J. T. Majors & Son, Inc. v. Lippert Bros., Inc., Lippert Bros., Inc., Cross-Appellant v. J. T. Majors & Son, Inc., Cross-Appellee

263 F.2d 650, 1958 U.S. App. LEXIS 6074
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 30, 1958
Docket5958_1
StatusPublished
Cited by20 cases

This text of 263 F.2d 650 (J. T. Majors & Son, Inc. v. Lippert Bros., Inc., Lippert Bros., Inc., Cross-Appellant v. J. T. Majors & Son, Inc., Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. T. Majors & Son, Inc. v. Lippert Bros., Inc., Lippert Bros., Inc., Cross-Appellant v. J. T. Majors & Son, Inc., Cross-Appellee, 263 F.2d 650, 1958 U.S. App. LEXIS 6074 (10th Cir. 1958).

Opinion

BREITENSTEIN, Circuit Judge.

Appellee-defendant, Lippert Bros., Inc., 1 had the prime contract for the construction of an abbey at Atchison, Kansas, and made a subcontract with appellant-plaintiff, J. T. Majors & Sons, Inc., 2 for the masonry work. Majors completed performance and brought suit alleging nonpayment for certain work done. Jurisdiction is based on diversity of citizenship.

The first claim relates to the cleaning of interior masonry and the second claim to the cleaning of exterior masonry. As to each of these claims the trial court directed a verdict in favor of defendant Lippert. The third claim covering the alteration of anchor holes was submitted to the jury which allowed the plaintiff a recovery of $4,322.73. As to this claim Lippert through a third-party complaint asserted that the liability, if any, was that of Forburger Company, Inc. After verdict, the court on its own motion reduced the recovery to $1,688.80 and entered judgment for that amount. The issues under the third-party complaint were settled by agreement. The fourth claim involved the pointing of terrazzo and the jury allowed recovery. Here also there was a third-party complaint, this time alleging that the liability was that of Advance Terrazzo Co., Inc., and a settlement was made by agreement.

Majors has appealed from the actions of the trial court in directing a verdict as to claims one and two and in reducing the jury verdict on claim three. Lip-pert filed a cross-appeal contending that there should be no recovery on the third claim but subsequently moved to dismiss that cross-appeal.

*653 The first two claims, which present the question of whether Majors is entitled to be paid for cleaning masonry, may be considered together. The subcontract provided that Majors, the subcontractor, was “to furnish labor to install masonry work as follows.” The itemization which follows contains 12 items with unit prices covering various types of brick, stone, tile, glass blocks, and granite. No reference is made to cleaning. The subcontract contains the common provision requiring extra work or changes to be agreed to in writing. 3 The subcontractor agreed to be bound by all terms and conditions of the general contract. The specifications made a part of the prime contract had two provisions relating to cleaning. 4

Before the execution of the subcontract the prime contractor had laid about 18,000 brick and between 4,000 and 4,500 feet of split-faced stone. The subcontractor cleaned this brick and stone as well as all masonry laid by it. The basis of its first two claims is that the subcontract required Majors to “install” but not to “clean,” and that the cleaning was done by it under an oral agreement with the prime contractor’s construction foreman. Lippert contends that the term “install” includes cleaning, that the construction superintendent had no authority to make any oral contract with Majors, and that the provisions of the subcontract requiring agreements for extra work or changes to be in writing precludes any such oral agreement.

Majors, asserting that the subcontract had a latent ambiguity, offered evidence of precontract conversations tending to show an intent not to include cleaning. The court held that the contract was not ambiguous and rejected the offer. Majors also offered testimony as to the technical meaning of the term “install.” This was received together with rebutting evidence with the result that there was a confusing conflict from which the conclusion can be reasonably drawn that when masonry work is covered by a lump sum contract cleaning is included but when it is a unit contract cleaning is not included unless specified.

Here we have a subcontract itemizing the work and providing for compensation on a unit basis. The reference to the general contract is unimportant. The obligation on the prime contractor to clean does not automatically fall on the subcontractor.

It is significant that Majors cleaned the brick and cut stone that had been laid by the prime contractor before the execution of the subcontract. No possible interpretation of the itemizations contained in the subcontract required it to do so. The testimony of an official for Lippert that payment for such work was made under “negotiated” quantities is far from convincing.

In the circumstances of this case it cannot be said with certainty what the parties meant by the use of the word “install.” The subcontract is ambiguous as the intention of the parties cannot be ascertained therefrom. In such a situation “the background against which the contract was executed and the circumstances attending its execution should be taken into consideration as an aid to the ascertainment of such intent.” 5 The trial court erred in rejecting the evidence as to the preliminary negotiations between the parties. While the interpretation of contractual language is a question of law, 6 in a sit *654 uation such as this where meaning depends on extrinsic evidence, there may result a material conflict or the possibility of more than one reasonable inference, either of which could present a question of fact rather than law. 7 We are unable to say whether on retrial such a factual issue will be presented.

The trial court directed a verdict as to claims one and two on the ground that there was no showing of authority in Lippert’s construction superintendent to contract with Majors for the cleaning. The record shows that such superintendent, who had no superior officer in Kansas, hired, fired, directed, and paid the workers on the job. He ordered and. paid for certain supplies but his check-writing authority was limited. A vice-president of Lippert testified that the superintendent had no authority to bind Lippert either orally or in writing. The superintendent admittedly kept a record of the time spent by Majors in the cleaning operations but did not keep such records in regard to other work done by Majors. An offer of Majors to prove its oral contract with the superintendent for the cleaning was rejected on the ground that there was no proof of his authority to bind Lippert.

An official of Majors testified that the superintendent was “in full charge” and was “the man we had to go to for everything.” Lippert knew that the cleaning work was being done as its vice-president testified that the cleaning of the brick and stone laid before Majors went on the job was paid for by “negotiated” quantities. Lippert did not notify Majors of any limitation on the superintendent’s authority. Lippert has acknowledged liability under the superintendent’s oral agreement for the alteration of the anchor holes. 8 Certainly the evidence is sufficient to justify the reasonable inference that the superintendent had authority to bind his principal. The question of authority of an agent is ordinarily one of fact. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
O'gilvie v. International Playtex, Inc.
821 F.2d 1438 (Tenth Circuit, 1987)
Smith v. Merritt Savings & Loan, Inc.
295 A.2d 474 (Court of Appeals of Maryland, 1972)
Steenberg Construction Co. v. Prepakt Concrete Co.
381 F.2d 768 (Tenth Circuit, 1967)
United States v. Continental Oil Company
364 F.2d 516 (Tenth Circuit, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
263 F.2d 650, 1958 U.S. App. LEXIS 6074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-t-majors-son-inc-v-lippert-bros-inc-lippert-bros-inc-ca10-1958.