Atlantic Station, LLC v. Vratsinas Construction Co.

705 S.E.2d 191, 307 Ga. App. 398, 2010 Fulton County D. Rep. 4074, 2010 Ga. App. LEXIS 1025
CourtCourt of Appeals of Georgia
DecidedOctober 29, 2010
DocketA10A1134
StatusPublished
Cited by1 cases

This text of 705 S.E.2d 191 (Atlantic Station, LLC v. Vratsinas Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Station, LLC v. Vratsinas Construction Co., 705 S.E.2d 191, 307 Ga. App. 398, 2010 Fulton County D. Rep. 4074, 2010 Ga. App. LEXIS 1025 (Ga. Ct. App. 2010).

Opinion

BARNES, Presiding Judge.

Atlantic Station, LLC, appeals the trial court’s denial of its petition to stay arbitration sought by Vratsinas Construction Company (VCC), which built the parking deck at the mixed use complex, contending that VCC’s claim is not subject to arbitration because it is for services that were not included in the parties’ written contracts. Because Atlantic Station participated in the dispute resolution process for 18 months before filing its petition to stay the arbitration, we affirm.

We review a grant or denial of a motion to stay arbitration de novo to determine whether the trial court was correct as a matter of law. See Tigner v. Shearson-Lehman Hutton, Inc., 201 Ga. App. 713, 715 (411 SE2d 800) (1991). A review of the voluminous record reveals the following relevant evidence.

The multi-use Atlantic Station complex was built on the 138-acre former “brown field” left by Atlantic Steel. In 1999, VCC began working with Atlantic Station, LLC, to develop proposals for the land. 1 At that time, according to VCC’s first arbitration demand, Atlantic Station did not have the personnel or cash flow to undertake the development itself. VCC contends it had an “understanding” with Atlantic Station that it would defer charging for these “precon-struction services” in exchange for the opportunity to serve as the general contractor for any structures that would be built on the property, essentially giving Atlantic Station the “equivalent of an interest free loan.”

The complex was eventually planned and financed, and in *399 February 2001, the parties entered into a contract providing that VCC would build the parking deck and related structures. According to VCC, this contract “merely formalized the relationship of the parties,” who continued to operate under the mutual understanding that VCC would be given the opportunity to serve as the contractor for new buildings in exchange for its continued consulting services. In September 2001, VCC contracted with Atlantic District, an affiliated partnership, to build the outer shell of some of the buildings on site, and in January 2003, VCC entered into a second contract with Atlantic Station when the parking lot design underwent major changes. Neither of these contracts refers to VCC supplying its consulting services in exchange for the right to bid on new construction. Both contracts include merger clauses, provide that they may be amended only by written modification, and contain specific provisions regarding the timing of claims. The contracts also define “preconstruction services” and specify the hourly rates to be charged by different personnel for these services. In the February 2001 contract the parties agree that VCC’s preconstruction phase began in 1999. The January 2003 contract states that the precon-struction phase began in April 2002.

In May 2006, according to VCC’s initial arbitration demand, Atlantic Station did not allow VCC to submit proposals to serve as the contractor for additional buildings, and in June 2006 VCC billed Atlantic Station for $4.5 million in services rendered from 1999 to 2004. (The company notes that it elected not to bill for services from 2004 to May 2005.) Atlantic Station did not respond to the invoices, and on March 28, 2007, VCC submitted its claims to the project architect, following the payment procedures set forth in the contracts. The architect did not respond in 30 days, and in April 2007 VCC submitted a demand for mediation to the American Arbitration Association (AAA) pursuant to the 2001 contract. In mid-August 2007, Atlantic Station sought backup documentation for the invoices and within a week VCC submitted documentation to Atlantic Station, detailing the services for which VCC sought payment. The parties participated in two unsuccessful mediation sessions in August and November 2007.

On December 18, 2007, VCC filed another demand for arbitration with AAA. In January 2008, Atlantic Station filed an answer and a counterclaim for $1 million, but did not object to the arbitration itself. The parties selected the arbitration panel and began conducting discovery. Meanwhile, Atlantic Town Center, a related entity which owns the retail and residential portions of the project, initiated an arbitration demand against VCC in May 2008, for damages allegedly resulting from water leaks in the buildings. Shortly afterward, Atlantic Station filed a motion in that proceeding, *400 seeking to have VCC’s claim against it for services heard at the same time as Atlantic Town Center’s water damage claims against VCC, and both arbitrations were stayed while AAA decided whether to consolidate the two demands. The motion to consolidate was denied in January 2009. Atlantic Station participated in the arbitration for six months, during which time it served discovery demands, produced and received documents, filed and opposed motions before the arbitrators, participated in telephone hearings with the Arbitrator Panel, and took depositions.

VCC amended its arbitration demand twice. It describes its first amendment in March 2009 as having “refined and expanded on facts in the original Statement of Claim,” but seeking the same amount of damages under the same theories of recovery. The second amendment in June 2009 also sought the same amount of relief. In May 2009, VCC produced 27,000 pages of documents backing up its claim for services performed throughout the project. According to Atlantic Station, depositions taken in June and July 2009 “clarified the basis of VCC’s claims” regarding the agreement upon which it relied to recover the costs of its development services. In one of these depositions, a VCC officer testified that when VCC was denied the opportunity to bid on a contract to build a 24-story office tower in 2006, it considered the agreement breached and issued the invoices, which cover development services provided in connection with the entire project site, not just the parking deck.

Atlantic Station then filed a petition to stay the arbitration, contending that “deposition testimony in recent weeks has demonstrated that VCC seeks to recover in arbitration for work outside the scope of the parties’ contract and outside the scope of the written arbitration agreement within the contract.” According to Atlantic Station, its motion to stay was timely because as a result of “procedural issues” — the motion to consolidate — the parties “did not exchange documents until May 2009” and did not take depositions until late June 2009. Atlantic Station filed the motion to stay within 30 days of the revealing depositions. In its motion to stay, Atlantic Station asserted that the arbitration was barred because the claims were for services outside the scope of the contract. It further contended that VCC failed to make the claims within 21 days of the costs being incurred, as required by the contract, and that the statute of limitation had run on some of the claims.

The trial court held a hearing in November 2009, and denied the motion to stay. In its order the court found that “from the sum and substance of the Agreement between them and the ALA documents that were in place between them and the arguments of counsel that it was the intent specifically of Atlantic Station and VCC to arbitrate.”

*401

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Salinas v. Atlanta Gas Light Company
819 S.E.2d 903 (Court of Appeals of Georgia, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
705 S.E.2d 191, 307 Ga. App. 398, 2010 Fulton County D. Rep. 4074, 2010 Ga. App. LEXIS 1025, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-station-llc-v-vratsinas-construction-co-gactapp-2010.