Ryland Group v. Daley

537 S.E.2d 732, 245 Ga. App. 496
CourtCourt of Appeals of Georgia
DecidedJuly 21, 2000
DocketA00A1656, A00A1657
StatusPublished
Cited by23 cases

This text of 537 S.E.2d 732 (Ryland Group v. Daley) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryland Group v. Daley, 537 S.E.2d 732, 245 Ga. App. 496 (Ga. Ct. App. 2000).

Opinion

Eldridge, Judge.

This is an appeal and cross-appeal on a claim and counterclaim wherein a Fulton County jury found for plaintiff homeowners Donna Jones Daley and Raymond Daley (“Daleys”) against defendant seller/ builder Ryland Group, Inc. (“Ryland”) on their complaint for breach of a building contract, negligent construction, and breach of warranty; the jury found for Ryland on its counterclaim alleging breach of an agreement entered into at closing regarding the installation of granite countertops in the kitchen of the Daleys’ house. For the reasons that follow, we affirm the trial court’s partial judgment notwithstanding the verdict (“j.n.o.v”) and denial of a motion for new trial.

Viewed in a light to uphold the jury’s verdict, 1 Ryland built the Daleys’ “Master’s Collection” house pursuant to a contractual agreement entered into in June 1994. The contract was amended in order to include the purchase and installation of Baltic Brown granite countertops in the kitchen of the house. The countertops were installed at the completion of construction so that they would not be damaged by the subcontractors working on other parts of the house. The Daleys saw the countertops for the first time the day before closing. Ryland had installed three-centimeter-thick Dakota Mahogany countertops with granite overhangs on the edges of the counters. The *497 color was unsatisfactory to the Daleys and not as specified. Ryland agreed that the countertop installation was incorrect because of the color; however, rather than delay closing, Ryland and the Daleys agreed to hold in escrow $8,000 out of the purchase price, pending installation of Baltic Brown granite countertops.

The parties closed on the house in September 1994. The agreement regarding reinstallation of the proper color countertops was reflected in a document generated at closing, and $8,000 was placed in escrow pending release by satisfactory installation. Ryland reinstalled the countertops in November 1994. The color of the granite was correct, but the granite was two centimeters thick, and there were no granite overhangs on the edges of the counters. The Daleys were dissatisfied with the second installation. In January 1995, Ryland refused to reinstall the countertops a third time and informed the Daleys that any changes between the first and second granite installation were consistent with the blueprint specifications and, thus, not in violation of contract. The Daleys would not agree to the release of the escrowed funds until the kitchen countertops were reinstalled using three-centimeter-thick Baltic Brown granite with granite overhangs on the edges consistent with the first installation.

Meanwhile, during the early months of 1995, the Daleys compiled a punch list of repairs, replacements, and defects in the construction of the house, the correction of which was Ryland’s responsibility pursuant to contract. This included serious defects in the installation of the hardwood floors on the first floor. Ryland took no significant action on any repairs to the Daleys’ house.

In July 1995, the Daleys asked a friend who is an attorney to aid them in obtaining repairs to the house pursuant to contract. Negotiations occurred between Ryland and the Daleys’ first attorney throughout 1995 and into 1996. During this time, Ryland made small repairs to the residence, but finally in late 1996, Ryland informed the Daleys that “there would be no movement with regard to the other defects and repairs that [the Daleys] noted until [they] resolved the counter top issue.”

In February 1997, the Daleys hired a litigation attorney. In early spring 1997, a structural engineer was engaged and, over two separate visits, did a complete inspection and found numerous structural defects, as well as other defects both related and unrelated to the structural problems with the house. An “Engineer’s Estimate” was generated, which included the estimated cost to repair the construction defects. The total cost to repair was $40,765. The Daleys filed suit October 1, 1997, alleging breach of contract, negligence, breach of warranty, and requesting attorney fees. Ryland counterclaimed for the $8,000 in escrow, alleging breach of the agreement reached at closing regarding the kitchen countertops.

*498 The jury found for the Daleys on all grounds of their complaint and awarded the Daleys $70,800 in damages and $22,500 in attorney fees. The jury found for Ryland on its counterclaim and awarded Ryland $8,000. Pursuant to election, the trial court entered judgment on the jury’s verdict as to the breach of contract claim and the award of $70,800 in damages and $22,500 in attorney fees. The trial court also entered judgment on the jury’s verdict as to Ryland’s counterclaim and the award of $8,000. Later, on Ryland’s motion for j.n.o.v., the trial court affirmed the jury’s award of attorney fees to the Daleys but reduced the damage award to $41,000 based on the actual cost to repair estimate as testified to by the Daleys’ structural engineer during trial.

