Boenning v. Brick Tp. Municipal Utilities Auth.

374 A.2d 1214, 150 N.J. Super. 32
CourtNew Jersey Superior Court Appellate Division
DecidedMay 13, 1977
StatusPublished
Cited by4 cases

This text of 374 A.2d 1214 (Boenning v. Brick Tp. Municipal Utilities Auth.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boenning v. Brick Tp. Municipal Utilities Auth., 374 A.2d 1214, 150 N.J. Super. 32 (N.J. Ct. App. 1977).

Opinion

150 N.J. Super. 32 (1977)
374 A.2d 1214

HENRY O. BOENNING, PLAINTIFF-RESPONDENT,
v.
THE BRICK TOWNSHIP MUNICIPAL UTILITIES AUTHORITY, DEFENDANT-APPELLANT.

Superior Court of New Jersey, Appellate Division.

Argued January 4, 1977.
Decided May 13, 1977.

*33 Before Judges HALPERN, BOTTER and DAVIDSON.

Mr. Charles E. Starkey argued the cause for appellant (Messrs. Starkey, Turnbach, White & Kelly, attorneys).

Mr. Edward Feurey argued the cause for respondent (Messrs. Paschon & Feurey, attorneys).

Messrs. Rosenberg & Waldman filed a brief for amicus curiae Utility Contractors Association of New Jersey, Inc. (Mr. Richard K. Rosenberg on the brief).

Messrs. Hiering, Grasso, Gelzer & Kelaher filed a brief for amicus curiae Ocean County Sewerage Authority (Mr. Richard H. Woods on the brief).

The opinion of the court was delivered by BOTTER, J.A.D.

The sole issue on this appeal is whether the Brick Township Municipal Utilities Authority (Authority) can legally establish minimum unit prices to be bid for certain items of work and materials of an indeterminate quantity which may be required in execution of contracts for the installation of a municipal sewerage collection system. The concepts involved are referred to as "unbalanced bids" and "pennying," that is, bidding nominal sums for certain items in public (and private) construction contracts. See Armaniaco v. Cresskill, 62 N.J. Super. 476 (App. Div. 1960); Frank Stamato & Co. v. New Brunswick, 20 N.J. Super. 340 (App. Div. 1952); Corbiscello Brothers, Inc. v. Fort Lee, 93 N.J. Super. 374 (Law Div. 1967); Phifer v. Bayonne, 105 N.J.L. 524 (Sup. Ct. 1929); Nelson v. New York City Mayor, 131 N.Y. 4, 29 N.E. 814 (Ct. App. 1892); New York Mayor v. Brady, 115 N.Y. 599, 22 N.E. 237 (Ct. App. 1889); Reilly v. *34 New York City Mayor, 111 N.Y. 473, 18 N.E. 623 (Ct. App. 1888); In Re Anderson, 109 N.Y. 554, 17 N.E. 209 (Ct. App. 1888); Abbett, Engineering Contracts and Specifications (4 ed. 1963) at 160-162; Cohen, Public Construction Contracts and the Law 53-56 (1961); Dunham & Young, Contracts, Specifications, and Law for Engineers (2 ed. 1971), at 262-264 and 271-272.

This case involves the solicitation of bids on Contracts S-5 and S-6 for the construction of a portion of the municipal sewerage system. The action was instituted in September 1975 by a property owner of Brick Township, Ocean County. The complaint asserted a violation of the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq. An order to show cause was issued with restraints to prevent the Authority from opening bids for the work and to allow contractors to withdraw bids previously submitted. After a hearing at which defendant's two expert witnesses testified, the trial judge held that fixing minimum unit prices that must be bid for certain items of work was inconsistent with the statutory goal of obtaining the lowest responsible bidder and was, therefore, illegal. A judgment was entered declaring the use of minimum price requirements unlawful as against public policy, restraining defendant from doing so in the future and allowing all bidders to withdraw their bids.

Although an appeal was filed, defendant was forced to readvertise and award the contracts in compliance with the trial judge's order because of time limits involved in the grant of Federal funding of the project.[1]

The Authority engaged the services of Charles J. Kupper, Inc. (Kupper) as consulting engineers for the design of the sewerage collection system and the preparation of *35 plans, specifications and contract documents. This firm was involved in the installation of sewers in Brick Township since 1963 or 1964. The bidding and contract documents prepared by Kupper required contractors to bid at least certain fixed or minimum unit prices for so-called "discretionary" items.

Discretionary items are distinguished from "certain" items by the fact that the nature and extent of "certain" items can be measured by reference to plans and specifications. An example of a "certain" item is sewer pipe, whose size and length are shown on the plans.

Discretionary items are types of work and material which cannot be accurately measured or ascertained, in terms of quantity or need, in advance of the work actually being performed. Here, these fell generally into two categories, one pertaining to underground work and the other to restoration work. The underground work entailed laying sewer pipe in trenches ranging generally from 6 to 20 feet deep. Although interval borings were used in designing the project, it was impossible to determine all soil conditions that would be encountered. Some soil conditions might require the use of stone and select material or concrete cradles to support the sewer pipe. Also, timber or steel sheeting left in place might be needed to shore up the trenches and protect the completed work. Some uncertainty also existed in regard to the extent of restoration work, such as asphalt paving or landscaping, that would be required after the sewers had been installed.

The term "discretionary" is used because the final determination of need must be made by the engineer on the site while the work is being performed. But, for the purpose of comparing competing bids, the engineers must estimate in advance the kind and extent of these discretionary items. They do so as best they can based upon the borings, their knowledge of local conditions and their experience in such projects.

*36 During the course of the work the judgment of the engineer, for example, as to the stability of soil conditions, may be questioned. A contractor who has "pennied" these indeterminate, discretionary items will be disinclined to accept the engineer's orders. That contractor will not want to incur the expense or loss in doing this work. As a result, according to the testimony, disputes will arise and will interfere with timely completion of the project.

Nevertheless, it is common practice in bidding for public and private utility contracts for contractors to bid a nominal sum or a penny for units of discretionary work. The Armaniaco case, supra 62 N.J. Super. at 480, shows the bid of one cent (or a total of $4.17) for units of timber sheeting left in place, whereas a second contractor bid $200 per unit for the same item, and, based on estimates, his total bid was $83,400 for that discretionary item. Similar examples are shown in other cases cited above.

How can a contractor bid one cent, or $4.17 in toto, for the estimated cost of this item while another estimates the cost to be $200 per unit and $83,400 in toto? One answer given in the testimony is that some contractors will gamble on this item. Another explanation may be a contractor's superior knowledge that the engineer has overestimated the need for such items. In such a case the public may not benefit, however, for the contractor who "pennies" the item and gains a competitive advantage can afford to increase his bid on "certain" items and thus obtain a windfall on those items. Another answer shown by the cases is collusion or fraud between the contractor and the engineer whose discretion will be invoked. Nelson v. New York City Mayor, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
374 A.2d 1214, 150 N.J. Super. 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boenning-v-brick-tp-municipal-utilities-auth-njsuperctappdiv-1977.