S&B/BIBB Hines PB 3 Joint Venture v. Progress Energy Florida, Inc.

365 F. App'x 202
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 11, 2010
Docket09-12150
StatusUnpublished
Cited by6 cases

This text of 365 F. App'x 202 (S&B/BIBB Hines PB 3 Joint Venture v. Progress Energy Florida, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S&B/BIBB Hines PB 3 Joint Venture v. Progress Energy Florida, Inc., 365 F. App'x 202 (11th Cir. 2010).

Opinion

*203 PER CURIAM:

This diversity action for breach of contract arises out of two multimillion dollar fixed price contracts dealing with the construction of two electric generating plants in Polk County, Florida. 1 Contractor S&B/BIBB Hines PB 3 Joint Venture and S&B Engineers and Constructors, Ltd. (“S&B”) agreed to perform the engineering, procurement, and construction work on the plants for owner Project Energy Florida, Inc. (“Project Energy”). During the course of performance, four hurricanes struck Polk County and three hurricanes hit the Gulf Coast, resulting in a shortage of labor and materials and a corresponding increase in the cost of construction for S&B. Global economic forces also contributed to an unanticipated increase in S&B’s materials costs.

S&B filed this action against Project Energy to recover approximately $40 million in additional compensation over and above the contract’s firm, fixed price. S&B alleges that Project Energy breached the contracts by refusing to provide compensation for its unforeseen labor and materials costs. S&B also alleges that Project Energy wrongfully recruited and hired away S&B employees during the contract term, thereby breaching the contracts and aiding and abetting a breach of fiduciary duty by S&B employees.

The district court dismissed the majority of S&B’s breach of contract and wrongful hiring claims on a Rule 12(b)(6) motion. S&B now seeks reinstatement of its claims, arguing that the district court misinterpreted the construction contracts and misapplied Florida law.

I. Breach of Contract

We review de novo the interpretation of a contract, Daewoo Motor Am., Inc. v. Gen. Motors Corp., 459 F.3d 1249, 1256 (11th Cir.2006), and the dismissal of a complaint for failure to state a claim pursuant to Federal Rule of Civil Procedure 12(b)(6), Redland Co. v. Bank of Am. Corp., 568 F.3d 1232, 1234 (11th Cir.2009). “A complaint may be dismissed if the facts as pled do not state a claim for relief that is plausible on its face.” Sinaltrainal v. Coca-Cola Co., 578 F.3d 1252, 1260 (11th Cir.2009).

The district court concluded that the fixed price contracts foreclosed any recovery of additional compensation beyond the contract price. We agree. Section 11 of the parties’ contracts addresses compensation. Section 11.A.1 provides that S&B, as the project contractor, “shall provide pricing for this Work at a firm fixed price.” “A pure fixed price contract requires the contractor to furnish the goods or services for a fixed amount of compensation regardless of the costs of performance, thereby placing the risk of incurring unforeseen costs of performance on the contractor.... ” Bowsher v. Merck & Co., Inc., 460 U.S. 824, 826 n. 1, 103 S.Ct. 1587, 1590 n. 1, 75 L.Ed.2d 580 (1983). In a fixed price contract, “if the final total costs of the agreed upon services exceed the contracted price, the contractor takes the loss; conversely, he can profit if the costs are lower than the contract price.” United States v. White, 765 F.2d 1469, 1472 (11th Cir.1985).

Section ll.A.l of the contracts defines “the Work” that is to be provided for a firm, fixed price as “all material, equipment, workmanship, labor, engineering, *204 and any other items or labor performed or furnished.” According to Section 11.C.8, another compensation provision: “No extra payment shall be allowed over and above the Contract Price except for work authorized by a Change Order or Amendment from Owner.”

Despite the fixed price nature of the contracts and the absence of any change order or contract amendment, S&B argues that it is entitled to recover its additional labor and materials costs due to the hurricanes and global economic forces. To support its claim, S&B relies on Section 37.A.3, which addresses S&B’s rights and obligations if a Force Majeure event occurs during contract performance. 2 Section 37.A.3, which is part of the contracts’ “no damage for delay” provision, 3 requires S&B to mitigate costs related to Force Majeure events, providing:

Should contractor be delayed in the commencement, performance or completion of the Work due to any of the conditions provided for under Section 37B, Force Majeure, Contractor shall be entitled to an extension of time only, provided however, that in no event shall Contractor be entitled to any increased costs, additional compensation, or damages of any type resulting from such Force Majeure delays, upon the conditions as permitted and provided for under Section 37B. Contractor shall use all reasonable means to minimize the extent of any interference, disruption, hindrance, or delay as aforesaid and to mitigate any and all costs from or related to any such cause or occurrence.

(emphasis added). S&B reads Section 37.-A.3 as imposing both an express obligation on S&B to mitigate costs related to a Force Majeure event and a corresponding implied obligation on Project Energy to compensate S&B for any costs it incurs in responding to a Force Majeure event. The essence of S&B’s argument is that the contracts’ firm, fixed price does not include S&B’s costs incurred due to unforeseeable Force Majeure events. We cannot endorse this interpretation of the contracts.

It is a well-settled rule of contract interpretation that courts must read provisions of a contract harmoniously in order to give effect to all portions thereof. Equity Lifestyle Props., Inc. v. Fla. Mowing & Landscape Serv., Inc., 556 F.3d 1232, 1242 (11th Cir.2009) (internal quotations and citations omitted); Triple E Development Co. v. Floridagold Citrus Corp., 51 So.2d 435, 438-39 (Fla.1951). Under Florida law, a “contract should be considered as a whole in determining the intention of the parties to the instrument,” City of Homestead v. Johnson, 760 So.2d 80, 84 (Fla.2000), and we “give effect to the plain language of contracts when that language is clear and unambiguous.” Equity Lifestyle Props., 556 F.3d at 1242 (internal quotations and citations omitted).

A plain reading of the whole contract indicates that the parties intended to include all labor and materials costs in the firm, fixed price, even those arising from Force Majeure events.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mp, LLC v. Sterling Holding, LLC
District Court of Appeal of Florida, 2017
Jonathan E. Perlman v. Wells Fargo Bank, N.A.
559 F. App'x 988 (Eleventh Circuit, 2014)
Wiand v. Wells Fargo Bank, N.A.
938 F. Supp. 2d 1238 (M.D. Florida, 2013)
Doe v. PRINCESS CRUISE LINES, LTD.
696 F. Supp. 2d 1282 (S.D. Florida, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
365 F. App'x 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sbbibb-hines-pb-3-joint-venture-v-progress-energy-florida-inc-ca11-2010.