Graton & Knight Manufacturing Co. v. Woodworth-Mason Co.

38 A. 790, 69 N.H. 177
CourtSupreme Court of New Hampshire
DecidedJune 5, 1897
StatusPublished
Cited by6 cases

This text of 38 A. 790 (Graton & Knight Manufacturing Co. v. Woodworth-Mason Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graton & Knight Manufacturing Co. v. Woodworth-Mason Co., 38 A. 790, 69 N.H. 177 (N.H. 1897).

Opinion

Chase, J.

“ If a person shall . . . furnish materials to the amount of fifteen dollars or more, for erecting ... a house or other buildings or appurtenances, by virtue of a contract with the owner thereof, he shall have a lien thereon and on any right of the owner to the lot of land on which the house, building, or appurtenances stand,” for ninety days after the materials are furnished. P. S., e. 141, ss. 10, 16. Whether the belting was a material to be used in the erection of the box factory building or its appurtenances, depends upon the question whether it would be a fixture after it was attached to the machinery as intended. Belting may be a fixture. Burnside v. Twitchell, 43 N. H. 390; Langdon v. Buchanan, 62 N. H. 657. In determining whether it is in a given case, “ the purpose of the annexation and the intent with which it is made are the important considerations.” Langdon v. Buchanan, 62 N. H. 657, 660. It is a mixed question of law and fact. Kent v. Brown, 59 N. H. 236; Turner v. Wentworth, 119 Mass. 459.

It is not found whether the belting became a fixture when affixed to the machinery as intended. If it did, the plaintiffs, by furnishing it, furnished a material for erecting the building or its appurtenances within the meaning of the statute. In such case, the lien w'ould attach upon the furnishing of the belting, although the belting was not affixed to the machinery until a later time. Barstow v. Robinson, 2 Allen 605. The building being in the course of erection when the claimant took the mortgages, he would have constructive, if not actual, notice of the contract under which the belting was furnished, and his security would be subject to the statutory lien, if one existed. Cheshire Provident Institution v. Stone, 52 N. H. 365; Pike v. Scott, 60 N. H. 469, 472.

Case discharged,

Blodgett, J., did not sit: the others concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
38 A. 790, 69 N.H. 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graton-knight-manufacturing-co-v-woodworth-mason-co-nh-1897.