Adamson Co. v. Owens-Illinois Development Corp.

309 S.E.2d 913, 168 Ga. App. 654, 1983 Ga. App. LEXIS 2882
CourtCourt of Appeals of Georgia
DecidedOctober 28, 1983
Docket66908
StatusPublished
Cited by15 cases

This text of 309 S.E.2d 913 (Adamson Co. v. Owens-Illinois Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adamson Co. v. Owens-Illinois Development Corp., 309 S.E.2d 913, 168 Ga. App. 654, 1983 Ga. App. LEXIS 2882 (Ga. Ct. App. 1983).

Opinion

McMurray, Presiding Judge.

This appeal involves the intervenor in a suit for damages based on breach of contract in which judgment was awarded to the original plaintiff against the defendant.

On or about January 25, 1982, Athena Pipeline, Inc., a Georgia corporation, entered into a contract with Owens-Illinois Development Corporation and agreed to furnish all labor, materials, equipment and supplies to construct a complete water treatment and distribution system in Owens-Illinois Development Corporation’s Scenic Shores subdivision (Tract 29), in Hancock County, Georgia. As a part of that contract there was a provision for a 10 % hold back of all amounts due contractor until final acceptance of the system by the proper state authority. In addition, if any phase of the contract is not completed by completion date and for which no extension of time had been granted the contractor shall pay the owner a daily penalty of $50 per working day for all days required beyond the appropriate completion time for final completion and no such payment shall constitute a waiver or release of any liability of the contractor under the contract. The contractor was to complete phase 1 by June 1,1982, and phase 2 by July 1,1982. By letters dated July 7,1982, and August 17, 1982, the owner notified the contractor of certain defaults in its contractual obligations and that it was enforcing the delay penalty provisions of the contract and that the contract would be terminated on September 3, 1982.

Plaintiff Owens-Illinois Development Corporation brought suit against Athena Pipeline, Inc. (contractor) contending that the contractor failed to complete either phase 1 or phase 2 on the specified dates and thereafter abandoned the project, leaving the system incomplete and inoperable, and that the plaintiff, as owner, exercised its rights under the contract and terminated the contract. Plaintiff further contended that in addition to the unauthorized delay in completing the system, the contractor failed to pay for materials and labor supplied to the project and subjected the owner’s *655 real estate to materialmen’s and laborer’s liens. Damages were sought against the defendant contractor for additional costs and expenses, the delay penalty, for lost sales, for cost and expenses involving the removal of liens and attorney fees and expenses of litigation.

The defendant Athena Pipeline, Inc. answered the complaint denying the claim, admitting only jurisdiction and the substance of the above facts with reference to the contract.

Adamson Company, Inc. then moved to intervene, having supplied certain storage tanks to the project site all in part performance of defendant’s contractual obligations to the owner (plaintiff Owens-Illinois Development Corporation) contending the tanks conform to the contractual requirements of the owner by the contractor (the defendant). Defendant failed to pay intervenor for the tanks and was liable to it for a breach of contract (Count 1), for unjust enrichment (Count 2) and for unjust enrichment on the part of the owner (Count 3), all in the same amount, seeking judgment in Counts 1 and 2 against the defendant in a stated sum; and judgment as to Count 3 against the plaintiff in the same amount. The court allowed the intervention. Thereafter Count 3 of the intervention was amended to set out that the defendant was out of business and insolvent, plaintiff had withheld 10% of all amounts due the defendant until final acceptance of the system and intervenor claims a beneficial interest in these sums withheld and that a resulting trust should be implied with regard to these monies. Intervenor prayed that it have judgment against the defendant for these sums and an implied resulting trust be impressed upon the monies held by the plaintiff to be awarded to it.

The plaintiff filed an answer to the cross-complaint, as amended, in substance denying the claims of the intervenor, admitting only the existence of the contract between the owner and the contractor, including its right to withhold 10 % of all amounts due the defendant until final acceptance of the system by the proper state authority and that the intervenor claims a beneficial interest in these monies, but denies that intervenor was entitled to any portion of same.

