Salliotte v. King Bridge Co.

122 F. 378, 65 L.R.A. 620, 1903 U.S. App. LEXIS 4767
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 20, 1903
DocketNo. 1,130
StatusPublished
Cited by34 cases

This text of 122 F. 378 (Salliotte v. King Bridge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salliotte v. King Bridge Co., 122 F. 378, 65 L.R.A. 620, 1903 U.S. App. LEXIS 4767 (6th Cir. 1903).

Opinion

BURTON, Circuit Judge,

having stated the case as above, delivered the opinion of the court.

1. The present structure took the place of an old bridge. It is not averred that the bridge was constructed without authority or unlawfully, and there was no evidence offered tending to show that the two townships were without authority in replacing the old by the new bridge, or exceeded their authority in contracti'ng for the construction of the particular bridge here in question. Under the law of Michigan, the county board of supervisors had the power to determine when and where navigable streams may be crossed by bridges; and, in the absence of any averment or evidence to the contrary, we must assume that this bridge was lawfully constructed, the townships having obtained the consent of the proper authority. Nelson v. Navigation Company, 44 Mich. 7, 5 N. W. 998, 38 Am. Rep. 222; Pratt v. Brown, 106 Mich. 628, 633, 64 N. W. 583. So far as the consent and approval of the United States was essential, that was obtained; the plans and specifications of the bridge having been submitted to, and approved by, the Secretary of War, 26 Stat. 454 (section 7, Act Sept. 19, 1890).

2. So far as the plaintiff’s declaration proceeded upon the ground of either unskillfulness or negligence in the construction of the bridge, or its abutments and pier, there was no substantial evidence upon which a verdict might have been returned against the King Bridge Company. The plans for the bridge, including its abut[380]*380ments and piers, were prepared under the direction and supervision of the authorities contracting for the erection of the bridge, and approved by the Secretary of War; and when so adopted the work of construction was let out, as a whole, to the King Bridge Company. That company contracted with a third person to construct the bridge abutments and piers, and this substructure was located •and constructed under the constant supervision of the civil engineer representing the owners of the bridge. The only charge of negligence is “that, to save the expense of hauling dirt from a distance, [the defendant] did, by a dredge, dig up a large amount of dirt next to the Ecorse abutment of said bridge; thereby tearing away the natural channel bank of the said River Rouge, and widening the same at that place,” etc. Now, if it was either unskillful or negligent to so dredge the river next the abutment on plaintiff’s side of the river, it was the negligence of an independent contractor, and not that of the defendant. The firm which built the abutments, and did the excavation for their foundation and the dredging in front when built, contracted to do that particular work in accordance with the plans and specifications already prepared. They did not become the general servants of the King Bridge Company, but only contracted to do for that company a specific work. That the bridge company, through its engineer or other agent, exercised some kind of general supervision, does not affect the question, where that is only for the purpose of seeing that the specific work is done in accordance with the contract. In such circumstances, those who contract to produce a finished structure according to plans furnished are independent contractors, responsible for their own acts of negligence. Powell v. Virginia Construction Co., 88 Tenn. 697, 13 S. W. 691, 17 Am. St. Rep. 925; Casement v. Brown, 148 U. S. 615, 13 Sup. Ct. 672, 37 L. Ed. 582; Railway Co. v. Martin, 100 Ala. 511, 14 South. 401. A general contractor is not liable to third persons for the negligent acts of an independent subcontractor unless the thing contracted to be done is necessarily a public nuisance, or the injury is a direct result from the act or thing which the independent contractor is required to do. 16 A. & Eng. Ency. Law, 192, 196; Quarman v. Burnett, 6 M. & W. 499; Laugher v. Pointer, 5 B. & C. 560; Blake v. Ferris, 5 N. Y. 48, 55 Am. Dec. 304; Robbins v. Chicago, 4 Wall. 657, 18 L. Ed. 427; Casement v. Brown, 148 U. S. 615, 13 Sup. Ct. 672, 37. L. Ed. 582. This principle of nonliability for the negligence of an independent contractor applies to and exempts the general contractor. Powell v. Virginia Const. Co., 88 Tenn. 692, 13 S. W. 691, 17 Am. St. Rep. 925; Rapson v. Cubitt, 9 M. & W. 710; Slater v. Mersereau, 64 N. Y. 138.

