Rok Builders, LLC v. 2010-1 SFG Venture LLC

726 F.3d 1, 2013 WL 3752482, 2013 U.S. App. LEXIS 14546, 58 Bankr. Ct. Dec. (CRR) 56
CourtCourt of Appeals for the First Circuit
DecidedJuly 18, 2013
DocketNo. 12-2182
StatusPublished
Cited by38 cases

This text of 726 F.3d 1 (Rok Builders, LLC v. 2010-1 SFG Venture LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rok Builders, LLC v. 2010-1 SFG Venture LLC, 726 F.3d 1, 2013 WL 3752482, 2013 U.S. App. LEXIS 14546, 58 Bankr. Ct. Dec. (CRR) 56 (1st Cir. 2013).

Opinion

KAYATTA, Circuit Judge.

This appeal presents two competing claims to the assets of the bankrupt Moultonborough Hotel Group, LLC. Appellant ROK Builders, LLC constructed a hotel for Moultonborough and has a mechanic’s lien on the property. Appellee 2010-1 SFG Venture, LLC, is the assignee of the construction lender and has a mortgage on the hotel. When Moultonborough filed for bankruptcy, SFG sought a declaration that its mortgage was senior to ROK’s lien to the extent the construction lender had disbursed loan funds to ROK. ROK responded by seeking a declaration that its lien was senior to SFG’s mortgage and by advancing various additional counterclaims. The New Hampshire bankruptcy court and district court ruled for SFG. We now affirm.

I. Background

This dispute has its origins in a project that began in 2006 to build a Hampton Inn & Suites in Tilton, New Hampshire. On December 1, 2006, ROK signed a contract with Moultonborough to construct the hotel. ROK began work, but the project stalled when Moultonborough proved un[3]*3able to pay its bills. In April 2007, ROK terminated the contract due to nonpayment of roughly $1.6 million. ROK signaled its willingness to resume work if Moultonborough secured adequate financing and paid the balance due, with interest.

On June 26, 2007, Moultonborough signed an agreement letter with Specialty Finance Group in which Specialty committed to extending up to $8.7 million in new funding to restart the project. ROK claims to have then immediately taken steps to resume construction. On September 21, ROK signed a new construction agreement with Moultonborough. Less than a month later, on October 10, Specialty signed a formal construction financing agreement with Moultonborough, as anticipated by the commitment letter. As security, Moultonborough executed a mortgage on the property, which Specialty recorded the next day. In conjunction with the financing agreement, Specialty paid ROK more than $1.8 million to settle the amount due, with interest, to ROK under its original 2006 construction agreement with Moultonborough.

ROK then set about finishing the hotel. For its work, it received loan disbursements from Specialty, in conjunction with at least two of which it executed lien waivers. In its final waiver, executed for the period ending May 31, 2008, ROK acknowledged past payments from Specialty of $5,751,419.39 for work done under its 2007 agreement with Moultonborough, and listed a balance due of $954,571.03. The waiver provided,

In consideration of the payment of the above stated sums currently due and amounts previously paid, the receipt of which is hereby acknowledged, [ROK]1 hereby waives, relinquishes, and releases any and all liens, rights, claims and interests (including, without limitation, all rights to mechanic’s and material-men’s liens) owned, to be owned, claimed or held by [ROK] in and to the [Hampton Inn & Suites in Tilton] ... by reason of the labor performed and/or materials furnished by [ROK] ... prior to and including the Payment Date____

At the time it submitted the waiver, ROK was unaware that Specialty had decided to stop payments due to Moultonborough’s failure to secure additional financing, as its loan agreement with Specialty required. Indeed, Specialty did not inform ROK of this decision even when it received the waiver, and ROK performed further work in June, still unaware that it would not be paid. ROK’s briefs do not dispute that it received an additional $682,655.01 from Specialty, presumably after the May waiver, yielding a total payout of $6,434,074.40 for work performed under the 2007 construction contract. However, ROK maintains that it is still owed $2,487,411.94 for work under that contract, secured by a mechanic’s lien.2

[4]*4Despite the unresolved payment issue, the hotel opened successfully in June of 2008. Moultonborough and Specialty, however, soon found themselves in financial trouble. In May of 2009, Specialty’s parent company, Silverton Bank, N.A., failed, and Specialty assigned the construction mortgage on the hotel to the Federal Deposit Insurance Corporation, the receiver for Silverton. Soon after, the FDIC assigned the mortgage to SFG. Later in 2009, Moultonborough filed a petition in New Hampshire bankruptcy court for reorganization under chapter 11 of the bankruptcy code.

On March 15, 2011, SFG initiated an adversary proceeding against ROK in bankruptcy court, seeking a declaration that $6,434,074.40 of the construction mortgage — the amount Specialty had disbursed to ROK for work performed under the 2007 construction contract — was senior to ROK’s mechanic’s lien. In response, ROK filed a dozen counterclaims: two seeking a determination that its lien was senior to SFG’s mortgage, and an additional ten advancing causes of action sounding in tort, contract, and equity. SFG filed a motion to dismiss, which the bankruptcy court granted as to the ten secondary counterclaims. SFG then filed a motion for summary judgment on the competing seniority claims, which the bankruptcy court granted. ROK timely appealed to the district court, see 28 U.S.C. § 158(a)(1), which affirmed following de novo review. ROK Builders, LLC v. 2010-1 SFG Venture, LLC, No. 12-cv-57-PB, 2012 WL 3779669 (D.N.H. Aug. 30, 2012). On September 28, 2012, ROK filed a timely notice of appeal to this court.

II. Analysis

On appeal, ROK challenges the grant of summary judgment on the competing seniority claims and the dismissal of three of its secondary counterclaims — specifically, those for breach of an implied contract, promissory estoppel, and unjust enrichment. Although we constitute the second tier of appellate review in this case arising out of a decision by the bankruptcy court in an adversary proceeding, “we cede no special deference to the determinations made by the ... district court” and instead “assess the bankruptcy court’s decision directly.” City Sanitation, LLC v. Allied Waste Servs, of Mass., LLC (In re Am. Cartage, Inc.), 656 F.3d 82, 87 (1st Cir.2011). In doing so, we “scrutinize that court’s findings of fact for clear error, and afford de novo review to its conclusions of law.” Brandt v. Repco Printers & Lithographies, Inc. (In re Healthco Int'l, Inc.), 132 F.3d 104, 107 (1st Cir.1997).

The legal standards traditionally applicable to motions for summary judgment and motions to dismiss apply without change in bankruptcy proceedings. See Soto-Rios v. Banco Popular de P.R., 662 F.3d 112, 115 (1st Cir.2011); Banco Santander de P.R. v. López-Stubbe (In re Colonial Mortg. Bankers Corp.), 324 F.3d 12, 15 (1st Cir.2003). Accordingly, in reviewing the bankruptcy court’s summary judgment ruling, our inquiry is whether any “genuine issue of material fact exists” and whether “the moving party is entitled to judgment as a matter of law.” Soto-Rios, 662 F.3d at 115; see also Fed. R. Bankr.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
726 F.3d 1, 2013 WL 3752482, 2013 U.S. App. LEXIS 14546, 58 Bankr. Ct. Dec. (CRR) 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rok-builders-llc-v-2010-1-sfg-venture-llc-ca1-2013.