Frank Stamato & Co. v. City of New Brunswick
This text of 90 A.2d 34 (Frank Stamato & Co. v. City of New Brunswick) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
FRANK STAMATO & CO., A CORPORATION, PLAINTIFF-RESPONDENT,
v.
CITY OF NEW BRUNSWICK, A MUNICIPAL CORPORATION, BOARD OF COMMISSIONERS OF THE CITY OF NEW BRUNSWICK, DEFENDANTS-RESPONDENTS, AND A. CESTONE COMPANY, A CORPORATION, DEFENDANT-APPELLANT.
Superior Court of New Jersey, Appellate Division.
*341 Before Judges McGEEHAN, JAYNE and GOLDMANN.
Mr. Peter P. Walsh, Jr., argued the cause for defendant-appellant (Messrs. Jamieson and Walsh, attorneys).
Mr. John T. Keefe argued the cause for plaintiff-respondent.
The opinion of the court was delivered by McGEEHAN, S.J.A.D.
The defendant City of New Brunswick advertised for bids for the construction of a 30-inch pipe line, approximately 14,000 feet in length, including pipe, excavation and other miscellaneous items. The defendant A. Cestone Company made its bid, in the total sum of $526,358.50, to furnish all materials and to perform all the required work according to the specifications. This was the lowest bid of the six bids made on the entire contract, as *342 awarded. The plaintiff, Frank Stamato & Co., submitted a bid in the total sum of $526,590, which was next to the lowest bid. On February 5, 1952, defendant City of New Brunswick passed a resolution accepting the bid of defendant A. Cestone Company.
Frank Stamato & Co. then brought suit in the Superior Court, Law Division, in which it sought a judgment setting aside the resolution of the City of New Brunswick awarding the contract to A. Cestone Company, and requiring the City of New Brunswick to award the contract to plaintiff. Defendants answered and both sides made motions for summary judgment on the pleadings and affidavits. The trial court entered summary judgment setting aside the resolution of February 5, 1952, and the defendant A. Cestone Company appeals.
The complaint alleged that A. Cestone Company had made an "unbalanced bid" on Items 7 and 8 of the specifications and demanded that the award of the contract to A. Cestone Company should be set aside because (1) Cestone's unbalanced bid violated the specifications which prohibited an obviously unbalanced bid, and (2) the city's failure to reject Cestone's unbalanced bid and its action in awarding the contract to Cestone "constituted unfair competition, partiality, privilege, and discrimination and plaintiff was not put on an equal footing or basis to compete with said defendants to bid said work according to said specifications."
The pertinent parts of the specifications provide:
"0.11 Basis for Comparing Bids
All bids will be compared on the basis of the Engineer's estimate of the quantities of work to be done. The estimated quantities shown in the proposal forms are not to be considered by the Contractor as actual quantities which may be required to complete the work, but solely to serve as a basis for comparing bids.
Bids which are obviously unbalanced, may be rejected."
"0.22 Borings
* * * * * * * *
In considering the results of the subsurface investigation thus presented, it shall be understood by the Contractor that the record, *343 as shown, represents the judgment of the observer as to the character of materials and subsurface conditions, and that the City, or its Engineer, do not guarantee that the character of the underground material will even approximately be as reported by the driller."
"Article VI Variations Between Proposal and Actual Quantities
The quantities of the various items of work to be done and materials to be furnished under this contract, which have been estimated as shown in the Schedule of Contract, Items attached hereto, are approximate only and for the purpose of comparing, on a uniform basis, the bids offered for the work under this contract; and the Owner is not to be held responsible that any of the estimated quantities shall be found even approximately correct in the construction of the work; and the Contractor shall make no claim for anticipated profits, or for loss of profit, because of a difference between the estimated quantities of the various items of work stated in the proposal, and the quantities actually performed, or materials actually delivered."
"Item 7 Additional Price for Rock Excavation
5000 Cu. Yds. @ $ ____ per Cu. Yd. $ ____ _________________________________________ (Write Unit Price) Item 8 For Timber Sheeting Left in Place 50 M Ft. B.M. @ $ ____ per M Ft. B.M. $ ____ ____________________________________________ (Write Unit Price)""7.00 Work Included and Payment
Where material excavated under Items 1, 5 or 6 is rock, an additional or excess price per cubic yard will be paid under Item 7.
7.01 Definition of Rock Excavation (Item 7)
Rock excavation shall comprise such ledge rock as in the opinion of the Engineer requires blasting, and boulders of one-half cubic yard or more in volume.
All other materials, however hard, stiff, and compact, including soft and disintegrated rock, which can be removed without the aid of explosives, shall be classed and paid for as earth.
8.00 Item 8 For Timber Sheeting Kept in Place
When, in the opinion of the Engineer, timber sheeting and bracing, furnished and placed under Items 1, 5 or 6 should be left in place to avoid undermining, or otherwise endangering the work or adjacent structures, payment will be made under this Item for such timber sheeting and bracing as is ordered left in place, at the price bid per thousand board measure under this Item."
*344 The bids submitted on Items 7 and 8 were as follows:
Item 7 Rock Excavation
Unit Price Bid on Estimated
Per Cu. Yd. 5000 Cu. Yds.
A. Cestone Company .................... $.01 $50.00
Frank Stamato & Co. ................... 5.00 2,500.00
Bidder M .............................. 3.00 15,000.00
Bidder A .............................. 20.00 100,000.00
Bidder L .............................. 1.00 5,000.00
Bidder V .............................. 10.00 50,000.00
Item 8 Timber Sheeting Left in Place
Unit Price Bid on Estimated
Per M ft. B.M. 50 M Ft. B.M.
A. Cestone Company ................... .01 .50
Frank Stamato & Co. .................. 20.00 10,000.00
Bidder M ............................. .01 .50
Bidder A ............................. 3.50 17,500.00
Bidder L ............................. 50.00 25,000.00
Bidder V ............................. .01 .50
An unbalanced bid comprehends a bid based on nominal prices for some work and enhanced prices for other work. The mere fact that a bidder has submitted an unbalanced bid, does not automatically operate to invalidate an award of the contract to such bidder.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
90 A.2d 34, 20 N.J. Super. 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-stamato-co-v-city-of-new-brunswick-njsuperctappdiv-1952.