Foley v. the Pittsburgh-Des Moines Co.

68 A.2d 517, 363 Pa. 1, 1949 Pa. LEXIS 450
CourtSupreme Court of Pennsylvania
DecidedApril 20, 1949
DocketAppeal, 83
StatusPublished
Cited by191 cases

This text of 68 A.2d 517 (Foley v. the Pittsburgh-Des Moines Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foley v. the Pittsburgh-Des Moines Co., 68 A.2d 517, 363 Pa. 1, 1949 Pa. LEXIS 450 (Pa. 1949).

Opinion

Opinion by

Mr. Justice Horace Stern,

This action arises out of a grave disaster which took place in the City of Cleveland, Ohio, on October 20,1944. Leakages occurred in a tank of the East Ohio Gas Company containing liquefied natural gas of a temperature of between 250 and 260 degrees below zero Fahrenheit; the tank collapsed, the liquid gas flowed out in all directions and became ignited, with the result that over a hundred persons lost their lives and some 231 separate suits for damages have been brought in Ohio and Pennsylvania, both in State and Federal courts, against the present and other defendants, most of them by widows of employes of the East Ohio Gas Company who were burned to death in the tragedy. Among the victims was Michael J. Foley, and the present action was instituted by his widow, Florence V. Foley, executrix of his estate, under the so-called Wrongful Death Statutes of the State of Ohio, for the benefit of herself and their three minor children, against Pittsburgh-Des Moines Company and Pittsburgh-Des Moines Steel Company, the manufacturers and installers of the tank, alleging negli *6 gence on their part in its design and construction and in the selection of the materials of which it was built. Plaintiff recovered a verdict in the Court of Common Pleas of Allegheny County of $50,000; the court en banc overruled a motion of defendants for a new trial but granted their motion for judgment n. o. v. Plaintiff now appeals from that decision.

The East Ohio Gas Company is a public utility distributing natural gas for industrial and domestic purposes in the City of Cleveland. Its problem was to acquire facilities for the storage of gas in sufficient quantity to meet the peak demand for it in the winter months. There was an experimental plant in West Virginia which liquefied natural gas under a patented process by which ammonia was cooled by water, ethylene by the ammonia, and the raw gas by the ethylene; the advantage of such liquefaction was that 600 cubic feet of the gas could be reduced to one cubic foot of liquid and therefore be stored in one-six hundredth of the space;, as and when needed it could be regasified for distribution and use. At this plant there had been built a small storage tank, cylindrical in shape, consisting of two shells, one within the other, with cork insulation between, operating somewhat on the principle of a thermos bottle. In .1940 the East Ohio Gas Company entered into a contract with the Gas Machinery Company, a Cleveland concern which owned the liquefaction patents and was engaged in the manufacture and installation of gas machinery equipment, for the erection of a liquefaction, storage and regasification plant at the East Ohio Gas Company’s No. 2 works located on a ten acre tract in an industrial section of the City of Cleveland. The Gas Machinery Company sublet different parts of the project, giving a contract for the erection of three storage tanks to the Pittsburgh-Des Moines Steel Company, the defendant partnership, which had been engaged for many years in the business *7 of building tanks and other large works of steel fabrication. As this was the first time an attempt was being made to store liquid gas on such a large scale for commercial use the Pittsburgh-Des Moines Steel Company consulted with one H. C. Cooper, who had designed the West Virginia plant and Avho will be referred to more at length hereafter, and, as a result of a combination of his ideas with theirs, they had the tanks built, spherical in form, by the Pittsburgh-Des Moines Company, th'e defendant corporation, which, as will subsequently appear, Avas an entity identical, for all practical purposes, with their OAvn partnership.

After these three tanks had been erected, put into Operation and found to be satisfactory, it was discovered by the East Ohio Gas Company in 1942 that additional storage capacity was needed to take care of the city’s requirements. Accordingly it entered into negotiations with defendants for the construction of a fourth tank which could store 100,000,000 cubic feet of natural gas, — twice the amount of each of the spherical tanks. Defendants offered to build such a tank based either on the model of the three former ones or on a vertical, cylindrical design with a toro-segmental bottom; they advised the East Ohio Gas Company that they were confident a cylindrical, toro-segmental-bottom tank would prove just as satisfactory as the spherical tanks and that it should be preferred because of a saving in cost. The East Ohio Gas Company thereupon entered into a contract with the Gas Machinery Company for such a tank and the latter in turn sub-contracted its construction to defendants. It was fabricated at Neville Island, Pittsburgh, by the defendant corporation and erected under the supervision of the construction engineer of the defendant partnership. Its outer shell was 51 feet high with a diameter of 76 feet, its inner shell 43 feet high with a diameter of 70 feet; the inner shell was built of 3y2% nickel steel, the outer of ordinary *8 carbon steel. Finding it difficult to obtain cork, which had been used as the insulating material between the inner and outer shells of the three spherical tanks, defendants employed rock wool for that purpose. After the tank was erected it was subjected to certain tests; later a crack developed which was repaired, and the tank was finally ready for operation in September, 1943; from time to time some defects appeared and certain additional repairs and installations were made.

