R. W. Dunteman Co. v. State

52 Ill. Ct. Cl. 33, 1999 Ill. Ct. Cl. LEXIS 65
CourtCourt of Claims of Illinois
DecidedJanuary 6, 1999
DocketNo. 88-CC-3663
StatusPublished

This text of 52 Ill. Ct. Cl. 33 (R. W. Dunteman Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. W. Dunteman Co. v. State, 52 Ill. Ct. Cl. 33, 1999 Ill. Ct. Cl. LEXIS 65 (Ill. Super. Ct. 1999).

Opinion

OPINION

Frederick, J.

This cause comes before the Court on Claimant, R. W. Dunteman Company’s, verified complaint alleging breach of contract by the Illinois Department of Transportation for its failure and refusal to pay R. W. Dunteman Company for topsoil furnished and placed at a construction site at the agreed upon unit price of $23 per square yard. Hereafter in this opinion, Claimant will be referred to as “Dunteman” and the Illinois Department of Transportation will be referred to as “IDOT.”

The topsoil was to be provided pursuant to contract no. 41432 in relation to the construction of road improvements near the City of Lisle (hereinafter referred to as the “Warrenville Road Project”). The verified complaint requests $496,505.60 in damages based upon its bid of a unit price of $23 for topsoil placement for 3,020 square yards of topsoil. The sum sought is now stated at $496,514.80.

Respondent, State of Illinois’ answer admits that the Contract Schedule of Prices indicates that Claimant bid a unit price of $23 on bid item no. 216003, estimated by the Department at 3,020 square yards, however, the project plans and cross-section plans which were part of the contract required 3,020 cubic yards. Respondent answers that the clear purpose and intent of contract no. 41423 was for Claimant to provide 3,020 cubic yards of topsoil.

The primary issue in this case is what quantity of topsoil was required by the contract between Claimant and Respondent.

The summaiy of quantities, the contract schedule of prices, and the proposal form to be used by contractors bidding indicate that 3,020 square yards were necessary for the Warrenville Road Project. The cross-sections contain drawings and measurements by which one could compute the topsoil needs to be 3,020 cubic yards or 27,180 square yards. The project actually required 3,020 cubic yards of topsoil.

Dunteman bid a unit price of $23 a square yard for the topsoil. Its bid on the entire project was $2,010,848.15. Dunteman has heretofore received $2,170,423.91 in payments, and if it collects the $496,514.80 claimed, will have received $2,666,938.71. The Department’s own three prebid estimates for the total project were: $2,684,422; $3,045,680; and $2,638,248.92.

The parties have stipulated that Dunteman actually delivered 24,286 square yards of topsoil and has been paid $62,063.20 for the topsoil. Dunteman seeks an additional $496,514.80 (21,587.60 sq. yds. x $23). The topsoil was placed between October 9 and October 21,1986.

There is evidence that Respondent’s agents had actual knowledge at the time the project was designed and at the time the plans and specifications and bid documents were being assembled that approximately 27,180 square yards of topsoil were needed. Although there is no direct evidence that unequivocally shows that Claimants agents had actual knowledge that the project needed approximately 27,180 square yards of topsoil, knowledge by Claimant that the project needed substantially more than 3.020 square yards is presumed because Claimants president refused to answer the direct question during the April 1996, hearing. Such knowledge may also be constructively attributed to Claimant because the cross-sections of the plans indicate that substantially more than 3.020 square yards of topsoil were required. The Court can find that as a matter of law both parties had actual and constructive knowledge that the project required approximately 27,180 square yards of topsoil. The important question of when such actual or constructive knowledge was obtained remains.

Procedural Background

This cause came before the Commissioner for a three-day trial commencing on March 28,199.4.

The Commissioner ruled prior to the trial that evidence of Dunteman’s losses on the Warrenville Road Project which were caused by fluctuations in the quantity of pay items other than topsoil were inadmissible. Dunteman indicated that it was prepared to prove that Dunteman had an aggregate loss on the Warrenville Road Project in the amount of $411,187.35 on pay items other than topsoil. Unit prices for pay items other than topsoil were not renegotiated despite quantity fluctuations which impacted the initial contract value by $504,913.45.

The Commissioner also ruled that evidence that would support Respondent’s affirmative defenses grounded upon equitable remedies would not be admissible.

