Crisp County v. S. J. Groves & Sons Co.

73 F.2d 327, 96 A.L.R. 391, 1934 U.S. App. LEXIS 2690
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 31, 1934
Docket7304
StatusPublished
Cited by15 cases

This text of 73 F.2d 327 (Crisp County v. S. J. Groves & Sons Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crisp County v. S. J. Groves & Sons Co., 73 F.2d 327, 96 A.L.R. 391, 1934 U.S. App. LEXIS 2690 (5th Cir. 1934).

Opinion

SIBLEY, Circuit Judge.

There being proper federal jurisdiction, S. J. Groves & Sons Company as transferee of L. E. Meyers Company, filed in the District Court a bill against Crisp county, Ga., and certain individuals who constituted the county’s power commission, to assert the right of L. E. Meyers Company, referred to hereafter as the contractor, to recover judgment for a balance due for the construction of a power dam, and to enforce a title or lien against it by virtue of an instrument executed by the power commission to the contractor at the completion of the work. The dam was alleged to be an inseparable part of an electric power plant, and a sale of the whole plant was sought with apportionment of the proceeds, and an account and apportionment of the profits of operation meanwhile was prayed, together with general relief. The petition sought relief which could not be had at law, and the court did not err in entertaining it in equity and in refusing to transfer it to the law docket.

The defenses now important were that about $30,000 of the amount sued for is for extra work done and materials furnished without the written order of the engineer as required by the contract, and allowed at a time when the money available for building the power plant was so depleted as to render the extra cost a debt which the county could not constitutionally create; that some $3,387.20 had already been paid for such extras and should be paid back; and that $36,000 was due the county as damages because of the contractor’s failure to complete the work within 365 days as contracted. Erom an adverse decree on these defenses the county appeals, assigning error as to them and also error in admitting parol evidence touching a blank in the plans which were a part of the written contract, and in decreeing that net receipts from the operation of the plant should, after providing for the interest and sinking fund of the bonds issued against the plant, be applied to the debt adjudged. The complainant takes a cross-appeal, assigning as error the refusal to decree in its favor a title to or lien on the plant itself.

The Constitution of Georgia, art. 7, § 7, par. 1, limits the total debt of a county to 7 per cent, of the assessed value of the taxable property therein, and prohibits any new debt (except a temporary loan to supply a casual deficiency in revenue not in excess of one-fifth of one per cent, of such assessed value), without assent of the people in an election. This paragraph of the Constitution was amended to permit Crisp county, after an election on the question, to issue additionally $1,250,000 of bonds, and with the proceeds to build and equip an electric power plant and to engage in the business of generating and selling electric power, the bonds to be a first lien on the plant and to be paid by preference out of the net receipts from it, but with power to provide by taxation for their payment if the net receipts proved insufficient. The sale of the bonds and the use of the proceeds in constructing, operating, and maintaining the plant were vested in a power commission, who were “authorized and empowered to employ such agents, servants, and employees, and to make and enter into such contracts as are reasonable and proper in the exercise of the duties and powers herein conferred upon said commission. * * * The General Assembly may confer further and additional authority upon the County of Crisp touching the construction, maintenance, control, and disposition of the Hydro-Electric power plant and properties herein provided for not inconsistent herewith.” Georgia Laws 1925, p. 72, § 1. The election carried. The power commission was appointed, but no laws conferring additional authority have been passed. The commission on August 6, 1928, made the contract here in question for the construction of the dam, being its first contract, when it had at its disposal the entire proceeds of the bonds. The contract price for all work and material was $776,837.19, subject to additions and deductions provided for in the contract and the plans. In the contract it is agreed that, if in carrying out the work the estimated quantities of material should be exceeded, the contractor should be paid nothing extra, but, if the excess should be caused by any change in the plans, a proper credit should be given him. The commission and its engineer are made the final arbiters of most matters under the plans. Payments were made as the work progressed, and a disagreement between the contractor and the engineer arose as to certain claims for additional materials used and *329 extra work done. But, after the conclusion of the. work, the engineer compromised the dispute, as the court on sufficient evidence found, by allowing about half of the disputed amounts, and issued his final estimate for $153,983.50. This was accepted by the contractor as a, settlement, and was formally approved for payment by the commission. They had, however, spent for machinery, land, and in other ways a large amount of the bond proceeds, and also lost a large sum through a bank failure, so that they could pay only part in cash, and executed on August 1st, 1930, an instrument whieh recited that the county acknowledged that the contractor owned, and was in possession of, an undivided interest in the dam, whieh the county desired to lease with an option to purchase, and it then purported to lease that interest for three years for quarterly rentals which would equal the balance due, the contractor placing in escrow a deed to all its interests to he delivered on completion of the payments. The payments were not met, and this suit followed.

The dam was built on land of the county, and the building- contract reserved no light of possession or other interest in the contractor. No statute gives a contractor any legal lien on public properties. City of Albany v. Lynch, 119 Ga. 491, 46 S. E. 622; Neal-Millard Co. v. Trustees of Chatham Academy, 121 Ga. 208, 48 S. E. 978. The constitutional amendment does not authorize the power commission to sell or incumber the plant. It says that the Legislature may give Crisp comity further authority touching among other things the disposition of the plant, but none has yet been given. The commission could not validly acknowledge title out of the county, nor estop it by a purported lease. The contractor in agreeing to improve the county’s land credited the proceeds of the bond issue and the good faith of the county, and acquired neither title to, nor lien on, the realty improved. The attempted lease is without legal effect, and there was no error in so decreeing.

On the other hand, the construction contract of August 6, 1928, was within the powers of the commission, and at the time of its making iliey had available the entire proceeds of the bond issue, so that it created no debt against the county in the sense of the Constitution. Butts County v. Jackson Banking Co., 129 Ga. 801, 60 S. E. 149, 15 L. R. A. (N. S.) 567, 121 Am. St. Rep. 244. Although by no fault of the contractor a, part of the bond money was thereafter used otherwise, and a part lost before the construction was completed, so that there theri remained not enough to discharge the payment duo, the contract remained a lawful and valid obligation of the county. McCord v. City of Jackson, 135 Ga. 177 (5), 69 S. E. 23; Wilson v. Gaston, 141 Ga. 770, 82 S. E. 136. Included in this obligation were the amounts for extras whieh were allowed in the final estimate, although at the time of their allowance money was not available to pay them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman v. Herrman
748 So. 2d 310 (District Court of Appeal of Florida, 1999)
Reed ex rel. Reed v. United States
891 F.2d 878 (Eleventh Circuit, 1990)
Reed v. United States
891 F.2d 878 (Eleventh Circuit, 1990)
Schank v. Clarkson Construction Co.
368 S.W.2d 720 (Missouri Court of Appeals, 1963)
McGee v. Marbury
83 A.2d 157 (District of Columbia Court of Appeals, 1951)
San Miguel, González & Valiente & Co. v. Municipality of Caguas
72 P.R. 366 (Supreme Court of Puerto Rico, 1951)
San Miguel v. Municipio de Caguas
72 P.R. Dec. 391 (Supreme Court of Puerto Rico, 1951)
Hall v. Keller
180 F.2d 753 (Fifth Circuit, 1950)
J. Kahn & Co., Inc. v. Clark, Attorney General
178 F.2d 111 (Fifth Circuit, 1949)
Harris v. Travelers Ins.
80 F.2d 127 (Fifth Circuit, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
73 F.2d 327, 96 A.L.R. 391, 1934 U.S. App. LEXIS 2690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crisp-county-v-s-j-groves-sons-co-ca5-1934.