The day before the accident three of the tanks, including No. 4, had been filled to their normal capacity for the anticipated Avinter demands, the remaining tank Avas being similarly filled, and the employes of the East Ohio Gas Company were starting to close doAvn the liquefaction operation; this Avas a more or less routine procedure, consisting of withdrawing from the system the ethylene and ammonia, shutting down the engines, and stopping the flow of gas. According to plaintiff’s testimony everything was proceeding smoothly throughout the plant. At about 2.40 o’clock in the afternoon of October 20th a witness in a building across an open field suddenly saw the No. 4 tank burst and liquid squirt out from it, apparently under pressure, at a point about ten feet above the retaining dike which had been constructed around its base. At first there Avere two streams that thus emerged, later there Avere seven or eight of them, and then the entire mass of the tank seemed to give way. There was testimony to the effect that no noise of any kind Avas heard, other testimony that there Avas a distant rumbling, Avhile one person said there was a sound as of falling steel. Several eye-witnesses testified that they saw streams of liquid coming out of breaks in the lower half of the tank and that the entire tank apparently collapsed after being enveloped in a cloud of vapor which instantly ignited. Fire spread over the entire area, the destruction of sur *9 rounding property ivas enormous, and the great loss of life that ensued has already been mentioned.

The problem in the case now presented is whether defendants were factually responsible, and, if so, legally liable, to plaintiff for the consequences of this accident.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Oil City Appeal of: Best
Supreme Court of Pennsylvania, 2023
T.M. v. Janssen Pharmaceuticals, Inc.
Superior Court of Pennsylvania, 2019
Nixon v. State
704 N.W.2d 643 (Supreme Court of Iowa, 2005)
Soave v. National Velour Corp.
863 A.2d 186 (Supreme Court of Rhode Island, 2004)
Pickens v. Tulsa Metropolitan Ministry
1997 OK 152 (Supreme Court of Oklahoma, 1997)
Resolution Trust Corp. v. Farmer
865 F. Supp. 1143 (E.D. Pennsylvania, 1994)
City of Philadelphia v. Lead Industries Ass'n
994 F.2d 112 (Third Circuit, 1993)
Garvey v. Dickinson College
761 F. Supp. 1175 (M.D. Pennsylvania, 1991)
Harford Mutual Insurance v. Moorhead
578 A.2d 492 (Supreme Court of Pennsylvania, 1990)
Centre Concrete Co. v. AGI, INC.
559 A.2d 516 (Supreme Court of Pennsylvania, 1989)
Merv Swing Agency, Inc. v. Graham Co.
579 F. Supp. 429 (E.D. Pennsylvania, 1983)
Lipitz v. Washington National Insurance
513 F. Supp. 606 (E.D. Pennsylvania, 1981)
Jones & Laughlin Steel Corp. v. Johns-Manville Sales Corp.
453 F. Supp. 527 (W.D. Pennsylvania, 1978)
Patterson Ex Rel. Patterson v. Her Majesty Industries, Inc.
450 F. Supp. 425 (E.D. Pennsylvania, 1978)
Berkebile v. Brantly Helicopter Corp.
337 A.2d 893 (Supreme Court of Pennsylvania, 1975)
Hooper v. Guthrie
390 F. Supp. 1327 (W.D. Pennsylvania, 1975)
Hughes v. Swinehart
376 F. Supp. 650 (E.D. Pennsylvania, 1974)
Dennis v. Ford Motor Company
332 F. Supp. 901 (W.D. Pennsylvania, 1971)
Hargraves v. Brackett Stripping MacHine Company
317 F. Supp. 676 (E.D. Tennessee, 1970)
Speyer, Inc. v. Humble Oil And Refining Company
403 F.2d 766 (Third Circuit, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
68 A.2d 517, 363 Pa. 1, 1949 Pa. LEXIS 450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foley-v-the-pittsburgh-des-moines-co-pa-1949.