In Case No. A00A1656, Ryland appeals the trial court’s judgment entered on the jury’s verdict for the Daleys on their breach of contract claim and the award of attorney fees. In Case No. A00A1657, the Daleys appeal from the trial court’s order on motion for j.n.o.v. reducing the damage award.

Case No. A00A1656

1. (a) Ryland contends that the Daleys failed to offer proof of the proper measure of damages. Ryland argues that “difference in value” is the only proper measure of damages for defective workmanship in a breach of contract action, while the Daleys relied upon cost to repair/correct defects in order to measure damages for breach of contract, negligent construction, and breach of warranty. However, in its brief, Ryland also concedes that “difference in value may be shown by evidence of the reasonable cost of correcting defects.” Of course, where the action is for breach of contract only, the difference between the value of the house as finished and the value of the house as it should have been finished, i.e., the benefit of the bargain, is a proper measure of damages, but it is by no means the exclusive measure. 2 Indeed, “[generally, the proper measure of damages for defective workmanship would be the cost of repair of the defect” when claiming negligent construction, as well as when claiming breach of contract. 3 Accordingly, there was no error in the method of measuring damages *499 in this case.

(b) We also find no merit to Ryland’s contention that the cost to repair the defects in the Daleys’ residence should have been measured at the time of the delivery of the new residence in September 1994, i.e., at closing. The record shows that the cost to the Daleys to repair defects in the home — defects for which Ryland was responsible under the contract — did not become a relevant issue until Ryland flatly refused to repair them. Ryland’s refusal occurred long after the 1994 closing on the house; any increase in the cost to repair the defects because of such delay is attributable to Ryland, arises naturally from Ryland’s breach of contract, and was in the contemplation of the parties to the contract. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Thurmond & Associates, Inc. v. Kennedy
668 S.E.2d 666 (Supreme Court of Georgia, 2008)
McFarland & McFarland, P.C. v. Holtzclaw
667 S.E.2d 874 (Court of Appeals of Georgia, 2008)
Energy & Process Corp. v. Jim Dally & Associates, Inc.
662 S.E.2d 835 (Court of Appeals of Georgia, 2008)
Kennedy v. John Thurmond & Associates, Inc.
649 S.E.2d 762 (Court of Appeals of Georgia, 2007)
Steel Magnolias Realty, LLC v. Bleakley
622 S.E.2d 481 (Court of Appeals of Georgia, 2005)
Rafferzeder v. Zellner
613 S.E.2d 229 (Court of Appeals of Georgia, 2005)
Wise v. Tidal Construction Co.
608 S.E.2d 11 (Court of Appeals of Georgia, 2004)
Godinger Silver Art Co. v. Olde Atlanta Marketing, Inc.
604 S.E.2d 212 (Court of Appeals of Georgia, 2004)
Morrison Homes of Florida, Inc. v. Wade
598 S.E.2d 358 (Court of Appeals of Georgia, 2004)
Freightliner Chattanooga, LLC v. Whitmire
584 S.E.2d 724 (Court of Appeals of Georgia, 2003)
City of Atlanta v. Conner
585 S.E.2d 634 (Court of Appeals of Georgia, 2003)
GEORGIA NORTHEASTERN RAILROAD CO. v. Lusk
574 S.E.2d 810 (Court of Appeals of Georgia, 2002)
Schaner v. Sterling Factors, Inc.
572 S.E.2d 14 (Court of Appeals of Georgia, 2002)
Song v. Brown
565 S.E.2d 884 (Court of Appeals of Georgia, 2002)
Kent v. AO WHITE
559 S.E.2d 731 (Court of Appeals of Georgia, 2002)
Nulite Industries Co., LLC v. Horne
556 S.E.2d 255 (Court of Appeals of Georgia, 2001)
UNIFIED GOVERNMENT v. North
551 S.E.2d 798 (Court of Appeals of Georgia, 2001)
Kent v. WHITE, CONSULTING ENGINEERS, PC
553 S.E.2d 1 (Court of Appeals of Georgia, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
537 S.E.2d 732, 245 Ga. App. 496, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryland-group-v-daley-gactapp-2000.