San Miguel, González & Valiente & Co. v. Municipality of Caguas

72 P.R. 366
CourtSupreme Court of Puerto Rico
DecidedApril 9, 1951
DocketNo. 9722
StatusPublished

This text of 72 P.R. 366 (San Miguel, González & Valiente & Co. v. Municipality of Caguas) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Miguel, González & Valiente & Co. v. Municipality of Caguas, 72 P.R. 366 (prsupreme 1951).

Opinion

ON RECONSIDERATION

Mr. Justice Negrón Fernández

delivered the opinion of the Court.

An extensive motion for reconsideration of our judgment of May 10, 1949, San Miguel, Etc. & Cía. v. Municipality, 69 P.R.R. 895, was filed by plaintiff-appellant which was likewise opposed in the same elaborate manner. Additional mo[369]*369tions were filed by the parties. The questions raised in said motion call for a re-examination of the record, as to the facts as well as to the applicable law.

By our judgment of May 10, 1949, we affirmed the decision rendered by the District Court of Caguas dismissing the complaint in an action for the recovery of money and other relief filed by San Miguel, González, and Valiente and Company. Said commercial firm purchased from the Banco .Territorial y Agrícola in liquidation, a credit for the amount of $2,500 which had been assigned to the bank by the engineer Robert R. Prann, and which the latter had against the Municipality of Caguas for the amount of $12,384.63.1 This sum. represented the difference between $33,368.70 actually' paid to Prann chargeable .to the sum of $33,976.64 — total amount of a contract adjudicated him at a public bid in' the-Municipality of Caguas for the construction of a filtration plant of the waterworks — and the final liquidation of the work, made by the Commissioner of the Interior, amounting-to $45,753.33, which was the total cost of same under the contract between the municipality and Prann.2 The money [370]*370to be used in the construction of said filtration plant was part of a loan made by the Municipality of Caguas for $146,000, of which $80,000 were allotted to improvements [371]*371to the municipal waterworks. The contract between Prann and the municipality in the amount of $33,976.64 was executed on February 3,1931, and approved by the Commissioner of the Interior of Puerto Rico on April 13, of the same year. [372]*372The “General Conditions of the Contract for. Insular Public Works/’ in force since July 1902 3 are a part of said contract.

Appellant’s first ground of his motion for reconsideration attacks our conclusion that the claim of contractor Prann against the Municipality of Caguas for extra work done under the terms of the contract herein referred to, should be considered as forfeited for nonperformance and as waived, since nothing in the record showed that said contractor had presented his claim to the municipality in the “next monthly estimate for extra work.” We believe that appellant is partly correct. Let us see.

As it appears from the voluminous record before us, once the work was begun by contractor Prann, and pursuant to the terms of the contractor to that effect, the Superintendent of Public Works of the Department of the Interior issued a monthly certificate, the approval of which he recommended [373]*373to the Engineer of Public Works of said department and which was finally approved by the Commissioner. Said certificate contained a monthly statement of the work performed and the material stored therefor by the engineer Prann during said month. It also contained the cost per unit and price, with the total of each item of the work done, and the material stored stating also the amounts which the municipality had to retain, under the terms of the contract, equivalent to 10 per cent of each payment, until the full completion of the work and its final acceptance. By virtue of these certificates the municipality issued payments in favor of the engineer Prann, which were certified by the Director of Public Works of the Municipality, approved by the Mayor and authorized by the Municipal Auditor, chargeable to the loan of $146,000 herein referred to in its item “Improvements in the Waterworks.” After said certificate were approved by the Commissioner of the Interior they were sent to the Mayor of Ca-guas to follow the aforesaid procedure.

Six certificates were issued up to January 30, 1932, amounting to $33,377.16 of which $30,090.14 were paid to Prann, and $3,287.01 were retained by the municipality according to the terms of the contract. In none of said six certificates engineer Prann claimed that he had done any “extra' work.” The following certificate, No. 7, comprised the work done by engineer Prann up to February 27, 1932, totalling $3,699.18, of which $420.62 were to be retained according to the terms of the contract, and $3,278.56 were to be paid to the contractor. This certificate contains for the first time, under the title “Work in Excess of the 20 per cent,” an item amounting to the sum of $1,350. This certificate after going through the usual proceedings regarding its approval was sent to the Mayor of Caguas for its payment on March 10, 1932. Thus far the only amount for extra work included in the first seven certificates in favor of engineer Prann, was that of $1,350 already mentioned, which sum, being included in [374]*374“the next monthly estimate for extra work,” was claimed in time and we cannot agree that it was waived or' forfeited.

No other work done by engineer Prann up to February 27, 1932, was considered by the latter, nor by the Superintendent of Public Works of the Department of the Interior, or the engineer of Municipal Works of said department, or by the Commissioner himself as “extra work,” under the terms of the contract. Until said date the total value of work done by engineer Prann plus the extra work amounted to $37,076.33.

The last certificate issued in favor of said contractor for work done, No. 8, is the final liquidation of the construction of the filtration plant, and covers the period up to June 3, 1933'. Said certificate amounts to $8,677 and includes, espe-cifically, an item of $2,843.57 for excavations in ditches in “excess of the 20 per cent,” extra work in the new dam for $546, lighting of the plant building for $370.50, and work “by administration” totalling $1,049.65, all of which amounts to $4,809.72 for extra work. No other work done by engineer Prann from February 27, 1932 until the final completion of the filtration plant, was included in certificate No. 8 as extra work or in excess of the 20 per cent. Therefore, from the total of $8,677 recommended for payment in said certificate No. 8, until the completion of the project, only the sum of $4,809.72 should be considered as forfeited and waived by Prann, for failure to file his claim to the municipality in the next monthly estimate for extra work, after it was completed, according to Clause 30 of the General Conditions. The difference between the amount of $12,384.63 claimed in the complaint and the $4,809.72 not timely claimed by Prann — and therefore waived by him — that is the sum of $7,574.91 was timely and properly claimed since from the last sum of .$7,574.91, only $1,350 was included as extra work on certificate No. 7, and as we have seen it was claimed in time. The sum of $6,224.91 corresponds to work done in alterations or changes in the original project, which was not [375]*375considered by any of the parties in the contract as extra work, as defined in Clause 30 of the General Conditions, and which is a part thereof. Clause 30 defines extra work as follows: “Any alteration or changes in the project producing work not provided for in the contract shall be considered as extra work.” It also provides that “The claims for extra work, when it is ordered, shall be presented and paid in the next monthly estimate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crisp County v. S. J. Groves & Sons Co.
73 F.2d 327 (Fifth Circuit, 1934)
Town of Covington v. Antrim Lbr. Co.
1926 OK 944 (Supreme Court of Oklahoma, 1926)
School Dist. No. 8, Marshall Co. v. Home Lumber Co.
1923 OK 1002 (Supreme Court of Oklahoma, 1923)
City of Healdton v. Blackburn
1934 OK 573 (Supreme Court of Oklahoma, 1934)
Wilson v. Gaston
82 S.E. 136 (Supreme Court of Georgia, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
72 P.R. 366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-miguel-gonzalez-valiente-co-v-municipality-of-caguas-prsupreme-1951.