Reiman Construction Co. v. Jerry Hiller Co.

709 P.2d 1271, 1985 Wyo. LEXIS 620
CourtWyoming Supreme Court
DecidedNovember 25, 1985
Docket85-39, 85-40
StatusPublished
Cited by24 cases

This text of 709 P.2d 1271 (Reiman Construction Co. v. Jerry Hiller Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reiman Construction Co. v. Jerry Hiller Co., 709 P.2d 1271, 1985 Wyo. LEXIS 620 (Wyo. 1985).

Opinions

BROWN, Justice.

This appeal results from an action for damages due to the faulty construction of a commercial building and warehouse near Casper, Wyoming. The owner of the building, appellee Jerry Hiller Company (hereinafter Hiller), filed suit against the soils [1273]*1273engineering firm of Chen & Associates (hereinafter Chen), the architectural firm of appellant Gerald Deines & Associates (hereinafter Deines), the engineering firm of appellant Volk & Harrison, P.C. (hereinafter Volk & Harrison), and the building contractor, appellant Reiman Construction Company (hereinafter Reiman). At the close of Hiller’s ease, the court dismissed the complaint against Chen and rendered judgment in favor of Hiller, finding Deines, Volk & Harrison, and Reiman negligent and liable to Hiller for the damage caused.

In Case No. 85-39, Reiman appeals from the judgment and raises the following issues:

“1. Will the evidence in this case support a judgment against Reiman Construction Company?
“2. Did the District Court err in refusing to specify its method of computing damages, thereby preventing an effective review?
“3. Did the District Court err in failing to determine specific percentages of negligence?
“4. Did the District Court err in failing to allocate damages among the defendants?”

In Case No. 85-40, appellant Deines and appellant Volk & Harrison together seek review of the judgment and raise the following issues:

“A. The Trial Court committed reversible error in failing to assess negligence against the Appellees.
“B. The Trial Court committed reversible error in failing to assess negligence against Defendant Chen and Associates. “C. The Trial Court committed reversible error in awarding damages that were excessive.”

The appeals were consolidated for argument and opinion. We will reverse the trial court’s judgment finding Reiman negligent in Case No. 85-39. In Case No. 85-40, we will affirm the trial court’s judgment finding Deines and Volk & Harrison negligent. On the issue of damages, we will remand the case to the district court.

In August 1977, Hiller entered into a contract with the architectural firm of Deines to design an office and warehouse building. Deines subsequently obtained a soils report from Chen and enlisted the engineering services of Volk & Harrison to design the foundation and floor of the building. When all the construction bids were received, Reiman’s was the lowest at $604,000, but well above the projected cost of $450,000. Therefore, all bids were rejected, and Hiller, at the suggestion of Deines, retained an outside consulting engineer to modify the building design and thereby reduce the construction cost. After the modification plans were completed, Reiman agreed tu construct the building, as modified, for the sum of $542,551.

The Chen soils report was used by both Deines and Volk & Harrison in the original design as well as the subsequent modified design. However, as Reiman points out in its brief, the plans did deviate from the soils report in the following respects:

“(1) Sheet FP of the plans showed that the floor slab was to be tied directly to the foundation, without providing for an expansion joint;
“(2) The roof drain on the north side of the building discharged directly against the side * * *;
“(3) No sloping contour lines were shown on the north side of the building

Construction on the building was substantially completed in December of 1979, and Hiller moved into the building. Subsequently, in July of 1981, inspection revealed cracks in the building. All witnesses agreed the damage was caused by water infiltrating into the foundation, causing the soil to expand.

