Lynch v. Norton Construction, Inc.

861 P.2d 1095, 1993 Wyo. LEXIS 166, 1993 WL 426358
CourtWyoming Supreme Court
DecidedOctober 25, 1993
Docket92-285
StatusPublished
Cited by31 cases

This text of 861 P.2d 1095 (Lynch v. Norton Construction, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lynch v. Norton Construction, Inc., 861 P.2d 1095, 1993 Wyo. LEXIS 166, 1993 WL 426358 (Wyo. 1993).

Opinions

GOLDEN, Justice.

Pamela and Rick Lynch (the Lynches) appeal the district court’s grant of summary judgment to Norton Construction, Inc. (Norton) on the Lynches’ claim of negligence. The district court found Norton owed no legal duty to the Lynches and was entitled to judgment as a matter of law.

[1096]*1096We decline to adopt the accepted work doctrine urged by Norton, which would extinguish a contractor’s liability to third persons upon the owner’s acceptance of the contractor’s work. We hold instead that a contractor does owe a duty of reasonable care to foreseeable users, even after an owner’s acceptance of the contractor’s work, and traditional negligence principles apply to questions of contractor liability. We affirm the district court’s judgment, however, on the ground that no genuine issue of material fact exists with respect to the question of proximate cause, and Norton is entitled to judgment as a matter of law.

ISSUES

The Lynches present the following issue for our review:

Did the district court correctly grant summary judgment to a contractor in a negligent construction case in ruling the contractor had no duty to a user of the sidewalk?

FACTS

In the spring of 1988, the Stocktrail Ele- ' mentary School in Gillette, Wyoming, added four annex buildings to accommodate additional students for the 1988-1989 school year. In early August, 1988, the school district determined it would need to install sidewalks between the main building and the annex buildings to provide easier pedestrian access to the buildings.

On August 9, 1988, the school district requested bids on the project from four local contractors. At the bid meeting, the school district presented each contractor with one page of plans and specifications for the sidewalk. The specification sheet included requirements that the sidewalk have a strength of 4,000 pounds per square inch; that six-inch by six-inch wire mesh be imbedded in the concrete for reinforcement; that expansion joints be installed in the concrete to help prevent cracking; and that the contractor remove the existing grass sod before pouring the concrete. The plans included no provisions for drainage, and the contractors were instructed to follow the natural slope of the terrain.

On August 10, 1988, the school district awarded the bid to Norton, who submitted the low bid for the project. Norton completed the project by the August 22, 1988 deadline; and at that time representatives of the school district accepted the work, informing Norton they were pleased with his workmanship and that his work complied with the school district’s plans and specifications.

As designed and constructed, the sidewalk provided no drainage for the run-off from the natural sloping of the terrain. As a result, beginning in the first winter following the sidewalk’s construction, an ice problem developed on the sidewalk. Water would accumulate on the sidewalk and freeze there, creating hazardous walking conditions.

On January 23, 1990, while working as a custodian at the Stocktrail Elementary School, Pamela Lynch slipped and fell on an icy spot on a sidewalk at the school. She injured her left arm leading to nerve damage called Reflex Sympathy Dystrophy Syndrome. Pamela Lynch’s injuries have rendered her totally and permanently disabled, and she is unable to work.

For over a year after the school district accepted Norton’s work, school personnel, including Pamela Lynch, knew of the ice problem on the sidewalk. Pamela Lynch’s duties included shoveling the sidewalks and spreading salt and sand over the icy spots. At the school district’s direction, to conserve materials, Pamela Lynch did not spread salt and sand over icy spots for her own safety; she was instructed to use the salt and sand only when children were on the premises. Several school employees, including Pamela Lynch, had slipped and fallen on the ice at the spot where Pamela Lynch fell again on January 23, 1990.

Having received several complaints about the icy condition of the sidewalk, the school principal had, nearly one year before Pamela Lynch’s accident, submitted a work order to the school district maintenance department. The work order requested in[1097]*1097stallation of a drainage system to allow water to drain appropriately instead of flowing over the sidewalks and freezing. The drainage system was not installed until eight months after Pamela Lynch’s accident. Neither the school district nor school personnel from Stoektrail Elementary ever notified Norton of the drainage problem.

On December 30, 1991, Pamela Lynch filed a complaint against Norton, the contractor who built the sidewalk. Her complaint alleged that Norton’s negligence in failing to provide drainage for the sidewalk caused her fall and subsequent disability. On September 10, 1992, Norton moved for summary judgment contending he owed no duty to the Lynches, and following a hearing on October 16, 1992, the district court granted Norton’s motion for summary judgment.

