Banner v. Town of Dayton

474 P.2d 300, 1970 Wyo. LEXIS 191
CourtWyoming Supreme Court
DecidedSeptember 8, 1970
Docket3824
StatusPublished
Cited by21 cases

This text of 474 P.2d 300 (Banner v. Town of Dayton) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Banner v. Town of Dayton, 474 P.2d 300, 1970 Wyo. LEXIS 191 (Wyo. 1970).

Opinion

Mr. Justice PARKER

delivered the opinion of the court.

On March 29, 1968, the Town of Dayton filed a complaint against defendant alleging that on October 8, 1956, the parties entered into a contract by which defendant was to supervise and provide engineering services for the construction and laying of a water line from the Tongue River, as the source, to Dayton; that all plans and specifications were either prepared or approved by defendant and all work done under his supervision; that commencing August 3, 1964, numerous leaks developed along the entire length of the line, the cause of which was electrolysis resulting from an improper type of pipe for existing soil conditions, or improper protection of the pipe against electrolysis, or improper laying of pipe, or a combination thereof; that defendant approved the type of pipe used, the method of its protection, and supervised and approved its laying; that defendant negligently failed and neglected to perform adequate soil resistivity tests to determine the soil conditions; that plaintiff’s expense in attempting to seal the leaks amounted to $1,645.42; that plaintiff was required to replace the line in its entirety at an expense of $120,000; and that defendant was negligent in (1) failing to make the necessary soil resistivity tests to determine what type of pipe and coating or protection should be required for the soil conditions, (2) approving a type of pipe which *302 was inadequate for the soil conditions, (3) approving the type of coating or protection placed on the pipe for the soil conditions, and (4) supervising and approving the laying of the pipe, including supervision and approval of the backfill methods — seeking judgment for $121,645.42. Defendant answered, admitting the contract, the preparation or approval of all plans and specifications for the project, but claiming that all this was done as a result of consultations and conferences with plaintiff and that it had assumed all risks. Defendant alleged he performed various inspection services in connection with all work rendered; denied other matters; pleaded that the complaint failed to state a claim; and also alleged affirmatively that the claim was barred by §§ 1-16, 1-17, and 1-18, W.S.1957 (statutes of limitations); that plaintiff had failed to take necessary and reasonable action to mitigate damages; and that he was not required to perform with respect to testing soil resistivity or any other services relating to protection of the system against electrolysis.

Defendant’s motion for summary judgment was denied, and the cause proceeded to trial, at the conclusion of which the court although not so requested under Rule 52(a), W.R.C.P., filed special findings of fact and conclusions of law, found generally for the plaintiff and against the defendant, and entered judgment against him for $25,806, from which this appeal has been taken.

Defendant here contends that (1) the trial court erred in determining the action was not barred by § 1-18, (2) while that court adopted the proper standard of care for a consulting engineer in this State, the evidence did not substantiate that two of the witnesses had sufficient knowledge of recognized Wyoming standards for consulting engineers to qualify them to comment with respect to defendant’s negligence, (3) in considering the evidence most favorable to plaintiff, such evidence wholly fails to substantiate by a preponderance that defendant was negligent in the performance of his duties with respect to the design, supervision, and installation of the water distribution line, and (4) damages awarded were excessive by reason of plaintiff’s failure to mitigate.

There seems no necessity of reciting the factual situation since, with one exception, there is tacit agreement concerning all facts, including the existence of the contract, the preparation and approval by defendant of the plans and specifications for the water line, his supervision of the work, and the later failure of the water line. The only disagreement or confusion concerns the statements made to the Dayton council about electrolysis, which aspect will be discussed later.

STATUTE OF LIMITATIONS

Defendant’s first challenge centers on the rejection of his argument that plaintiff’s action was barred by the statute of limitations. The trial court in its findings on this phase of the case said:

“The Court prefers the rule advocated by the Plaintiff that it should not be precluded by the harsh rule that where it has no way of knowing about the wrongful act until an injury is suffered that the statute of limitations should start to run from the time when the injury is sustained. In this particular case, the Defendant would have no way of knowing the work was defective until it sustained some perceptible injury. The water line was underground where it could not be seen and the forces of electricity were operating in a way that could not be observed. The rule otherwise would practically preclude forever, any relief from professional negligence of engineers, where latent defects take time to appear, in their long term product.
“The Plaintiff started patching in the fall of 1964, shortly after it discovered its first leaks. In the fall of 1965, wet spots appeared and it was then that Mr. Pilch, an engineer of Sheridan was called *303 and after an investigation by a corrosion man from Denver, it was determined that the pipe was being eaten away by electrical forces. In the spring of 1966, the Defendant was contacted. It must be realized that the members of the Town Council are laymen, were justifiably mystified by the cause of the damage that was being wrought. The members had hired professional help because of their inability. It took almost 4 years from the time of the discovery of the first injury until March of 1968 to get the law suit filed. The Court finds that the suit was filed within the four year Statute of Limitations.
“The case of Town Council of the Town of Hudson v. Ladd, 37 Wyo. 419, 263 P. 703 is useful in its equitable view that there could be no cause of action until there was injury. There, work was done in 1914, but damage did not occur until 1925. The Court held that the Statute commenced to run in 1925.”

We must consider whether this finding was erroneous as is contended in the appeal or was a proper disposition of the matter under the circumstances.

There has not been unanimity of viewpoint among courts concerning the time a statute of limitation begins to run in suits charging negligent performance of professional duties. As is frequently true in litigation involving controversial, pivotal questions, the outcome of each suit often depends on its unique facts. Authorities have on occasion pointed out that the law relating to the liability of architects and engineers, two professions which have frequently been held to be controlled by similar principles 1 have evolved from and are similar to those applicable to other professions. Prosser, Law of Torts, p. 164 (3 ed.), says:

“Professional men in general, and those who undertake any work calling for special skill, are required not only to exercise reasonable care in what they do, but also to possess a standard minimum of special knowledge and ability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. State
2001 WY 5 (Wyoming Supreme Court, 2001)
Corkill v. Knowles
955 P.2d 438 (Wyoming Supreme Court, 1998)
Barlage v. Key Bank of Wyoming
892 P.2d 124 (Wyoming Supreme Court, 1995)
Samuel Roberts Noble Foundation, Inc. v. Vick
1992 OK 140 (Supreme Court of Oklahoma, 1992)
Reiman Construction Co. v. Jerry Hiller Co.
709 P.2d 1271 (Wyoming Supreme Court, 1985)
Young v. Young
709 P.2d 1254 (Wyoming Supreme Court, 1985)
Metzger v. Kalke
709 P.2d 414 (Wyoming Supreme Court, 1985)
Olson v. AH Robins Co., Inc.
696 P.2d 1294 (Wyoming Supreme Court, 1985)
ABC Builders, Inc. v. Phillips
632 P.2d 925 (Wyoming Supreme Court, 1981)
Duke v. Housen
589 P.2d 334 (Wyoming Supreme Court, 1979)
South Burlington School District v. Goodrich
382 A.2d 220 (Supreme Court of Vermont, 1977)
Redland v. Tharp
498 P.2d 1240 (Wyoming Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
474 P.2d 300, 1970 Wyo. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/banner-v-town-of-dayton-wyo-1970.