3. But aside from this, the evidence clearly established that the dirt excavated at the edge of the river bank, where the road touches the river for the purpose of making a pit for the foundation of the abutment, was thrown on the river side and into the river to make an embankment to keep the water out. When the abutment was finished, the dirt thus thrown into the edge of the river was dredged out and used to fill in behind the abutment. There was no substantial evidence that the dirt dredged and used- to form the bridge [381]*381approach exceeded that thrown into the river, or that the river bank was cut away either to save hauling, or for any other unlawful purpose, or in a negligent or unskillful manner.

4. So far as the plaintiff’s case is rested upon damages due to any defective construction for which the defendant might be liable upon its contract to the owners of the bridge, it is not maintainable, because there is not the slightest evidence that any damage occurred until after the completion of the bridge and its acceptance by the townships. There is no rule under which a third person may recover damages against a builder or contractor for an injury sustained by reason of defective construction, if the thing constructed is not inherently and necessarily dangerous, when the injury did not occur until after the builder or contractor had parted with the possession and title. The liability of the builder or contractor for defective-construction is to the person with whom he was under contractual relations, and a stranger can hold him liable after he has parted with the possession only under exceptional circumstances. Marquardt v. Ball Engine Co., 122 Fed. 374. This rule has been applied to suits by strangers for injury arising from defective construction of bridges and houses, when it -was sought to hold the contractor liable after completion of his work (The Mayor of Albany v. Cunliff, 2 N. Y. 165; Curtin v. Somerset, 140 Pa. 70, 21 Atl. 244, 12 L. R. A. 322, 23 Am. St. Rep. 220), and to an action against a contractor for an injury from a bursting sewer. First Presbyterian Cong. v. Smith, 163 Pa. 561, 30 Atl. 279, 26 L. R. A. 504, 43 Am. St. Rep. 808. In Blunt v. Aikin, 15 Wend. 522, 30 Am. Dec. 72, it was held that an action on the case for flowing lands will not lie against a former owner of the dam, who erected the dam and built the wall by means of which the injury was done, when it appears that other persons are in possession of the premises, occupying them as their own, not being tenants of such former owner.

5. The river Rouge between the stone abutments of the bridge is 198 feet wide. The pier upon which the bridge swings is in the center of the river, and is 32 feet wide. This pier obstructs what had been the deep, navigable channel of the river, and rendered necessary the deepening of the river on one or the other side of the pier so as to continue the navigability of the river. The act of 1890 (Act Sept. 19; 26 Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evergreen International, S.A. v. Marinex Construction Co.
477 F. Supp. 2d 690 (D. South Carolina, 2007)
Schank v. Clarkson Construction Co.
368 S.W.2d 720 (Missouri Court of Appeals, 1963)
International Harvester Co. v. Sartain
222 S.W.2d 854 (Court of Appeals of Tennessee, 1948)
Price v. Johnston Cotton Co. of Wendell
40 S.E.2d 344 (Supreme Court of North Carolina, 1946)
Sester v. Belvue Drainage District
173 P.2d 610 (Supreme Court of Kansas, 1946)
United States v. Dickinson
152 F.2d 865 (Fourth Circuit, 1946)
Grand River Dam Auth. v. Bd. of Ed. Town Wyandotte
1943 OK 424 (Supreme Court of Oklahoma, 1943)
Gulf Refining Co. v. Mark C. Walker & Son Co.
124 F.2d 420 (Sixth Circuit, 1942)
Evans v. Massman Construction Co.
122 S.W.2d 924 (Supreme Court of Missouri, 1938)
Short v. Pierce County
78 P.2d 610 (Washington Supreme Court, 1938)
Evans v. Massman Construction Co.
115 S.W.2d 163 (Missouri Court of Appeals, 1938)
Sponenbarger v. United States
21 F. Supp. 28 (E.D. Arkansas, 1937)
Hough v. Central States Freight Service, Inc.
269 N.W. 1 (Supreme Court of Iowa, 1936)
Panhandle Const. Co. v. Shireman
80 S.W.2d 461 (Court of Appeals of Texas, 1935)
Russell v. General Const. Co.
59 S.W.2d 1109 (Court of Appeals of Texas, 1933)
Wilkey v. Rouse Construction Co.
28 S.W.2d 674 (Missouri Court of Appeals, 1930)
Ford v. Sturgis
14 F.2d 253 (D.C. Circuit, 1926)
Armstrong v. City of Tulsa
1924 OK 532 (Supreme Court of Oklahoma, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
122 F. 378, 65 L.R.A. 620, 1903 U.S. App. LEXIS 4767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salliotte-v-king-bridge-co-ca6-1903.