Wise v. Tidal Const. Co., Inc.

583 S.E.2d 466, 261 Ga. App. 670, 2003 Fulton County D. Rep. 1715, 2003 Ga. App. LEXIS 639
CourtCourt of Appeals of Georgia
DecidedMay 23, 2003
DocketA03A0859
StatusPublished
Cited by33 cases

This text of 583 S.E.2d 466 (Wise v. Tidal Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wise v. Tidal Const. Co., Inc., 583 S.E.2d 466, 261 Ga. App. 670, 2003 Fulton County D. Rep. 1715, 2003 Ga. App. LEXIS 639 (Ga. Ct. App. 2003).

Opinion

Eldridge, Judge.

This is an interlocutory appeal from the trial court’s stay and order for mandatory arbitration under the Federal Arbitration Act, *671 because Mary L. Rose Wise and Nell Lackman, plaintiffs, contend that Tidal Construction Company, Inc.’s inconsistent actions (proceeding with discovery, motion for summary judgment, entry of a pre-trial order, and jury selection) waived the right to arbitration. 1 Finding that Tidal Construction’s inconsistent conduct constituted a waiver of the arbitration agreement, we reverse.

On October 16, 2000, the builder-sellers, Tidal Construction Company, Inc., C. L. Stafford Building Contractor, Inc., and C. L. Stafford were sued by the purchasers Mary L. Rose Wise and Nell Lackman for negligence, negligence per se, breach of implied warranty of good workmanship, and breach of contract as to the implied duty of good workmanship for estimated special damages of $199,000, because the new house, which was sold to them for $138,000, was built over a buried wood debris field. On December 5, 2000, Tidal Construction answered and stated “[t]his matter may be subject to mandatory binding arbitration pursuant to the contract or contracts between this [sic] parties and should be dismissed.” The parties proceeded with litigation and went through extensive discovery, including some eight depositions. On October 24, 2001, Tidal Construction moved for summary judgment based upon the discovery. In November 2001, the case came on the trial calendar but was continued by agreement to complete discovery. On February 13, 2002, the parties entered into a consolidated pre-trial order without Tidal Construction again raising the issue of mandatory arbitration, On February 20, 2002, the trial court set the case for trial on the calendar for March 21-April 17, 2002. Finally, on March 7, 2002, Tidal Construction moved for a stay for mandatory arbitration and to amend the pre-trial order to assert such defense. The. plaintiffs dismissed their warranty claims under the construction contract; also, they dismissed the claims against Stafford and his company to avoid the arbitration issue; On March 20, 2002, the parties struck a jury for the special trial set for April 21, 2002. On September 18, 2002, the trial court granted the stay and ordered arbitration, which earlier order had been misfiled and not sent to the parties. By March 7, 2002, when Tidal Construction filed its demand for arbitration, the plaintiffs’ trial preparation expenses exceeded $11,000.

The basis for Tidal Construction’s demand for mandatory arbitration was: on March 16, 1997, the parties entered into a sales contract, providing the special condition that the “SELLER TO FUR *672 NISH A 2/10 HOME WARRANTY.” On March 26, 1997, Tidal Construction complied by issuing a “Workmanship/Systems and Structural Limited Warranty,” which was administered by the Home Buyers Warranty Corporation and insured by National Home Insurance Company, foreign corporations; Mary L. Rose signed the application for this home enrollment under this express warranty. Attached to the application was the “Home Buyers Warranty Booklet,” which included mandatory arbitration of all claims arising in warranty, contract, fraud, or tort under the FAA. The express written warranty was issued to the plaintiffs as part of the sale contract, which incorporated the warranty booklet with the mandatory arbitration clause under the FAA.

1. Plaintiffs contend that the trial court erred in compelling arbitration, because they did not allege a violation of the Home Buyers Warranty, causing the arbitration clause to be invoked. We do not agree.

The arbitration clause provided that the mandatory arbitration come under the FAA, 9 USC §§ 1-16, excluding any contrary provisions of state law. Issues as to the applicability of and the scope of arbitration were matters for arbitration under the arbitration clause. Plaintiffs agreed to such provisions for arbitration.

