Jeff Milliken v. C. Merrill Construction, LLC

CourtCourt of Appeals of Georgia
DecidedMay 29, 2024
DocketA24A0348
StatusPublished

This text of Jeff Milliken v. C. Merrill Construction, LLC (Jeff Milliken v. C. Merrill Construction, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeff Milliken v. C. Merrill Construction, LLC, (Ga. Ct. App. 2024).

Opinion

FOURTH DIVISION DILLARD, P. J., BROWN and PADGETT, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

May 29, 2024

In the Court of Appeals of Georgia A24A0348. MILLIKEN v. C. MERRILL CONSTRUCTION, LLC.

BROWN, Judge.

Jeff Milliken (“the owner”) appeals from the trial court’s entry of a final money

judgment of $100,827.96 in favor of C. Merrill Construction, LLC (“the contractor”)

following his confession of judgment. The owner contends that the trial court erred

in denying his motion to compel arbitration and to dismiss, in granting the

contractor’s motion to stay arbitration, in its rulings on discovery, and in granting

attorney fees to the contractor. For the reasons explained below, we affirm the trial

court’s denial of the owner’s motion to dismiss, reverse the trial court’s denial of the

owner’s motion to compel arbitration and its grant of the contractor’s motion to stay arbitration, vacate the trial court’s discovery orders and final judgment, and remand

with direction for the trial court to order the parties to submit to arbitration.

The record shows that on January 6, 2021, the parties entered into a

construction contract that included a dispute resolution provision. On October 7,

2022, the contractor filed suit alleging the owner breached the contract by failing to

pay over $48,000 in outstanding invoices, $5,225.58 owed on an open account for

repairs performed for the owner at a different restaurant location, $8,441 owed on an

open account for HVAC repairs, and interest on these amounts. In addition to its

breach of contract and open account claims, the contractor sought damages based

upon unjust enrichment, quantum meruit, as well as a writ of attachment on restaurant

equipment listed for sale and attorney fees, litigation expenses, and costs. The

complaint was served on October 21, 2022, and the owner filed an answer on

November 16, 2022, denying liability; the owner did not raise arbitration as a defense

to the lawsuit.

On January 5, 2023, the owner moved the trial court to dismiss the lawsuit and

compel arbitration. According to the owner’s motion, the contractor failed to make

a demand for arbitration under the contract and brought litigation in violation of the

2 contract terms. The contractor opposed the motion and requested a stay of arbitration

under OCGA § 9-9-6 (b), arguing that the owner waived his right to arbitration, failed

to comply with the agreement to arbitrate by ignoring the contractor’s pre-suit request

for mediation and demand for arbitration, and that not all of the claims asserted in the

complaint were subject to arbitration.

On February 6, 2023, the trial court scheduled a hearing for March 6, 2023, on

the owner’s motion to dismiss and compel arbitration. The following day, however,

the trial court issued a short order denying the motion based upon its consideration

of the written submissions of both parties. It subsequently denied the owner’s request

for a certificate of immediate review.

On March 17, 2023, the owner filed a verified “Confession of Judgment” in

which he authorized “the clerk of the superior court” to enter “judgment for

$69,009.55.” The document recites that the owner “desires to confess judgment . .

. to settle all claims made or that could have been made by [the contractor]” in the

pending lawsuit. On April 6, 2023, the owner paid $69,009.55 into the registry of the

clerk of court.

3 On May 8, 2023, the contractor filed a motion for attorney fees under OCGA

§ 9-15-14 and OCGA § 13-6-11. Following the filing of an opposition brief by the

owner and a hearing held on July 10, 2023, the trial court entered a judgment, as later

amended to correct a minor mathematical error, in the total amount of $100,827.96,

based upon the confessed judgment amount of $69,009.55, prejudgment interest of

$11,317.74, and a $27,431.84 award of attorney fees and expenses under OCGA § 9-15-

14 (b) and OCGA § 13-6-11.

1. The owner asserts that the trial court erred in denying his motion to dismiss

and compel arbitration and in granting the contractor’s motion to stay arbitration,

contending that he did not waive his right to arbitration after the contractor filed suit,

did not fail to comply with conditions precedent for arbitration, and that all of the

claims in the contractor’s complaint should be submitted to the arbitrator. As outlined

below, the trial court should have ordered the parties to submit to arbitration.

