First Presbyterian Congregation v. Smith

30 A. 279, 163 Pa. 561, 1894 Pa. LEXIS 1216
CourtSupreme Court of Pennsylvania
DecidedOctober 1, 1894
DocketAppeal, No. 167
StatusPublished
Cited by32 cases

This text of 30 A. 279 (First Presbyterian Congregation v. Smith) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Presbyterian Congregation v. Smith, 30 A. 279, 163 Pa. 561, 1894 Pa. LEXIS 1216 (Pa. 1894).

Opinion

Opinion by

Mb. Justice Dean,

The church of plaintiff is a large brick building on the northwest corner of Second and Bushkill streets, in the city of Easton. On January 2, 1891, Bushkill street, in front of the-church, commencing at the line of Second street and extending along the street for 75 to 80 feet, caved in, taking with it a portion of the pavement. A large sewer and the water main* of the Lehigh Water Company were located longitudinally on* Bushkill street, and after the cave-in were found to be broken. A great quantity of water from both flowed towards the church, undermined the pavement and saturated the foundation, causing very serious damage to the property.

The plaintiff alleged the damage was caused by the negligent construction- of the sewer in this: The church service pipe-connecting with the water main had broken, and the water-flowing therefrom bad broken in the sewer, undermined the-pavement, and damaged the foundation, before being perceptible from the surface; the ground being frozen at the time, until the cave-in, the crust was not disturbed; the service pipe broke, it was alleged, because, in constructing the sewer, the [572]*572trench was negligently filled up—the plank sheeting, supporting temporarily the sides of the excavation during construction, being left in, and the cro.ss timbers permitted to remain resting on the service .pipe, and then the filling-up done by puddling instead of tamping. As a result, when the earth settled, the weight wrenched off the service pipe from its connection, and the injury followed.

The plaintiff held the defendants answerable for the consequences of this negligent work at the sewer, because, it was averred, they had, as independent contractors with the city of Easton, constructed it under a written contract made the 1st of April, 1890, in pursuance of which contract they had finished the work about June 12th following.

At the trial, there was much evidence on both sides on the questions : 1. Was the injury caused by the negligent construction of the sewer ? 2. If so, then did this negligence consist in following the directions of the city engineer, as provided in the contract?

The court, in a very full charge, submitted the evidence bearing on both’ questions to the jury. There was a verdict and judgment for defendants, and then this appeal, with thirty-eight assignments of error, each one of them pressed earnestly at the bar and in elaborate argument in voluminous paper-books.

At the trial below, as the case was presented by counsel, and-submitted by the court to the jury, the question of negligence was considered first, and that of answerability of defendants second. We reverse this order, and inquire, first, whether, under the contract and evidence, the defendants are answerable, regardless of proof of negligent construction ?

If the negligence which caused the injury was puddling up of the sewer trench, and leaving in the sheeting which rested on the service pipe, was this the act of the city, or that of the defendants as independent contractors ? If the city by the contract retained control of the method of performing the work, then, to the extent defendants followed the method prescribed, certainly they were not independent.

The city ordinance, under date of 29th of November, 1889, enacts: Sec. 1. “. . . . The department of sewers is hereby authorized to construct the following described sewers in ac[573]*573cordance with the adopted map and plan on file in the office of the city engineer.” Then follows a detailed enumeration of sewers, main and lateral, according to an elaborate plan. The sewer on Bushkill street is called Main Sewer B. Then section 4 enacts: “ Th$ building of said sewers shall be under the supervision and management of the city engineer.” Paragraph 47 of the contract stipulates that the sewer shall be constructed according to the plans on file, and according to the grades and lines- given by the engineer .... and the sides of the trench shall, at the contractor’s expense, be supported by proper timber-work, when required by the engineer, to prevent caving .... and, after-the completion of the brick-work, shall-be carefully filled up and tamped around the sewer in horizontal layers of not over six inches, until the filling reaches a height of one foot above the -top of the sewer, and then carried up in horizontal layers of not over nine inches, to the surface of the street, or within such distance of the surface as the engineer shall direct. And the engineer shall have the right to make alterations in the line, plan, form .or quantity of the work; and in consideration of the completion of the work in conformity with the specifications and stipulations, and in strict accordance with the instructions of the engineer, the city agrees to pay, etc. And so, all through the contract, the intent of the city is to reserve control, not only of how the work shall be done to meet the specifications, but to change or vary the specifications as circumstances might suggest during the progress of it. The contractors had but very little authority, independent of the city engineer; in substance, they were to follow the specifications, unless the' engineer directed otherwise; when the engineer did direct, then the city exercised the control it had reserved, and the contractors were, as to such work, not independent. ■ ■