STANDARD OF REVIEW

Summary judgment is proper when no genuine issues of material fact exist, and the prevailing party is entitled to judgment as a matter of law. Brown v. Avery, 850 P.2d 612, 614-15 (Wyo.1993). When reviewing the propriety of a grant of summary judgment, we review the record in the light most favorable to the party opposing the motion, giving that party all favorable inferences that can be drawn from the facts. Miller v. Campbell County, 854 P.2d 71, 75 (Wyo.1993); Abell v. Dewey, 847 P.2d 36, 39 (Wyo.1993). “Conclusory statements or mere opinions are insufficient, however, to satisfy an opposing party’s burden.” Boehm v. Cody Country Chamber of Commerce, 748 P.2d 704, 710 (Wyo.1987). “If no issue of material fact is found to exist, summary judgment is appropriate, even in a negligence case.” Brown, 850 P.2d at 614.

DISCUSSION

1. The Accepted Work Doctrine

Several jurisdictions have adopted the accepted work doctrine, applying it in cases where a contractor has completed a project, the owner has accepted the contractor’s work, and a third party has subsequently been injured by the condition of the work done. See e.g., Forbes v. Romo, 123 Ariz. 548, 601 P.2d 311, 314 (1979); Hale v. Depaoli, 33 Cal.2d 228, 201 P.2d 1, 2 (1948); Lindauer v. LDB Drainlaying, 38 Colo.App. 266, 555 P.2d 197, 199 (1976); Easterday v. Masiello, 518 So.2d 260, 261 (Fla.1988); Pennington v. Cecil N. Brown Co., 187 Ga.App. 621, 371 S.E.2d 106,107 (1988); Harrington v. LaBelle’s of Colorado, 235 Mont. 80, 765 P.2d 732, 733 (1988); Singleton v. Charlebois Constr. Co., 690 S.W.2d 845, 849 (Mo.App.1985); McKinstry v. Cass County, 228 Neb. 733, 424 N.W.2d 322, 328-29 (1988). The rule relieves an independent contractor of liability for injuries to third parties after the contractor has completed his work, and the owner or employer has accepted the work, regardless of the contractor’s negligence in completing the project. Pennington, 371 S.E.2d at 107; McKinstry, 424 N.W.2d at 328-29.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Oil City Appeal of: Best
Supreme Court of Pennsylvania, 2023
Wood v. CRST Expedited, Inc.
419 P.3d 503 (Wyoming Supreme Court, 2018)
Collard v. Vista Paving Corp.
2012 COA 208 (Colorado Court of Appeals, 2012)
Hoy v. Miller
2006 WY 147 (Wyoming Supreme Court, 2006)
Black v. William Insulation Co., Inc.
2006 WY 106 (Wyoming Supreme Court, 2006)
Black v. William Insulation Co.
2006 WY 123 (Wyoming Supreme Court, 2006)
Foote v. Simek
2006 WY 96 (Wyoming Supreme Court, 2006)
Killian v. Caza Drilling, Inc.
2006 WY 42 (Wyoming Supreme Court, 2006)
Peters v. Forster
804 N.E.2d 736 (Indiana Supreme Court, 2004)
Sisco v. Broce Manufacturing, Inc.
1 F. App'x 420 (Sixth Circuit, 2001)
Duncan v. Afton, Inc.
991 P.2d 739 (Wyoming Supreme Court, 1999)
Suneson v. Holloway Construction Co.
992 S.W.2d 79 (Supreme Court of Arkansas, 1999)
Pickens v. Tulsa Metropolitan Ministry
1997 OK 152 (Supreme Court of Oklahoma, 1997)
Turcq v. Shanahan
950 P.2d 47 (Wyoming Supreme Court, 1997)
Estate of Coleman v. Casper Concrete Co.
939 P.2d 233 (Wyoming Supreme Court, 1997)
Pullman v. Outzen
924 P.2d 416 (Wyoming Supreme Court, 1996)
Daily v. Bone
906 P.2d 1039 (Wyoming Supreme Court, 1995)
Duncan v. Town of Jackson
903 P.2d 548 (Wyoming Supreme Court, 1995)
Downen v. Sinclair Oil Corp.
887 P.2d 515 (Wyoming Supreme Court, 1994)
Treemont, Inc. v. Hawley
886 P.2d 589 (Wyoming Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
861 P.2d 1095, 1993 Wyo. LEXIS 166, 1993 WL 426358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lynch-v-norton-construction-inc-wyo-1993.