Remediation Constructors, Inc. v. United States

68 Fed. Cl. 162, 2005 U.S. Claims LEXIS 286, 2005 WL 2445472
CourtUnited States Court of Federal Claims
DecidedSeptember 30, 2005
DocketNo. 03-2478C
StatusPublished
Cited by7 cases

This text of 68 Fed. Cl. 162 (Remediation Constructors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Remediation Constructors, Inc. v. United States, 68 Fed. Cl. 162, 2005 U.S. Claims LEXIS 286, 2005 WL 2445472 (uscfc 2005).

Opinion

MEMORANDUM OPINION AND ORDER DENYING PARTIAL SUMMARY JUDGMENT AND GRANTING MOTION TO FILE FIRST SUPPLEMENTAL COMPLAINT

BRADEN, Judge.

RELEVANT FACTS1

On May 15, 2001, the United States (“the Government”) entered into Contract No. 1443C80000100903 (“the Contract”) with Remediation Constructors, Inc. (“Remcon”) to perform certain construction work in Sequoia National Park in California. See Compl. ¶ 4; Pl. Findings Resp. ¶ 1. The Contract required: demolition of an existing comfort station, road, and parking area; the construction of a new comfort station, access road, parking lot, pedestrian trail, and leach field; and the re-alignment of the General’s Highway to incorporate roadside parking and site restoration. See Gov’t Mot. S.J. at 2-3; Pl. PF ¶¶ 3-5. The Contract required Rem-con to complete the project within 792 calendar days2 at a price of $7,121,636.00. See Pl. Findings Resp. ¶¶ 1,2.

Remcon asserts that performance was adversely affected because of omission, errors, and inconsistencies in the project design, coupled with mistakes and delays made by the National Park Service.3 See Compl. ¶ 7; Pl. PF ¶¶ 2, 21, 23, 24, 28-33, 41-53, 56-61, 70-75, 77, 78,82-84, 86, 87, 93, 118, 134. Remcon also contends that the Government’s actions caused multiple breaches of the Contract, thereby excusing Remcon from completing performance. See Pl. Findings Resp. ¶ 16. Remcon further asserts that these events also increased the cost of the project and that the Government failed to timely and fully pay Remcon for the work performed during the 2001 and 2002 construction seasons.4 Id ¶ 19. The Government denies responsibility for Remcon’s failure to remain on schedule and within budget. See Answer ¶ 7.

On July 24, 2003, the Government issued a cure notice to Remcon because of the limited progress in completing the job and “fail[ure] to mobilize to the site for the 2003 construction season.” Pl. Findings Resp. ¶¶ 17-21. The Government contends that neither Rem-con, nor anyone on its behalf, responded to the July 24, 2003 cure notice; and, therefore, [164]*164the Government terminated the Contract for default on August 13, 2003. Id. ¶¶25, 26. Remcon challenges the validity of the cure notice and justification for issuance. Id. ¶ 18. Remcon also disputes the Government’s assertion that, it never received a response to the cure notice, because Remcon allegedly provided multiple letters and a certified claim responding to the substance of the cure notice.5 Id. ¶ 25.

PROCEDURAL BACKGROUND

On October 21, 2003, Remcon filed a Complaint in the United States Court of Federal Claims alleging that the Government’s failure to agree to an equitable adjustment of the contract price and to remit other monies due breached the Contract. See Compl. ¶ 13. In addition, the Complaint alleges that the Government wrongfully terminated Remcon for default. See Compl. ¶ 14. The Government filed an Answer on March 8, 2004.

On March 18, 2005, Remcon filed a Motion to File and Serve First Supplemental Complaint regarding events that transpired after the Government terminated the Contract for default. The Government filed a response in opposition to this motion on April 29, 2005.

On June 24, 2005, the Government filed a Motion for Partial Summary Judgment regarding the Government’s default termination. Remcon filed an opposition on July 22, 2005. The Government filed a reply on September 2, 2005.6

DISCUSSION

A. Jurisdiction.

The United States Court of Federal Claims has jurisdiction “to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1). The Tucker Act, however, is “only a jurisdictional statute; it does not create any substantive right enforceable against the United States for money damages.” United States v. Mitchell, 445 U.S. 535, 538, 100 S.Ct. 1349, 63 L.Ed.2d 607 (1980) (quoting United States v. Testan, 424 U.S. 392, 398, 96 S.Ct. 948, 47 L.Ed.2d 114 (1976)). Therefore, to satisfy jurisdictional requirements of the Tucker Act, a plaintiff must identify and plead a constitutional provision, federal statute, independent contractual relationship, and/or executive agency regulation that provides a substantive right to money damages. See Todd v. United States, 386 F.3d 1091, 1094 (Fed.Cir.2004) (“[Jjurisdiction under the Tucker Act requires the litigant to identify a substantive right for money damages against the United States separate from the Tucker Act.”); see also Roth v. United States, 378 F.3d 1371, 1384 (Fed.Cir.2004) (“Because the Tucker Act itself does not provide a substantive cause of action, ... a plaintiff must find elsewhere a money-mandating source upon which to base a suit.”).

In this case, the United States Court of Federal Claims has “jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under ... the Contract Disputes Act of 1978, 41 U.S.C. [165]*165§§ 601-613, (‘Contract Disputes Act’) including a dispute concerning ... rights in tangible or intangible property, compliance with cost accounting standards, and other non-monetary disputes on which a decision of the contracting officer has been issued under section 6 of that Act.” 28 U.S.C. § 1491(a)(2); see Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1270 (Fed.Cir.1999) (holding that “the Tucker Act grants the United States Court of Federal Claims jurisdiction to grant nonmonetary relief in connection with contractor claims, including claims requesting an interpretation of contract terms.”).

Section 6 of the Contract Disputes Act provides that claims7 relating to a contract by a contractor or the Government shall be submitted to the contracting officer for a decision and that the contracting officer’s decision shall be in writing and furnished to the contractor, stating the reasons for the decision and informing the contractor of its rights thereunder. See 41 U.S.C. § 605(a); see also Alliant Techsystems, Inc., 178 F.3d at 1267 (discussing the requirements set forth in § 605(a)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Information Sciences Corp. v. United States
86 Fed. Cl. 269 (Federal Claims, 2009)
American Red Ball International, Inc. v. United States
79 Fed. Cl. 474 (Federal Claims, 2007)
Patton v. United States
74 Fed. Cl. 110 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
International Data Products Corp. v. United States
70 Fed. Cl. 387 (Federal Claims, 2006)
Pacific Gas & Electric Co. v. United States
70 Fed. Cl. 758 (Federal Claims, 2006)
Tennessee Valley Authority v. United States
69 Fed. Cl. 515 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
68 Fed. Cl. 162, 2005 U.S. Claims LEXIS 286, 2005 WL 2445472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/remediation-constructors-inc-v-united-states-uscfc-2005.