Bisson v. John B. Kelly, Inc.

170 A. 139, 314 Pa. 99, 1934 Pa. LEXIS 457
CourtSupreme Court of Pennsylvania
DecidedDecember 5, 1933
DocketAppeal, 307
StatusPublished
Cited by60 cases

This text of 170 A. 139 (Bisson v. John B. Kelly, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bisson v. John B. Kelly, Inc., 170 A. 139, 314 Pa. 99, 1934 Pa. LEXIS 457 (Pa. 1933).

Opinions

Opinion by

Mr. Justice Maxey,

This is an appeal from the judgment of the Court of Common Pleas No. 2 of Philadelphia County, entered on a verdict in favor of plaintiff in the sum of $15,000, after defendant’s rule for a new trial and motion for judgment n. o. v. were discharged.

On February 17, 1931, the plaintiff, while working on the construction of a building, was hit on the head and seriously and permanently injured by a piece of tile fall *101 ing nearly fourteen feet and weighing twenty pounds. He was employed by the Gorham Company, subcontractor of the building’s bronze and ornamental iron work. Defendant was the subcontractor for the brick and hollow tile work and constructed, twelve inches from the main wall on the fifth floor, a “furring” wall, from the upper tier of which fell the piece of tile. This wall was eight feet in length from one window to another and was fourteen feet in height. It was built up to a line four feet below the ceiling, except at the middle, where the tiles were extended to the ceiling. It consisted of hollow tiles twelve inches wide and three inches thick. The tiles were set in cement. The wall’s only attachment to the main wall was by “returns” at each end, which were cemented to the main wall. Between the “returns” at each end, the tiles were not anchored to the main wall by metal ties. Except for these “returns” and a small attachment to the ceiling from the center of the top, this wall was not supported by ceiling brace, floor brace, or by any metal ties.

Outside of the window, which was contiguous to the tile wall, was a hoist used by stone masons. Its running caused a noticeable vibration. Just prior to the accident, plaintiff felt a vibration from the hoist.

An expert witness testified for the plaintiff that “in a case like this,” he “would not think it would be safe to let it [the cement] stand alone under twenty-eight days because there is sometimes shrinkage after it dries. ...... This shrinkage causes cracks in the mortar.” He also testified that vibration would adversely affect the cement’s holding power within a period of four days after it was used. The accident to plaintiff happened four days after the tiles were laid in cement. There was further expert testimony to the effect that the near-by vibration “would cause the breaking of the bond” of the tile.

At the time plaintiff was injured, he had stepped out of the window, where he had been oiling pulleys, to get *102 some more oil on a rag, and as lie leaned over to reach the can of oil the falling tile hit him on the head and arm.

The negligence averred was, in substance, that the defendant, its servants, etc., affixed this tile to the wall in a careless manner and permitted it to remain in a dangerous condition.

Apparently the defendant built the wall according to plans and specifications. Between the top of the wall and the main ceiling there was later to be erected by another contractor an artificial ceiling and to this ceiling the top of the fourteen-foot wall was to be “tied.” With that the defendant company had nothing to do, but it did know that some time would have to elapse after the completion of its work before the new contractor could begin his work on the artificial ceiling and the “tieing” of the wall thereto, for the holding cement would have to be given time to “set” before the complementary construction work could be begun.

We said in Pope v. Reading Co., 304 Pa. 326, 331, 156 A. 106: “While the doctrine of res ipsa loquitur does not apply to cases in which a plaintiff: is injured by a falling body, the negligent acts of omission by a defendant in such cases may be shown by establishing facts and circumstances from which his negligence may be legitimately inferred. It is not a case of presuming negligence from the mere happening of an accident, but it is a case of inferring negligence from the circumstances from which the accident apparently arises....... At common law it was held that every man must have some knowledge ‘of the quality of his beast’ (1 Hale P. C. 430) and use appropriate means to keep that beast from harming people. Public welfare requires that this same salutary rule apply to the inanimate objects in a man’s possession and subject to his intelligent control. For example, when a person places a milk bottle or other object on the window ledge of a building, he does so in the knowledge that the wind or some vibration may dislodge that bottle and gravity will cause it to fall.” We there *103 cited Ryan v. Woodbury Granite Co., 266 Pa. 105, 110 A. 279, where the plaintiff, who was an employee of a contractor engaged on a building construction, was injured by the falling of a portion of tile. In that case this court said: “Defendant knew that tiles supported only on three sides are more apt to fall than those supported on all four sides; and hence, in making the opening, and in inspecting the tiles surrounding it at the time it was made and thereafter until it was closed, defendant was bound to exercise care proportionate to the risk to which it thereby exposed those who would be constantly using the floor below.”