On October 26,1995, the Court entered an order remanding this case for the purpose of hearing evidence on the issue of profit and loss on the overall contract, the fairness of Claimants bid, and Claimants losses caused by the fluctuations in the quantity of pay items other than topsoil. The order also specified that evidence in regard to equitable defenses should be heard by the Commissioner.

The Facts

On or about May 21, 1986, Dunteman contracted with IDOT to reconstruct and widen Warrenville Road, Route 53 and Middleton Avenue, and perform related work, in DuPage County, Illinois. Joint trial exhibits comprise contract documents between Dunteman and IDOT. Joint exhibit IE is the Departments agreement with the Village of Lisle (hereinafter referred to as “Lisle”) which employed Lisle to administer and supervise the Warrenville Road Project on behalf of IDOT. Joint exhibit IF is Lisles agreement with the consulting firm of BartonAschman & Associates (hereinafter referred to as “BartonAschman”) which employed Barton-Aschman to administer and supervise the Warrenville Road Project on behalf of Lisle, including the preparation of plans and the measurement and computation of pay items.

Advertisements in the form of bulletins were issued for the Warrenville Road Project approximately five weeks prior to the April 18, 1986, letting date. The bulletin consisted of an identification of the project, a brief description of the project, and an identification of the projects major pay items. Dunteman requested the contract documents and obtained joint exhibits 1A, IB and 1C approximately three weeks prior to the April 18, 1986, bid letting for the Warrenville Road Project.

The documents issued to Dunteman mandated the use of a proposal form for the submission of bids by interested contractors. Instructions to bidders were contained in the Standard Specifications for Road and Bridge Construction. Joint exhibit 1C, section 101.26 of the Standard Specifications prescribed the manner in which bidders were to submit their proposals as follows:

“Section 102.06 Preparation of the Proposal. The bidder shall submit his proposal on the form furnished by the Department. The proposal shall be executed properly, and bids shall be made for all items indicated in the proposal form, except that when alternate bids are asked, a bid on more than one alternate for each item is not required, unless otherwise provided. The bidder shall indicate, in figures, a unit price for each of the separate items called for in the proposal form; he shall show the products of the respective quantities and unit prices in the column provided for that purpose and the gross sum shown in the place indicated in the proposal form shall be the summation of said products.”

Section 103.01 of the Standard Specifications provided:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. A. Jones Construction Company v. The United States
395 F.2d 783 (Court of Claims, 1968)
Lyons Savings & Loan Ass'n v. Geode Co.
641 F. Supp. 1313 (N.D. Illinois, 1986)
Riverland Const. Co. v. Lombardo Contracting Co.
380 A.2d 1161 (New Jersey Superior Court App Division, 1977)
Frank Stamato & Co. v. City of New Brunswick
90 A.2d 34 (New Jersey Superior Court App Division, 1952)
J. & R. Electric Co. v. Edward P. Allison Co.
260 N.E.2d 755 (Appellate Court of Illinois, 1970)
R.W. Dunteman Co. v. Village of Lombard
666 N.E.2d 762 (Appellate Court of Illinois, 1996)
Martindell v. Lake Shore National Bank
154 N.E.2d 683 (Illinois Supreme Court, 1958)
Pielet Bros. Trading, Inc. v. Pollution Control Board
442 N.E.2d 1374 (Appellate Court of Illinois, 1982)
Pedrick v. Peoria & Eastern Railroad
229 N.E.2d 504 (Illinois Supreme Court, 1967)
Santucci Construction Co. v. County of Cook
315 N.E.2d 565 (Appellate Court of Illinois, 1974)
Casanas v. Nelson
489 N.E.2d 358 (Appellate Court of Illinois, 1986)
Scholes v. Ames
850 F. Supp. 707 (N.D. Illinois, 1994)
M.J. Oldenstedt Plumbing Co. v. K Mart Corp.
629 N.E.2d 214 (Appellate Court of Illinois, 1994)
Lenzi v. Morkin
469 N.E.2d 178 (Illinois Supreme Court, 1984)
Stone v. Those Certain Underwriters at Lloyds
401 N.E.2d 622 (Appellate Court of Illinois, 1980)
Armaniaco v. Cresskill
163 A.2d 379 (New Jersey Superior Court App Division, 1960)
Touhy v. Twentieth Century-Fox Film Corp.
387 N.E.2d 862 (Appellate Court of Illinois, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
52 Ill. Ct. Cl. 33, 1999 Ill. Ct. Cl. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-w-dunteman-co-v-state-ilclaimsct-1999.