International Erectors, Inc. v. Wilhoit Steel Erectors & Rental Service

400 F.2d 465
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 18, 1968
Docket24867_1
StatusPublished
Cited by75 cases

This text of 400 F.2d 465 (International Erectors, Inc. v. Wilhoit Steel Erectors & Rental Service) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Erectors, Inc. v. Wilhoit Steel Erectors & Rental Service, 400 F.2d 465 (5th Cir. 1968).

Opinion

GOLDBERG, Circuit Judge.

This is a ease of frustration arising out of unilateral and unarticulated contract expectations. The two questions presented here are (1) whether the contract between International Erectors, Inc., and Wilhoit Steel Erectors & Rental Service which subcontracted the work to International imposed any duty upon Wilhoit to supply materials according to *467 certain specifications and in a particular sequence, and (2) whether International, a sub-sub-sub-contractor may recover upon a third party beneficiary theory against Southern Engineering which had a contract with the general contractor, not a party to this suit, to fabricate and erect the steel.

I. Facts

This diversity action 1 for breach of contract was brought by International against Wilhoit. The respective disputes arise out of contracts dealing with the construction of a plant for Sunbeam Electronics Company in Fort Lauderdale, Florida. The responsibility for construction of the plant was given to a general contractor who subcontracted to Southern the work of fabricating and erecting the structural steel portion of the job. Southern, while retaining the responsibility as to the general contractor for providing the steel for the construction job, sub-sub-contracted the erection of the steel to Wilhoit. Wilhoit sub-sub-sub-contracted the job of erecting the steel to International, but retained a duty to Southern to supervise and assist the erection.

The loss which International seeks to recoup by this suit occurred when the steel to be erected by International was not delivered in the proper condition and time sequence. International alleges that it had the necessary men and equipment present on the job site, but that the misfeasance of the steel supplier prevented the erection from proceeding as scheduled. This delay allegedly caused $36,-559.09 damages in the form of additional costs of labor and equipment, additional overhead, and loss of profit.

International can recover from these defendants only if one or both had a contractual obligation to furnish the steel to International. 2 The district court, sitting without a jury, held that Wilhoit was under no contractual obligation to supply steel to International. As to Southern the court, after four amended complaints, dismissed the suit with prejudice, holding that International had failed to allege any breach of duty. From these determinations International appeals.

II. International v. Wilhoit

Since this is a diversity action, we interpret this contract according to the substantive law of Florida. Erie R. R. v. Tompkins, 1938, 304 U.S. 64, 58 S. Ct. 817, 82 L.Ed. 1188; Starling v. Gulf Life Ins. Co., 5 Cir. 1967, 382 F.2d 701, 705. We have not, however, found any Florida ease directly in point under the facts presented here. We therefore must decide this case as we believe the Florida courts would decide if confronted with these facts. Stevens Industries, Inc. v. Maryland Casualty Co., 5 Cir. 1968, 391 F.2d 411, 413, and cases therein cited. Certain general principles of Florida contract law are clarion and we construe the contract between Wilhoit and International in the light of those principles.

The Florida Supreme Court has taken the position that crystalline and unambiguous language in a written contract is controlling as to the intention of the parties and thus to the legal effect of the contract provisions. In Durham Tropical Land Corp. v. Sun Garden Sales Co., 1931, 106 Fla. 429, 138 So. 21, reh. den., 1932, 106 Fla. 429, 143 So. 758, af *468 firmed 106 Fla. 429, 151 So. 327, the rule was stated as follows:

“The intention of the parties to a contract is to be deducted from language employed, and such intention, when expressed, is controlling, regardless of intention existing in the minds of parties. Stokes v. Victory Land Co., 99 Fla. 795, 128 So. 408, and cases there cited.” 138 So. 21 at p. 23.