In the instant case the fact that defendant permitted a twenty-pound tile to remain unsecured, except by “green” cement, in the side of a wall fourteen feet above the floor where workmen were likely to be, which wall was not supported by a ceiling brace, floor brace or by any metal ties, and the further fact that this wall was near a hoist which when operated caused the wall to vibrate, are facts which here justified a finding of negligence.

The pivotal question is: A duty having been breached, with serious consequences to the plaintiff, who was the breacher? Appellant argues that “the duty breached (if any duty existed) rested on the general contractor to protect persons working on the floor from any danger lurking in this wall.” Appellant cites as the leading case on this question, Hooey v. Airport Const. Co. et al., 253 N. Y. 486, 171 N. E. 752. In that case an employee of the subcontractor was assigned the building of the walls of hangars. Other subcontractors, roofers, carpenters, and manufacturers of sash had their allotted tasks. One day the south wall of hangar No. 2 had been carried by the subcontractor to the level of the window sills. On the next day by 11 a. m. the brick piers had been built between the windows, and between the windows and the door. “The masons then gave way until the sash was set in place. They left their tools, bricks, and mortar on the *104 spot, for they would have to return at a later stage and construct the brick sills. An employee of the subcontractor for the sash began his work at the wall on the morning of the next day. The wall was eight inches thick, about fifty feet long, and nine feet high, with neither roof nor rafter nor partition to bind it to the hangar of which it was to form a part. It had been left standing in the open country, swept by heavy winds, without braces or supports. Shortly after the plaintiff began placing the sash, the piers toppled over and buried him below.” He sued the general contractor. The only question decided

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SPEAKS v. United States
E.D. Pennsylvania, 2024
Brown v. Oil City Appeal of: Best
Supreme Court of Pennsylvania, 2023
Stewart v. O.C. Cluss Lumber Co.
7 Pa. D. & C.5th 369 (Beaver County Court of Common Pleas, 2009)
McVeigh v. Irving
26 Pa. D. & C.4th 552 (Delaware County Court of Common Pleas, 1995)
Harford Mutual Insurance v. Moorhead
578 A.2d 492 (Supreme Court of Pennsylvania, 1990)
Weiser v. Bethlehem Steel Corp.
508 A.2d 1241 (Supreme Court of Pennsylvania, 1986)
Wyke v. Ward
474 A.2d 375 (Commonwealth Court of Pennsylvania, 1984)
Hawthorne v. DRAVO CORP. KEYSTONE DIV.
460 A.2d 266 (Superior Court of Pennsylvania, 1983)
St. Clair v. B & L PAVING CO.
411 A.2d 525 (Superior Court of Pennsylvania, 1979)
Printed Terry Finishing Co. v. City of Lebanon
372 A.2d 460 (Superior Court of Pennsylvania, 1977)
Sherman v. Heitz
46 Pa. D. & C.2d 177 (Bucks County Court of Common Pleas, 1968)
In re the Complaint of Consolidation Coal Co.
296 F. Supp. 837 (W.D. Pennsylvania, 1968)
Stebner v. Young Men's Christian Ass'n
238 A.2d 19 (Supreme Court of Pennsylvania, 1968)
Tournier v. Gretz
42 Pa. D. & C.2d 474 (Montgomery County Court of Common Pleas, 1967)
Siegler v. Counties Contracting & Construction Co.
202 A.2d 127 (Superior Court of Pennsylvania, 1964)
McSparran v. Hanigan
225 F. Supp. 628 (E.D. Pennsylvania, 1963)
Hader v. Coplay Cement Mfg. Co.
189 A.2d 271 (Supreme Court of Pennsylvania, 1963)
Prost v. Caldwell Store, Inc.
187 A.2d 273 (Supreme Court of Pennsylvania, 1963)
Stewart v. Morow
170 A.2d 338 (Supreme Court of Pennsylvania, 1961)
Commonwealth v. Fabrizio
21 Pa. D. & C.2d 564 (Luzerne County Court of Quarter Sessions, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
170 A. 139, 314 Pa. 99, 1934 Pa. LEXIS 457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bisson-v-john-b-kelly-inc-pa-1933.