Plaintiffs sought to avoid arbitration by abandoning their warranty claims; however, both breach of contract and negligence claims come within the mandatory arbitration clause, as well as warranty claims, and do not violate Georgia public policy by requiring such issues to be arbitrated. Haynes v. Fincher, 241 Ga. App. 179, 180 (1) (525 SE2d 405) (1999). “[A]ny doubts concerning the scope of arbitra-ble issues should be resolved in favor of arbitration.” Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp., 460 U. S. 1, 24-25 (103 SC 927, 74 LE2d 765) (1983). In this case, the arbitration clause stated that it was to cover “[a]ny and all disputes and controversies arising under or relating to this Agreement,” and therefore, was intended to be broad enough in scope to reach all disputes.

We believe that, as a matter of law, the arbitration clause in the 1990 Agreement is broad. The clause provides that arbitration is the exclusive remedy available to the parties to settle controversies or claims that not only arise from the 1990 Agreement but also those relating to the contract. The Second Circuit considered language nearly identical to the language here, calling it “the paradigm of a broad clause.” Collins & Aikman Prods. Co. v. Building Sys., Inc., 58 F3d 16, 20 (2d Cir. 1995). Such a provision constitutes the broadest language the parties could reasonably use to subject their disputes to that form of settlement, including col *673 lateral disputes that relate to the agreement containing the clause. . . . Where a broad arbitration clause is in effect, even the question of whether the controversy relates to the agreement containing the clause is subject to arbitration.

(Citation, punctuation and footnote omitted.) Fleet Tire Svc. of North Little Rock v. Oliver Rubber Co., 118 F3d 619, 621 (8th Cir. 1997). A party may not avoid a contractual arbitration clause merely by “ ‘casting its complaint in tort.’ ” (Citation omitted.) In re Oil Spill by the “Amoco Cadiz,” 659 F2d 789, 794 (7th Cir. 1981).

Section 2 [of the FAA] is a congressional declaration of a liberal federal policy favoring arbitration agreements, notwithstanding any state substantive or procedural policies to the contrary. The effect of the section is to create a body of federal substantive law of arbitrability, applicable to any arbitration agreement within the coverage of the Act. .... The Arbitration Act establishes that, as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.

(Citation omitted.) Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp., supra at 24-25; accord DiMambro-Northend Assoc. v. BlanckAlvarez, Inc., 251 Ga. 704, 707 (1) (309 SE2d 364) (1983); Hilton Constr. Co. v. Martin Mechanical Contractors, 251 Ga. 701 (308 SE2d 830) (1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeff Milliken v. C. Merrill Construction, LLC
Court of Appeals of Georgia, 2024
Emory Health Care, Inc. v. Richard Farrell
Court of Appeals of Georgia, 2021
Tauheed Epps v. Rockmo Entertainment, LLC
Court of Appeals of Georgia, 2020
Forrest Cate, III v. Anthony C. Patterson
Court of Appeals of Georgia, 2020
SCHINAZI Et Al. v. EDEN.
830 S.E.2d 531 (Court of Appeals of Georgia, 2019)
Web IV, LLC v. Samples Construction, LLC
824 S.E.2d 107 (Court of Appeals of Georgia, 2019)
Greystone Nevada, LLC v. Huynh
Nevada Supreme Court, 2018
U.S. Home Corp. v. Lanier
Nevada Supreme Court, 2018
SunTrust Bank v. Lilliston
809 S.E.2d 819 (Supreme Court of Georgia, 2018)
Davidson v. A. G. Edwards & Sons, Inc.
748 S.E.2d 300 (Court of Appeals of Georgia, 2013)
Atlantic Station, LLC v. Vratsinas Construction Co.
705 S.E.2d 191 (Court of Appeals of Georgia, 2010)
McLellan v. Chilivis, Cochran, Larkins & Bever, LLP
692 S.E.2d 26 (Court of Appeals of Georgia, 2010)
Etowah Environmental Group v. Advanced Disposal Services, Inc.
676 S.E.2d 456 (Court of Appeals of Georgia, 2009)
Ed Voyles Jeep-Chrysler, Inc. v. Wahls
670 S.E.2d 540 (Court of Appeals of Georgia, 2008)
Hathaway Development Co. v. Advantage Fire Sprinkler Co.
659 S.E.2d 778 (Court of Appeals of Georgia, 2008)
McDonald v. H & S HOMES, LLC
658 S.E.2d 901 (Court of Appeals of Georgia, 2008)
Adajar v. RWR Homes, Inc.
73 Cal. Rptr. 3d 17 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
583 S.E.2d 466, 261 Ga. App. 670, 2003 Fulton County D. Rep. 1715, 2003 Ga. App. LEXIS 639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wise-v-tidal-const-co-inc-gactapp-2003.