See also Gendzier v. Bielecki, FIa.1957, 97 So.2d 604; Hamilton Const. Co. v. Board of Public Instruction, Fla.1953, 65 So.2d 729, 731; Lyng v. Bugbee Distributing Co., 1938, 133 Fla. 419, 182 So. 801, 802; Hurley v. Werley, Fla.Dist.Ct. App.1957, 203 So.2d 530, 537-538; Azalea Park Utilities v. Knox-Florida Develop. Corp., Fla.Dist.Ct.App.1961, 127 So.2d 121, 122-123. In construing such contractual language courts should attempt to give words and phrases the natural meaning or the meaning most commonly understood when considered in reference to the subject matter and the circumstances. Rupp Hotel Operating Co. v. Donn, 1947, 158 Fla. 541, 29 So.2d 441, 445; Florida Boca Ratan Housing Assoc, v. Marqusee Assoc., Fla.Dist.Ct. App.1965, 177 So.2d 370, 373; Miami National Bank v. Fink, Fla.Dist.Ct.App. 1965, 174 So.2d 38, 40.

The contract between Wilhoit and International Erectors provided that International Erectors was to “furnish all necessary labor, supervisions, equipment, supplies to unload from rail cars, haul, erect and touch-up paint approximately 225 tons of structural steel and 100 tons facia plates” in accordance with certain plans and specifications. This contract, which designated Wilhoit as “contractor” and International Erectors as “subcontractor” and Southern as “owner,” provides in part as follows:

“Subcontractor [International] agrees to furnish and supply at Subcontractor’s expense, unless hereinafter specified to the contrary, all labor, transportation, materials, apparatus, fuel, energy, light, water, scaffolding, tools, and other facilities necessary for
the execution of the work specified in Paragraph First above.
“Contractor [Wilhoit] agrees to furnish and supply, at its expense, the following labor, materials, etc., for the doing and performing of the work specified in Paragraph First above, to-wit:
“NONE.” (Emphasis added.)

We agree with the district court that this language expresses pellueidly and without ambiguity that at the time the contract was executed the parties did not contemplate that Wilhoit was to be responsible for the delivery of the steel. The use of the word “NONE” in the blank reserved for a description of the materials to be supplied by Wilhoit is an absolute and unequivocal statement that Wilhoit was not to be responsible for the delivery of any materials. “None” cannot mean “some,” and without an obligation that some steel be delivered there can be no contractual responsibility for a failure to properly deliver steel.

Notwithstanding the preceding unmistakable disclaimer of all responsibility for providing materials, International argues: “By the contract of June 5,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pimentel v. Strength20, LLC
M.D. Florida, 2024
Davis v. Lockett
M.D. Florida, 2020
Larrabee v. Masarone
M.D. Florida, 2019
Carver Middle School Gay-Straight Alliance v. School Board
2 F. Supp. 3d 1277 (M.D. Florida, 2014)
United States v. Florida West International Airways, Inc.
853 F. Supp. 2d 1209 (S.D. Florida, 2012)
CYBER ZONE E-CAFE, INC. v. King
782 F. Supp. 2d 1331 (M.D. Florida, 2011)
Rebman v. Follett Higher Education Group, Inc.
248 F.R.D. 624 (M.D. Florida, 2008)
New Lenox Industries, Inc. v. Fenton
510 F. Supp. 2d 893 (M.D. Florida, 2007)
Mercado Arocho v. United States
455 F. Supp. 2d 15 (D. Puerto Rico, 2006)
Jordan v. Trans Union LLC
377 F. Supp. 2d 1307 (N.D. Georgia, 2005)
Thompson v. Rinker Materials of Florida, Inc.
390 F. Supp. 2d 1165 (M.D. Florida, 2005)
Craig v. Park Financial of Broward County, Inc.
390 F. Supp. 2d 1150 (M.D. Florida, 2005)
Alfred L. Bochese v. Town of Ponce Inlet
405 F.3d 964 (Eleventh Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
400 F.2d 465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-erectors-inc-v-wilhoit-steel-erectors-rental-service-ca5-1968.