On turning to the evidence touching on the filling of this trench in front of the church, we find that, by the ordinance, the sides of the trench were to be supported by timber-work when required by the engineer, to prevent caving, and the completion of the work, by the contract, was to be in- strict accordance with his instructions. The brick-work of the sewer having been finished, to complete the work, required tamping or puddling, either with the sheeting left on the sides of the [574]*574trench, or with it taken out. Then the engineer gives this •order:

“ Easton, Pa., June 10th, 1890.
■“ Messrs. Smith & Minnahan : -
“ You will not remove any of the sheet piling now on Bush-kill street between Front and Third streets, as I' am afraid by so doing you will interfere with the gas and water mains.
“Yours truly,
“ A. J. Cooper, Engineer.” .

The city had reserved the right to make such an order, and the contractors were bound to obey it; in so far as leaving the sheeting in was negligence,, the city was answerable for the consequences.

The engineer further testified that the method of filling up ■the trench was by his directions; that he directed them to puddle instead of tamping three feet above the archway to the sur-: face, and it was done as he directed; because, in his opinion, puddling as ordered bj^ him was better work than tamping. James Smith, one of defendants., who had supervision of the work in front of the church, testified that, after tamping three feet above the arch of the sewer, from there to the surface it was puddled as directed by the city engineer. ■ There is no evidence in the case which contradicts this testimony tending to .show that the work of filling the trench was wholly controlled by the city. There may have been negligence on the part of the city in the methods adopted, but, in giving such directions ■as were given, there was no usurpation of authority, but only the exercise of an authority reserved, and to be exercised, if the city chose, independent of the judgment of the contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodward v. Dietrich
548 A.2d 301 (Supreme Court of Pennsylvania, 1988)
Patraka v. Armco Steel Co.
495 F. Supp. 1013 (M.D. Pennsylvania, 1980)
Chesser v. King
428 S.W.2d 633 (Supreme Court of Arkansas, 1968)
Mahoney v. Walter Reed Corp.
12 Mass. App. Dec. 80 (Mass. Dist. Ct., App. Div., 1956)
Krisovich v. John Booth, Inc.
121 A.2d 890 (Superior Court of Pennsylvania, 1956)
Foley v. the Pittsburgh-Des Moines Co.
68 A.2d 517 (Supreme Court of Pennsylvania, 1949)
Miller v. Erie
16 A.2d 37 (Supreme Court of Pennsylvania, 1940)
Samford v. Petroleum Casualty Co.
81 S.W.2d 743 (Court of Appeals of Texas, 1935)
Bisson v. John B. Kelly, Inc.
170 A. 139 (Supreme Court of Pennsylvania, 1933)
Griffith v. Atlantic Refining Co.
157 A. 791 (Supreme Court of Pennsylvania, 1931)
Scalise v. F. M. Venzie Co., Inc.
152 A. 90 (Supreme Court of Pennsylvania, 1930)
Werner v. Trout
2 S.W.2d 525 (Court of Appeals of Texas, 1928)
Knopf v. Delaware County
140 A. 903 (Supreme Court of Pennsylvania, 1928)
Ford v. Sturgis
14 F.2d 253 (D.C. Circuit, 1926)
King v. Galloway
284 S.W. 942 (Texas Commission of Appeals, 1926)
Rengstorf v. Winston Brothers Co.
208 N.W. 995 (Supreme Court of Minnesota, 1926)
Armstrong v. City of Tulsa
1924 OK 532 (Supreme Court of Oklahoma, 1924)
Stubbs Et Ux. v. Duquesne L. Co.
84 Pa. Super. 1 (Superior Court of Pennsylvania, 1924)
Arizona Binghampton Copper Co. v. Dickson
195 P. 538 (Arizona Supreme Court, 1921)
Shepard v. Utah Light & Traction Co.
184 P. 542 (Utah Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
30 A. 279, 163 Pa. 561, 1894 Pa. LEXIS 1216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-presbyterian-congregation-v-smith-pa-1894.