After discovery motions for summary judgment were filed by the plaintiff and the intervenor. After a hearing the court granted a partial summary judgment to the plaintiff against the defendant for breach of contract for $6,750 as liquidated damages for 135 days at $50 per day, but reserved for determination at a bench trial all other issues of damages. As to the intervenor, the court granted its motion for summary judgment against the defendant in the sum of $33,378.74.

The intervention was severed, or rather, only the main action *656 was considered as to the remaining issues of plaintiffs claim. The case proceeded to trial before the court without the intervention of a jury at which time the issues were narrowed to the value of cost to the plaintiff of obtaining a replacement warranty which was one of the things contained in the contract with reference to a one year warranty of the water system that was to be installed. Plaintiff contends it lost the benefit of the one year warranty by reason of the default in the contract. The plaintiff had brought in another contractor to complete the system, and the same has been totally completed. The plaintiff set forth that the only claim remaining was the value of the Warranty which had not been complied with inasmuch as it had obtained another contractor to get the job completed, and the contract with the new contractor was approximately the same it would have been had the defendant completed the job. However, this contract work did not cover the warranty. Counsel for plaintiff also points out that liens had been filed against plaintiff and that other liens still might be filed, and the plaintiff still had some contingent liability with reference to these liens, contending therein that regardless of the outcome of the claim of the intervenor plaintiff would be entitled to hold the retainage money until it was determined whether or not it would be liable on prospective future liens. During a colloquy with the court counsel for plaintiff disclosed that the 10 % retainage on the contract amounted to some $16,000.

The trial continued on the sole issue as to the cost of the warranty as an element of damages arising out of the breach of the contract. After hearing evidence the trial court rendered judgment in favor of the plaintiff in the amount of $14,550 for compensatory damages for breach of the one year warranty, awarding the plaintiff judgment for that amount and nothing as attorney fees.

The intervenor appeals enumerating error to the award of damages in that the plaintiff failed to prove all of the elements necessary for the trier of fact to calculate damages and the amount awarded was not supported by the evidence and contrary to the evidence. Held:

In the case sub judice, the intervenor’s action against the defendant (breach of contract and unjust enrichment) and against the plaintiff (unjust enrichment and implied resulting trust) was not considered by the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SPIRITS, INC. v. PATEL Et Al.
828 S.E.2d 381 (Court of Appeals of Georgia, 2019)
PHILLIPS Et Al. v. OWNERS INSURANCE COMPANY
802 S.E.2d 420 (Court of Appeals of Georgia, 2017)
Hodges v. Vara
603 S.E.2d 327 (Court of Appeals of Georgia, 2004)
Roberson v. Ocwen Federal Bank FSB
553 S.E.2d 162 (Court of Appeals of Georgia, 2001)
Ryland Group v. Daley
537 S.E.2d 732 (Court of Appeals of Georgia, 2000)
Little Tree, Inc. v. Fields
522 S.E.2d 509 (Court of Appeals of Georgia, 1999)
Paul Davis Systems of Savannah, Inc. v. Peth
412 S.E.2d 279 (Court of Appeals of Georgia, 1991)
Hertz Corp. v. McCray
402 S.E.2d 298 (Court of Appeals of Georgia, 1991)
Clements v. Barnes
397 S.E.2d 560 (Court of Appeals of Georgia, 1990)
Webb v. Hancock Plumbing & Heating Co.
391 S.E.2d 697 (Court of Appeals of Georgia, 1990)
Armech Service Co. v. Rose Electric Co.
386 S.E.2d 709 (Court of Appeals of Georgia, 1989)
Simmons v. Boros
335 S.E.2d 662 (Court of Appeals of Georgia, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
309 S.E.2d 913, 168 Ga. App. 654, 1983 Ga. App. LEXIS 2882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adamson-co-v-owens-illinois-development-corp-gactapp-1983.