In its decision letter, the trial court found:

“1. In August of 1977, plaintiffs and defendant Deines contracted for Deines to design an office and warehouse building for plaintiffs. Deines retained defendant Volk and Harrison as structural engineer. In January of 1979, plaintiffs and defendant Reiman contracted for con[1274]*1274struction of the building in accordance with plans and specifications prepared by Deines and Volk.
“2. In September of 1977, a soils report was submitted by defendant Chen noting that the underlying soil possessed a high swell potential. Chen recommended that the building be designed to account for this with particular reference to the floor, exterior ground slope, and roof drain discharges. This report was submitted to Deines, made available to Volk, and included in the specifications for the Reiman contract.
“3. The building was not designed and constructed to accommodate the findings and recommendations of the soils report. The design and construction should have allowed for vertical movement of the floor and walls, for roof drains to discharge water a sufficient distance from the foundation, and for adequate exterior ground slope to drain water away from the building.
“4. Defendants had a duty to design and construct the building in accordance with the soils report. The breach of this duty was negligence and below standards in the industry. It was technically feasible to design and construct the building to allow for the soil conditions. “5. As a result of the negligence of defendants, roof drains discharged water too near the foundation and the drainage slope north of the building was inadequate. Water thus flowed underneath the floor slab, causing the ground to swell. The slab heaved, causing cracks in the floor, walls, and ceiling and relating damages throughout the office portion of the building.
“6. Cracks appeared in the concrete before completion of the building. Plaintiffs occupied the building in December of 1979, with the understanding that the defects had been or would be corrected by Deines and Reiman.
“7. There was no negligence by Chen or plaintiffs or, if they were negligent, it was not a proximate cause of the damages.
“8. There is not such a disproportion of fault among the defendants as to render inequitable an equal distribution among them of their common liability. The injuries sustained by plaintiffs are incapable of any logical, reasonable or practical division. The conduct of defendants each constitutes a legal cause of the injuries. Thus, the defendants are jointly and severally liable.
“9. As a proximate cause of the negligence of defendants, plaintiffs were injured in the amount of $167,200.00, the reasonable cost of repairs determined from comparing the damage estimates received in evidence.”

CASE NO. 85-39

As noted earlier, appellant Reiman raises the issue of whether there was sufficient evidence to support a finding of negligence against Reiman. Since we find insufficient evidence to find Reiman negligent, we need not address the other issues raised by Rei-man.

As stated above, Reiman constructed the building from the plans and specifications provided by Deines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roden v. State
2007 WY 200 (Wyoming Supreme Court, 2007)
Farmer v. Rickard
2007 WY 19 (Wyoming Supreme Court, 2007)
Rittierodt v. State Farm Insurance Company
3 P.3d 841 (Wyoming Supreme Court, 2000)
McCreary v. Weast
971 P.2d 974 (Wyoming Supreme Court, 1999)
Farmers Insurance Exchange v. Shirley
958 P.2d 1040 (Wyoming Supreme Court, 1998)
Cottonwood Valley Ranch, Inc. v. Roberts
874 P.2d 897 (Wyoming Supreme Court, 1994)
Lynch v. Norton Construction, Inc.
861 P.2d 1095 (Wyoming Supreme Court, 1993)
Hopper v. All Pet Animal Clinic, Inc.
861 P.2d 531 (Wyoming Supreme Court, 1993)
Sewell v. Black Butte Coal Co.
963 F.2d 382 (Tenth Circuit, 1992)
Allied-Signal, Inc. v. Wyoming State Board of Equalization
813 P.2d 214 (Wyoming Supreme Court, 1991)
Miller v. Rissler & McMurry Co.
794 P.2d 91 (Wyoming Supreme Court, 1990)
Martinez v. City of Cheyenne
791 P.2d 949 (Wyoming Supreme Court, 1990)
Melehes v. Wilson
774 P.2d 573 (Wyoming Supreme Court, 1989)
Reposa v. Buhler
770 P.2d 235 (Wyoming Supreme Court, 1989)
Hashimoto v. Marathon Pipe Line Co.
767 P.2d 158 (Wyoming Supreme Court, 1989)
Reiman Construction Co. v. Jerry Hiller Co.
709 P.2d 1271 (Wyoming Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
709 P.2d 1271, 1985 Wyo. LEXIS 620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reiman-construction-co-v-jerry-hiller-co-wyo-1985.