Wise v. Tidal Construction Co.

608 S.E.2d 11, 270 Ga. App. 725, 2004 Fulton County D. Rep. 3684, 2004 Ga. App. LEXIS 1435
CourtCourt of Appeals of Georgia
DecidedNovember 8, 2004
DocketA04A1943
StatusPublished
Cited by4 cases

This text of 608 S.E.2d 11 (Wise v. Tidal Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wise v. Tidal Construction Co., 608 S.E.2d 11, 270 Ga. App. 725, 2004 Fulton County D. Rep. 3684, 2004 Ga. App. LEXIS 1435 (Ga. Ct. App. 2004).

Opinion

Andrews, Presiding Judge.

Mary Rose Wise and Nell Lackman, her mother, appeal from the trial court’s direction of a verdict in favor of Tidal Construction Company, Inc. (Tidal) in their suit arising from claimed defective construction of a home owned by them. 1

“A directed verdict is authorized only when there is no conflict in the evidence as to any material issue and the evidence introduced, with all reasonable deductions therefrom, shall demand a particular verdict.” (Citation and punctuation omitted.) Carden v. Burckhalter, *726 214 Ga. App. 487, 488 (1) (b) (448 SE2d 251) (1994). On appeal, we conduct a de novo review and will uphold the grant of a directed verdict only if all the evidence demands it. Id.

Tidal purchased the lot in Richmond Hill upon which the home was built from developer Charles Stafford on July 21, 1995. A building permit was obtained by Tidal on November 19,1995. The lot was cleared and the site was prepared by Tidal’s subcontractor. The concrete slab foundation, including footers, was poured in January 1996. On March 31, 1997, Mary Rose 2 (not yet married to Michael Wise) and her mother bought the home from Tidal for $138,900.

On June 15, 1998, Wise saw a four to five-inch sink hole in the rear portion of her backyard between her patio and privacy fence. She walked over to it and the hole caved around her up to her knees. Wise immediately contacted Tidal, which disclaimed any knowledge of why the yard would be caving in. She then contacted Stafford, and he sent a truck load of sand, which was poured into the sinkhole to fill it. Nonetheless, the hole caved in again six months later and was filled again.

On October 6,2002, Michael Wise, then Wise’s fiancé, dug up four portions of her backyard with a backhoe, including the sinkhole area. In these four areas, Michael Wise found organic debris, consisting of pine limbs and pine straw, which he removed from the holes. Michael Wise dug up some fairly large stumps from the sinkhole area, but nothing of that magnitude from the other three holes. In the hole dug closest to the house, near the master bedroom and chimney, a pine tree limb was found and appeared to extend partially under the home. Michael Wise also dug by hand around the foundation and removed all organic material he found near it. There is a lip of concrete from the foundation which extends beyond the brick veneer on the exterior of the house. When Michael Wise stated that he found limbs and pine straw “under the footings,” he acknowledged that he was referring to material under the concrete lip. Michael Wise also acknowledged that, up to the time of trial in November 2003, there had been no further sinking in any portion of the yard or cracking or failure of the slab.

S M & E, a drilling company, performed hand augurings and used very large core drills to drill into the ground. No landfill was located anywhere around the perimeter of the house.

Wise contacted Whitaker Labs, an engineering firm in Savannah. Carroll Crowther, a civil engineer with a specialty in soil mechanics and the use of soils to support structures, was accepted by *727 the court as an expert in the field of engineering. He inspected the house in 2001, and did test soil borings around the house.

Crowther acknowledged that he did not work with or report to a structural engineer, did not hold himself out as a contractor, and could not establish the standard of care required of a contractor. Further, he had no personal knowledge of how Wise’s house was constructed and did not know which codes were applicable to one- and two-family dwellings in Richmond Hill, but said that decision would be up to the code administrator. The parties stipulated that the Council of American Building Officials (CABO) code was applicable to dwellings in Richmond Hill. Crowther stated that “the building inspector, whoever he was, believed that the [CABO] code was being complied with.”

Crowther also admitted that he did not know if the site where Wise’s slab was poured had been scraped with a tractor or bulldozer with a blade before the pour, but acknowledged that this was common practice. He further acknowledged that the Richmond Hill building inspector would inspect the site after this had been done and the footings dug, before the slab was poured. Also, he stated that “[v]irgin soils in this area of Richmond Hill are inherently stable.”

Based on his review of the videotapes of Michael Wise’s excavation in the yard and his own borings, Crowther opined that the rear area of the yard had not been adequately prepped and that organic debris was under a third of the concrete slab. Crowther acknowledged that, as of trial, he had observed no signs of settlement in the slab or the yard around it or damage to the home. Crowther’s sole recommendation for correction of the problem was that, in the area where he observed the one limb which, in his opinion, was going under the footer, the limb be removed and the area undercut, the dirt be removed, and the area backfilled with “flowable fill,” a low strength concrete that can flow under the footings and fill back in.

Based on this testimony of Crowther, Tidal objected to the introduction of the testimony of Alan Mock, owner of Mock Construction Company, who had, based solely on a drawing of the excavation spots prepared by Crowther, prepared an estimate of what it would cost to excavate under the entire one-third of the slab where debris was opined to exist, shore that area up and replace the soil under it, basically deconstruct that portion of the house over that area, and rebuild it. His estimate was $199,226.06. Wise testified that, in her opinion, the fair market value of the house in 2003 was between $150,000 and $160,000.

The trial court sustained this objection and then granted the motion for directed verdict of Tidal.

*728 1. Wise’s first enumeration of error is that the trial court erred in directing a verdict based on the possibility that the repair cost may be greater than the home’s fair market value.

Wise proceeded on breach of contract and negligent construction theories. 3 No breach of contract was demonstrated, leaving only the negligence claim.

(a) The motion for directed verdict was premised on Wise’s failure to prove any demonstrable damages to the home by any breach of duty by Tidal and that, even if a breach were shown, the only damages testified to by Crowther, the needed removal of the one limb and slurrying, were not the basis for the estimation of repair costs made by Mock.

In her second enumeration of error, Wise argues that these two bases for the directed verdict are all we may consider. This, however, is incorrect. 4 “If a judgment entered pursuant to the granting of a directed verdict is right for any reason, it will be affirmed. Star Mfg. v. Edenfield, 191 Ga. App. 665, 668 (382 SE2d 706) [(1989)].” Fowler v. Smith, 230 Ga. App. 817, 821 (3) (498 SE2d 130) (1998). See also Looney v. M-Squared, 262 Ga. App. 499, 505, n.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NORFOLK BELT LINE R. CO. v. Wilson
667 S.E.2d 735 (Supreme Court of Virginia, 2008)
John Thurmond & Associates, Inc. v. Kennedy
668 S.E.2d 666 (Supreme Court of Georgia, 2008)
Considine v. City of Waterbury
905 A.2d 70 (Supreme Court of Connecticut, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
608 S.E.2d 11, 270 Ga. App. 725, 2004 Fulton County D. Rep. 3684, 2004 Ga. App. LEXIS 1435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wise-v-tidal-construction-co-gactapp-2004.