Yates to present evidence and witness testimony. Caldwell also contends that the trial court erred in finding that the arbitrator's award contained a facially evident miscalculation. We agree. Based on the analysis below, this Court finds that the arbitrator's award contained no evident miscalculations which would merit modification. Moreover, the circuit court erred by allowing Yates to present witnesses before the court. Therefore, we reverse the decision of the Neshoba County Circuit Court and remand for the court to confirm the arbitration award.

APPLICABLE LAW

¶ 10. This matter involves a contract's choice-of-law provision and the applicability of federal and state statutes, as well as trade-association regulations. Caldwell (a Georgia-based company) and Yates (a Mississippi corporation) entered into a subcontract in Mississippi to be performed in Alabama. It is undisputed that, between the two companies, their employees, and their distributors, both labor and materials crossed state lines. Unquestionably, these facts affect interstate commerce, creating the need to continue under the mandate of the Federal Arbitration Act. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
242 So. 3d 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-w-caldwell-inc-v-wg-yates-sons-construction-company-miss-2018.