Energy & Process Corp. v. Jim Dally & Associates, Inc.

662 S.E.2d 835, 291 Ga. App. 772, 2008 Fulton County D. Rep. 1903, 2008 Ga. App. LEXIS 640
CourtCourt of Appeals of Georgia
DecidedJune 4, 2008
DocketA08A0201
StatusPublished
Cited by7 cases

This text of 662 S.E.2d 835 (Energy & Process Corp. v. Jim Dally & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Energy & Process Corp. v. Jim Dally & Associates, Inc., 662 S.E.2d 835, 291 Ga. App. 772, 2008 Fulton County D. Rep. 1903, 2008 Ga. App. LEXIS 640 (Ga. Ct. App. 2008).

Opinion

Phipps, Judge.

Energy & Process Corporation (“Energy”) brought this suit against Jim Dally and Associates, Inc., d/b/a Standard Resistance Welder Company (“Standard”), seeking $7,222.50 in damages for breach of contract and an award of attorney fees under OCGA § 13-6-11. At trial, Standard moved for a directed verdict on the contract claim based on the voluntary payment doctrine and on the attorney fee claim based on an absence of evidence to authorize an award of fees. The trial court granted the motion and entered final judgment in Standard’s favor on both claims. Energy appeals. For reasons that follow, we reverse.

Evidence introduced at trial showed that Energy, a seller of electrical components to the utility industry, asked Standard to supply it with welding electrodes that Energy was going to sell the Westinghouse Savannah River Company for use by the Department of Energy (“DOE”) in a nuclear power project.

On August 15, 2003, Energy sent Standard an order to purchase 18 of the welding electrodes. Under the terms of the purchase order, Standard was to manufacture the electrodes in accordance with certain DOE specifications. At the outset, Standard was to supply “starting materials” (metal discs) to Energy for testing and inspection. Energy was then required to return the discs to Standard to begin the manufacturing process. The terms of payment were “NET 30 days,” meaning that payment by Energy was not due until 30 days after Standard had shipped the finished products.

Standard obtained the metal discs and sent them to Energy for testing on December 15, 2003. Energy indicated to Standard that *773 testing would be completed in two to four weeks. The materials had not been returned, however, as of March 3, 2004, when Standard submitted to Energy an invoice for payment of “half price of the . . . purchase order[,]” along with a letter reminding Energy that the parts had not been returned. In turn, Energy sent Standard a check dated June 25, 2004, in payment of the amount requested. Energy’s president testified that he authorized this interim payment even though it was not required under the purchase order, because “[w]e were under the hammer of our customer ... to fulfill this order” and had concluded, based on statements made by Standard representatives, that “there was going to be no forward movement without it.” As further described by Energy’s president, “[w]e were operating under some threat of performance.”

Nonetheless, in August 2004 Standard advised Energy that it was canceling the order because Energy still had not returned the metal discs. When Energy, however, asked Standard to reconsider because the DOE would not allow its contract with Energy to be cancelled, Standard agreed. Energy returned the discs to Standard in early 2005. In June 2005, Standard sent two completed parts to Energy. It is undisputed that these parts failed to comply with the specifications, that they were returned to Standard, and that Standard agreed to correct the defects.

Later in June, Standard shipped seven completed parts to Energy COD. Energy refused to accept delivery because, contrary to the terms of the purchase order, accepting delivery would have required that it pay for the goods before inspection, and the two parts that had been shipped earlier were noncompliant. Energy’s president testified that after rejecting the shipment, Energy attempted without success to make alternative arrangements with Standard to inspect the parts before paying for them, as it had a contractual right to do. Because the inspection never took place, Standard inventoried the parts, and Energy never obtained them. Westinghouse subsequently agreed to terminate its contract with Energy without penalty based on Energy’s inability to provide parts. In September 2005, Energy through counsel sent Standard a letter demanding refund of the partial payment. Because no refund was made, Energy filed this suit.

1. Energy contends that the trial court erred in granting Standard’s motion for directed verdict on its contract claim under the voluntary payment doctrine. Finding Broome v. Cavanaugh 1 controlling, and cases such as Liberty Nat. Life Ins. Co. v. Radio *774 therapy of Ga., 2 Lowe v. Presley, 3 Commerce Finance Co. v. Perry, 4 New York Life Ins. Co. v. Williamson, 5 and Arnold & DuBose v. Ga. R. and Banking Co. 6 distinguishable, we agree.

The voluntary payment doctrine is codified in OCGA § 13-1-13, which provides:

Payments of claims made through ignorance of the law or where all the facts are known and there is no misplaced confidence and no artifice, deception, or fraudulent practice used by the other party are deemed voluntary and cannot be recovered unless made under an urgent and immediate necessity therefor or to release person or property from detention or to prevent an immediate seizure of person or property. Filing a protest at the time of payment does not change the rule prescribed in this Code section.

Thus, in Arnold & DuBose, 7 a shipper of cotton sought to recover freight charges that it had paid the carrier. The shipper claimed that the charges were unlawfully excessive. The Court found the excess payments nonrecoverable, holding

that where money is paid with a full knowledge of all the facts and circumstances upon which it is demanded, or with the means of such knowledge, it cannot be recovered back upon the ground that the party supposed he was bound in law to pay it, when in truth he was not. He shall not be permitted to allege his ignorance of the law; and it shall be considered a voluntary payment. 8

Nevertheless, under the express terms of OCGA § 13-1-13, the voluntary payment doctrine “has no application where the payment is induced by misplaced confidence, artifice, deception, or fraudulent practice on the part of the person to whom the money is paid. ’ ’ 9 Thus, the court in Lowe 10 found the voluntary payment doctrine no bar to the plaintiffs recovery of money he had paid to a person who had misrepresented himself as an attorney authorized to practice law *775 and who had rendered legal services of no material benefit to the plaintiff. In contrast, in Liberty Nat., 11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Navicent Health, Inc. v. Fady S. Wanna
Court of Appeals of Georgia, 2020
National Freight, Inc. v. Consolidated Container Co.
166 F. Supp. 3d 1320 (N.D. Georgia, 2015)
Gant v. AZALEA CITY CREDIT UNION
69 So. 3d 880 (Court of Civil Appeals of Alabama, 2011)
Southern Mutual Church Insurance Co. v. ARS Mechanical, LLC
703 S.E.2d 363 (Court of Appeals of Georgia, 2010)
Pew v. One Buckhead Loop Condominium Ass'n
700 S.E.2d 831 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
662 S.E.2d 835, 291 Ga. App. 772, 2008 Fulton County D. Rep. 1903, 2008 Ga. App. LEXIS 640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/energy-process-corp-v-jim-dally-associates-inc-gactapp-2008.