“This Court reviews the grant or denial of a motion to compel arbitration de

novo to see if the trial court’s decision is correct as a matter of law; but we defer to the

trial court’s factual findings unless they are clearly erroneous.” Emory Healthcare v.

Farrell, 359 Ga. App. 621, 622 (859 SE2d 576) (2021). “The Federal Arbitration Act

4 (“FAA”) applies in state and federal courts to all contracts containing an arbitration

clause that involves or affects interstate commerce. When the FAA applies, as it does

here, it must be applied using federal substantive law.” (Citations and punctuation

omitted.) SunTrust Bank v. Lilliston, 302 Ga. 840, 842 (809 SE2d 819) (2018). As a

preliminary matter, we must determine whether the trial court or the arbitrator should

have determined the issues of waiver, compliance with conditions precedent, and

whether all of the claims asserted in the complaint are subject to arbitration. See

generally Brown v. RAC Acceptance East, 303 Ga. 172, 174-177 (2) (a)-(b) (809 SE2d

801) (2018).

(a) Conduct-based waiver. In general, “courts decide issues of alleged conduct-

based waiver of arbitration rights[,] . . . but . . . where there is clear and unmistakable

evidence that the parties wanted an arbitrator to resolve the dispute about arbitrability,

courts must give effect to the parties’ agreement.” (Citations and punctuation

omitted.) Brown, 303 Ga. at 175 (2) (a). Accordingly, the Supreme Court of Georgia

has previously held that contract language assigning the “responsibility for resolving

‘disputes about the validity, enforceability, arbitrability or scope of this Arbitration

Agreement’ to the arbitrator” provides clear and unmistakable evidence that the

5 arbitrator should decide the issue of conduct-based waiver. Id. at 175-176 (2) (a). More

specifically, the Supreme Court concluded that the appellant’s “conduct-based waiver

argument is a direct challenge to the enforceability of the arbitration agreement.”

(Emphasis supplied.) Id. at 176 (2) (a).

In this case, the parties’ arbitration agreement does not assign responsibility for

resolving disputes involving enforceability to the arbitrator; we must therefore

examine the particular contract language before us for any clear and unmistakable

intent for the arbitrator to decide the issue of conduct-based waiver. The front page

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kemiron Atlantic, Inc. v. Aguakem International, Inc.
290 F.3d 1287 (Eleventh Circuit, 2002)
Ed Voyles Jeep-Chrysler, Inc. v. Wahls
670 S.E.2d 540 (Court of Appeals of Georgia, 2008)
Langfitt v. Jackson
644 S.E.2d 460 (Court of Appeals of Georgia, 2007)
Wise v. Tidal Const. Co., Inc.
583 S.E.2d 466 (Court of Appeals of Georgia, 2003)
Phil Wooden Homes, Inc. v. Ladwig
586 S.E.2d 697 (Court of Appeals of Georgia, 2003)
USA Payday Cash Advance Center 1 v. Evans
637 S.E.2d 418 (Court of Appeals of Georgia, 2006)
Stark v. Molod Spitz DeSantis & Stark, P.C.
876 N.E.2d 903 (New York Court of Appeals, 2007)
Web IV, LLC v. Samples Construction, LLC
824 S.E.2d 107 (Court of Appeals of Georgia, 2019)
James Darren Summerville v. Innovative Images, LLC
826 S.E.2d 391 (Court of Appeals of Georgia, 2019)
Intl Engy Ventures Manage v. Untd Engy Grp
999 F.3d 257 (Fifth Circuit, 2021)
SunTrust Bank v. Lilliston
809 S.E.2d 819 (Supreme Court of Georgia, 2018)
Morgan v. Sundance, Inc.
596 U.S. 411 (Supreme Court, 2022)
Brown v. RAC Acceptance E., LLC.
809 S.E.2d 801 (Supreme Court of Georgia, 2018)
Miller v. GGNSC Atlanta, LLC
746 S.E.2d 680 (Court of Appeals of Georgia, 2013)
BROWN v. RAC ACCEPTANCE EAST, LLC
303 Ga. 172 (Supreme Court of Georgia, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Jeff Milliken v. C. Merrill Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeff-milliken-v-c-merrill-construction-llc-gactapp-2024.