Schank v. Clarkson Construction Co.

368 S.W.2d 720, 1963 Mo. App. LEXIS 519
CourtMissouri Court of Appeals
DecidedJune 3, 1963
DocketNos. 23473-23477
StatusPublished

This text of 368 S.W.2d 720 (Schank v. Clarkson Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schank v. Clarkson Construction Co., 368 S.W.2d 720, 1963 Mo. App. LEXIS 519 (Mo. Ct. App. 1963).

Opinion

MAUGHMER, Commissioner.

Plaintiffs, Dwight and Joanna Schank, were lessees of a 240 acre Missouri River bottom farm located in Holt County, Missouri. The other plaintiffs were the owners of the farm and lessors under a share-crop rental lease. They brought five separate lawsuits against the defendant Clarkson Construction Company, alleging that it negligently performed some water control construction work which caused flooding of the farm with consequent damage to their crops and to the utility of the farm for crop production. These five lawsuits were consolidated for trial by the circuit court and are consolidated on this appeal. The trial resulted in verdicts and judgments for defendant and plaintiffs have appealed.

Pursuant to authority duly vested, the United States Government, through its United States Corps of Engineers, entered into a contract dated November 12, 1957, with defendant under which defendant was to do certain construction, including building of channels, levees and flood control structures in the vicinity of Napier, Missouri, and along a new proposed channel for the Tarkio-Squaw Creek Drainage. This project was located near and over a part of plaintiffs’ land. Its purpose and plan was to improve the drainage in the area and control or lessen the havoc wrought on these bottom lands by flash floods and river overflows.

Actually, only 200 acres are involved in this controversy. This tract is bounded on the east by Squaw Creek, which is the only water outlet from the 8,000 acre Squaw Creek Migratory Waterfowl Refuge, the south part of which lies about one mile north. The drainage in the whole area is generally south. The farm is bounded on the west by Five Mile Road, along the west side of which lies Five Mile Ditch. Plaintiffs had placed two drainage tubes in their northwest corner emptying into Five Mile Ditch and had built levees along the north and south sides of the 200 acres with these levee ditches discharging into Squaw Creek on the east.

One of the charges of negligence is that defendant removed the two drainage tubes on the north side of plaintiff’s property, causing water to pile up, thereby raising the water level on the 200 acres. A second charge is that defendant closed the ditch along the north; third, defendant opened up the levee on the south, and fourth, that defendant plugged up the drainage from Penny Lake on the north to Five Mile Ditch. However, plaintiffs joined and approved this project and signed an agreement releasing 32 acres of the farm lying along Five Mile Road to Clarkson Construction Company for use in building a levee. The two steel tubes removed were located on these 32 acres.

Although the damages sought were allegedly caused by flooding during the year 1958, our acquaintance with this farm under the evidence begins in 1933, when it was owned by a Mrs. Mariey. She died in 1943 and the present owners are her sons and daughters — natural and in-law. It appears that no farming operations were carried out on this land from 1938 to 1955. During this period the buildings were taken away or destroyed and the whole area grew up in willows.

From 1955 on, the plaintiffs Mr. and Mrs. Schank were lessees. They embarked on a program to reclaim the land. Bulldozers pushed out the trees, a levee was dug along the north and south line and drainage tubes were installed. Dr. Carroll, one of the plaintiffs and a son-in-law of Mrs. Maney, said he had advanced $9,000 for this work. Some crops were harvested in 1955 and 1956, but none in 1957 and 1958, except some corn was salvaged after the 1958 floodings of February and May.

[722]*722This Schank farm, according to the.Department of Agriculture and University of Missouri survey map, is located in an area formerly described as “Impassable Lake”. Soil maps describe its soil as “swamp” and “salt marsh”. The Holt County Agricultural Extension agent said the soil was predominantly “Wabash Clay, ponded phase”, which means the soil holds water on top rather than allowing it to sink in. The soil survey map, supra, gives the following description of “Wabash Clay, pond-ed phase”: “This phase, one of the most extensive bottom land soils in the county, occupies iihe lowest position in the flood plain along the Missouri and Nodaway rivers. The largest area is in a marsh formerly known as Impassable Lake”. Beginning in 1955, Mr. Schank leased a part of the farm to duck hunters, who dug a well, installed a pump and flooded a few acres to attract ducks.

Defendant began work under the contract on November 22, 1957. It began south of plaintiffs’ farm and worked north. Five Mile Ditch was widened and deepened. The two tubes of plaintiffs running into Five Mile Ditch were removed but temporary smaller ones under the road were inserted. The contract and over-all plan provided that after construction of the levee a drainage structure was to be built in the northwest corner of the Schank farm consisting of a 36-inch pipe with a concrete controlling gate which could be shut off during high water and opened by gravity flow during low water. The Corps of Engineers’ work schedule called for starting this concrete work in June, 1958. Work on the whole project continued — subject to stoppages due to inclement weather — until March 25, 1958, when the government issued its “Stop Order”1, which directed immediate suspension of all work under the contract. No further work was done until May 9, 1958, when a “Restoration Order” was issued under which the whole project was to be restored to the same condition as it was in prior to November 22, 1957. It was conceded that restoration was completed in due time thereafter. However, the farm flooded again in 1959 after the restoration. There was a heavy snowfall in January or February, 1958, exceeding 10 inches which melted in late February. The spring was unusually wet. The farm flooded in late February or March and again in May, 1958.

On appeal plaintiffs make two assignments of error. First, that the court erred in refusing to admit into evidence before the jury Section 9.06 of the contract between defendant and the United States Corps of Engineers as follows: “Diversion of Water. Full responsibility for the diversion and care of water, during the entire construction time, shall be borne by the contractor”. Second, the court erred in giving Instruction No. 5, because it "was misleading and confusing because it singled out and commented on defendant’s duties under its contract with the Corps of Engineers when said contract was not before the jury; that it was confusing and misleading in that it directed the jury to find the terms of a contract not in evidence before them; that said instruction amounted to a direction on the part of the court that defendant could not be liable if it performed its contract, when the test for the jury was the negligence of the defendant”. We set forth Instruction No. 5:

“The Court instructs the jury that if you find and believe from the evidence that defendant removed a drainage tube from the northwest corner of plaintiffs’ farm and plugged up the drainage from Penny Lake to Five Mile Ditch at that point, if so, and that defendant dug an opening in the levee at the southwest corner of said farm, [723]*723if so, yet if you further find and believe from the evidence that defendant Clarkson Construction Company on November 12, 1957, entered into Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bedford v. United States
192 U.S. 217 (Supreme Court, 1904)
Crisp County v. S. J. Groves & Sons Co.
73 F.2d 327 (Fifth Circuit, 1934)
Johnson v. Thompson
236 S.W.2d 1 (Missouri Court of Appeals, 1950)
Rector v. Tobin Construction Company
351 S.W.2d 816 (Missouri Court of Appeals, 1961)
Evans v. Massman Construction Co.
122 S.W.2d 924 (Supreme Court of Missouri, 1938)
City of St. Louis v. Ruecking
134 S.W. 657 (Supreme Court of Missouri, 1911)
Salliotte v. King Bridge Co.
122 F. 378 (Sixth Circuit, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
368 S.W.2d 720, 1963 Mo. App. LEXIS 519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schank-v-clarkson-construction-co-moctapp-1963.